McManus v. Commissioner of Environmental Protection

623 A.2d 1041, 31 Conn. App. 105, 1993 Conn. App. LEXIS 198
CourtConnecticut Appellate Court
DecidedApril 27, 1993
Docket11343
StatusPublished
Cited by2 cases

This text of 623 A.2d 1041 (McManus v. Commissioner of Environmental Protection) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McManus v. Commissioner of Environmental Protection, 623 A.2d 1041, 31 Conn. App. 105, 1993 Conn. App. LEXIS 198 (Colo. Ct. App. 1993).

Opinion

Dupont, C. J.

The plaintiffs1 appeal from a judgment of the trial court upholding an order of the commissioner of the department of environmental protection (DEP). The order required the plaintiffs to remove fill that had been placed around a farm pond that had been excavated on wetlands on their property and to restore the wetlands surrounding the pond. The dispositive issue on appeal is one that has not been resolved by our appellate courts. It is whether the DEP could prop[107]*107erly issue an administrative order under General Statutes § 22a-44 (a) three years after having originally brought a civil action pursuant to General Statutes § 22a-44 (b), which action was still pending at the time of the order. We hold that the DEP cannot.2

The following facts are undisputed by the parties. In April, 1985, the named plaintiff contacted the DEP about excavating for a farm pond on his property. A DEP environmental analyst made a preliminary on-site determination that the proposed farm pond was not likely to have a significant adverse impact and was “no big deal.” In September, 1985, the DEP informed the plaintiffs that their proposed farm pond could be excavated without a permit and that they were entitled to an exemption under General Statutes § 22a-40 (a) (1), but creation of a “pasture or other fast land in wetlands adjacent to the pond [was] not exempt.” Shortly thereafter, the plaintiffs filed an application for a permit, which they withdrew on November 6, 1985.

In the spring of 1987, the plaintiffs excavated a farm pond on their property without a permit from the DEP. On May 4, 1987, the DEP filed a civil action pursuant to General Statutes § 22a-44 (b) against the plaintiffs seeking the removal of the fill from the wetlands adjacent to the farm pond, the restoration of the wetlands to their prior condition and the payment of a civil penalty and various other costs. On March 6, 1990, the DEP issued an administrative order directing the same remedy as was sought in the civil claim, except for the penalty and costs.3 Two days later, after almost three [108]*108years of extensive pleadings, motions and depositions, the DEP withdrew its civil claim against the plaintiffs, leaving its administrative order extant.

Pursuant to General Statutes § 22a-43, the plaintiffs appealed from the administrative order. After a hearing was held, a DEP administrative hearing officer issued a “Final Decision and Order” that upheld the administrative order. The plaintiffs then appealed to the Superior Court, which upheld the decision of the DEP administrative hearing officer. This appeal followed.

The dispositive issue here revolves around the relationship and interaction between subsections (a) and (b) of General Statutes § 22a-44.4 The plaintiffs claim [109]*109that because the defendant originally brought a civil action against the plaintiffs pursuant to § 22a-44 (b), litigated it for three years and then withdrew it, the defendant could not then issue an administrative order pursuant to § 22a-44 (a). The plaintiffs contend that allowing the DEP, after three years of litigation, to effect the same remedy by administrative order as was sought in the civil action is highly inequitable and oppressive. The DEP, however, claims that the subsections allow alternative remedies, are not exclusive, and the use of one does not bar the use or substitution of the other.

General Statutes § 22a-44 provides two different statutory remedies for dealing with a violation of General Statutes §§ 22a-36 through 22a-45, the Inland Wetlands and Watercourses Act. Conservation Commission v. Price, 193 Conn. 414, 421, 479 A.2d 187 (1984). Subsection (a) allows an inland wetlands agency or its agent to issue orders directing a violator of the act “to cease immediately such activity or to correct such [violations].” Subsection (b) provides for the assessment of a civil penalty for violations of the act and gives the Superior Court jurisdiction “to restrain a continuing violation ... to issue orders directing that the vio[110]*110lation be corrected or removed and to assess civil penalties . . . .” Subsection (b) also provides for the awarding of all costs, fees and expenses in connection with such action, including reasonable attorney’s fees.

“ ‘[T]he construction and interpretation of a statute is a question of law for the courts . . . particularly where . . . the statute has not previously been subjected to judicial scrutiny or time-tested agency interpretations.’ ” Jutkowitz v. Department of Health Services, 220 Conn. 86, 106, 596 A.2d 374 (1991); New Haven v. Freedom of Information Commission, 205 Conn. 767, 773-74, 535 A.2d 1297 (1988). In construing a statute, our objective is to ascertain and give effect to the apparent intent of the legislature. Rose v. Freedom of Information Commission, 221 Conn. 217, 225, 602 A.2d 1019 (1992); Cummings v. Twin Mfg., Inc., 29 Conn. App. 249, 254, 614 A.2d 857 (1992). We approach this objective by first looking to the language of the statute. United Illuminating Co. v. Groppo, 220 Conn. 749, 756, 601 A.2d 1005 (1992); Cummings v. Twin Mfg., Inc., supra. If the language of the statute is clear and unambiguous, we need not go any further. Rose v. Freedom of Information Commission, supra; Cummings v. Twin Mfg., Inc., supra. “[N]o part of a legislative enactment is to be treated as insignificant or unnecessary, and there is a presumption of purpose behind every sentence, clause or phrase . . . .’’(Citations omitted; internal quotation marks omitted.) Peck v. Jacquemin, 196 Conn. 53, 66, 491 A.2d 1043 (1985).

Subsection (a) specifically states that “[t]he issuance of an order pursuant to this section shall not delay or bar an action pursuant to subsection (b) of this section.” It is clear from this language that the appropriate inland wetlands agency can issue an order under (a) and also pursue a civil penalty and a court order for noncompliance with an administrative order under subsection (b) either simultaneously or at a later date. [111]*111Subsection (b), however, does not include similar language. If the legislature had intended that administrative actions brought under subsection (a) are not barred or delayed by a prior action brought under subsection (b), it would have included the language found in subsection (a) in subsection (b). See Red Hill Coalition, Inc. v. Conservation Commission, 212 Conn. 710, 726, 563 A.2d 1339 (1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McManus v. Commissioner of Environmental Protection
632 A.2d 692 (Supreme Court of Connecticut, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
623 A.2d 1041, 31 Conn. App. 105, 1993 Conn. App. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmanus-v-commissioner-of-environmental-protection-connappct-1993.