MCI WorldCom Network Services, Inc. v. OSP Consultants, Inc.

585 S.E.2d 540, 266 Va. 389, 2003 Va. LEXIS 78
CourtSupreme Court of Virginia
DecidedSeptember 12, 2003
DocketRecord 030312
StatusPublished
Cited by10 cases

This text of 585 S.E.2d 540 (MCI WorldCom Network Services, Inc. v. OSP Consultants, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI WorldCom Network Services, Inc. v. OSP Consultants, Inc., 585 S.E.2d 540, 266 Va. 389, 2003 Va. LEXIS 78 (Va. 2003).

Opinion

SENIOR JUSTICE STEPHENSON

delivered the opinion of the Court.

Pursuant to Article VI, Section 1 of the Constitution of Virginia and Rule 5:42, the United States Court of Appeals for the Fourth Circuit (the Fourth Circuit), by an order entered February 10, 2003, certified to this Court the following question:

Is a telecommunications services carrier entitled to damages for the loss of use of a fiber-optic cable damaged by a defendant when the carrier intended to have the full capacity of the damaged cable available for its use should the need have arisen, but the carrier was able to accommodate within its own network the telecommunications traffic carried by the damaged cable and the carrier presented no evidence that it suffered loss of revenue or other damages during the time that the cable was unavailable?

*391 I

MCI WorldCom Network Services, Incorporated (MWNS) provides telecommunications services through underground fiber-optic cables. On March 27, 2000, OSP Consultants, Incorporated (OSP) severed one of MWNS’s underground fiber-optic cables while excavating near Centreville, Virginia. Consequently, MWNS sued OSP in tort, based upon theories of negligence and trespass, seeking repair costs of $32,509.33 and $454,484.10 for loss of use of the severed cable.

OSP conceded liability, and, in a subsequent bench trial in the United States District Court for the Eastern District of Virginia, the district court awarded MWNS the repair costs of $32,509.33. The district court, however, refused to award damages for loss of use, and MWNS appealed that ruling to the Fourth Circuit.

On February 10, 2003, the Fourth Circuit certified the above-quoted question. By an order entered March 6, 2003, we accepted the question.

II

The relevant facts, as set forth in the certification order, are not in dispute. The severed underground fiber-optic cable was one of MWNS’s primary transmission routes for telecommunications traffic along the East Coast. The cable carried voice and data traffic as well as high-speed data transmission for banks and credit card companies. Like other telecommunications providers, MWNS has built into its network excess capacity to allow for varying levels of traffic and to permit traffic to be rerouted, and service maintained, in the event of an outage in one part of its network.

In the telecommunications industry, a “DS-3” is a standard unit of capacity, and one DS-3 represents 672 voice circuits or individual telephone calls. The cable severed by OSP had a total capacity of 960 DS-3s. The number of active DS-3s varies from moment to moment, depending on the volume of traffic. When the cable was severed, 222 DS-3s were active, and more than 3000 voice calls were lost or blocked, as was some amount of private-line and Internet traffic. MWNS, however, was able to quickly reroute the traffic carried by the severed cable because of the excess capacity built into its network. A computer effected this rerouting automatically.

On the day that OSP severed MWNS’s cable near Centreville, MWNS suffered another cable break in Pennsylvania. MWNS ordinarily could have used the excess capacity in the Centreville cable to *392 handle the traffic rerouted from the Pennsylvania cable. Nothing in the record, however, suggests that MWNS had any difficulty rerouting within its network the traffic from both broken cables.

Although traffic was not fully restored to the Centreville cable for more than thirteen hours after it was severed, MWNS sought recovery for only seven-and-one-half hours of lost use of the cables; i.e., four-and-one-half hours to make the physical repairs to the cable and three hours to “normalize” the traffic that had been re-routed. MWNS arrived at its loss-of-use damages by consulting the tariff rates filed by competitors Sprint and AT&T to determine the per-hour cost of procuring substitute DS-3s. Sprint’s tariff rate, the lower of the two, for one DS-3 was $45,448.41 for one month. Thus, MWNS calculated that replacing 960 DS-3s, or the entire capacity of the severed cable, for one month would cost $43,630,473.60 and that replacing 960 DS-3s for one hour would cost $60,597.88. MWNS then multiplied the hourly rate by the seven-and-one-half hours the cable was unavailable and arrived at $454,484.10 in loss-of-use damages. MWNS did not attempt to assign any economic value to the traffic that was lost at the moment the cable was severed, and it presented no evidence that it lost customers or revenue as a result.

Ill

MWNS contends that it is entitled to loss-of-use damages measured by the cost of replacing 960 DS-3s for seven-and-one-half hours even though it was able to accommodate within its own network all the telecommunications traffic carried by the damaged cable. In other words, MWNS seeks to recover the reasonable cost of obtaining replacement property even though it did not, in fact, obtain a replacement.

OSP concedes that loss-of-use damages may be recovered in appropriate cases. OSP contends, however, that MWNS suffered no damages from the loss of the use of its cable because it had within its own network the capacity to handle all the traffic carried by the damaged cable. OSP asserts that to award MWNS loss-of-use damages under the circumstances would “bestow a massive and unfair windfall.”

We have recognized that loss of use is a compensable element of damages for the detention of personal property. See, e.g., Vines v. Branch, 244 Va. 185, 190, 418 S.E.2d 890, 894 (1992); Shearer v. Taylor, 106 Va. 26, 28, 55 S.E. 7, 8 (1906). In Shearer, the plaintiff had her furniture in storage under a 12-month storage contract. While *393 the furniture was in storage, a creditor of the plaintiff had a distress warrant levied on the furniture. The furniture remained in storage for approximately six months after being released from the levy. The plaintiff sued the creditor, claiming damages for the wrongful levy, including damages for the loss of use of the furniture during the time it was held under the warrant. The jury returned a verdict in favor of the plaintiff. 106 Va. at 27-29, 55 S.E. at 7-8.

At trial, the jury was instructed “to allow a fair rental value for the property during the time it was held under levy, considering the character of the property levied on.” Id. at 28, 55 S.E. at 8. The jury was further instructed that “the measure of damage in this case is: (1) A fair rental value of the property levied on for the period that same was held under the distress warrant, not exceeding twelve months; (2) the damage to the same occasioned by the storage during the same period.” Id.

We reversed the judgment and remanded the case for a new trial, holding that the jury was improperly instructed about the measure of damages that plaintiff could recover. We acknowledged the general principle that the value of the use of property during an unlawful detention is an appropriate element of damages. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Level 3 Communications, LLC v. TNT Construction, Inc.
220 F. Supp. 3d 812 (W.D. Kentucky, 2016)
Matulenas v. Venture Supply
86 Va. Cir. 290 (Norfolk County Circuit Court, 2013)
MCI Communications Services, Inc. v. CMES, Inc.
728 S.E.2d 649 (Supreme Court of Georgia, 2012)
MCI Communication Servs. v. Barrett Paving Materials, Inc.
2012 Ohio 1700 (Ohio Court of Appeals, 2012)
PurCo Fleet Services, Inc. v. Koenig
240 P.3d 435 (Colorado Court of Appeals, 2010)
MCI Worldcom Network Services, Inc. v. Mastec, Inc.
995 So. 2d 221 (Supreme Court of Florida, 2008)
MCI, LLC v. Patriot Engineering & Environmental, Inc.
487 F. Supp. 2d 1029 (S.D. Indiana, 2007)
MCI Worldcom Network Services, Inc. v. W.M. Brode Co.
413 F. Supp. 2d 868 (N.D. Ohio, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
585 S.E.2d 540, 266 Va. 389, 2003 Va. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-worldcom-network-services-inc-v-osp-consultants-inc-va-2003.