McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.

193 P.3d 9, 345 Or. 272, 2008 Ore. LEXIS 672
CourtOregon Supreme Court
DecidedSeptember 18, 2008
DocketCC 01-2126; CA A125459; SC S054626
StatusPublished
Cited by25 cases

This text of 193 P.3d 9 (McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co., 193 P.3d 9, 345 Or. 272, 2008 Ore. LEXIS 672 (Or. 2008).

Opinion

*275 KISTLER, J.

Plaintiff brought this action, alleging that defendants had failed to pay for work that plaintiff had done on a construction project. Defendants denied that allegation and alleged, as an affirmative defense, that plaintiff had agreed to release its claims against defendants in return for defendants paying plaintiff $896,000. Defendants also counterclaimed for specific performance of that settlement agreement. On defendants’ motion, the trial court bifurcated the trial and agreed to try defendants’ counterclaim for specific performance of the settlement agreement before trying plaintiffs claims for breach of the construction contract.

The primary question that this case presents is whether plaintiff has a state constitutional right to a jury trial on the factual issues that defendant’s counterclaim raised. The trial court concluded that plaintiff had no such right and, sitting as the trier of fact, found that plaintiff had accepted defendants’ offer to settle its claims and entered judgment accordingly. A divided Court of Appeals affirmed the trial court’s judgment. McDowell Welding & Pipefitting v. US Gypsum Co., 209 Or App 441, 149 P3d 173 (2006). We allowed plaintiffs petition for review and now affirm the Court of Appeals decision on plaintiffs jury trial claim but reverse its decision on a subsidiary issue regarding prejudgment interest.

The relevant facts can be summarized briefly. Defendant United States Gypsum (US Gypsum) was constructing a new plant in Columbia County. Defendant BE&K Construction Co. (BE&K) was the general contractor on that project. BE&K subcontracted with plaintiff to perform work on the project. During construction, defendants asked plaintiff to perform additional tasks, over and above plaintiffs contractual obligations, and defendants promised to pay plaintiff for doing so. After plaintiff completed its work on the project, the parties disagreed over the amount that defendants owed for the additional work that plaintiff had performed.

Plaintiff filed this action against defendants, alleging breach of contract and related claims. All of plaintiffs *276 claims arose out of the modification to the construction contract. BE&K’s answer included an affirmative defense captioned “Compromise and Settlement,” alleging that plaintiff had agreed to settle its claims against defendants. Specifically, defendants alleged:

“112.
“On February 22, 2001, Dan McDowell, President and owner of [plaintiff], agreed to a settlement of all the claims against BE&K and US Gypsum in connection with the US Gypsum construction project.
“113.
“The settlement provided for US Gypsum to pay [plaintiff] the total of $896,000, including direct payments to [plaintiffs] unpaid subcontractors and suppliers, in exchange for a release of the claims [that plaintiff] is now pursuing against BE&K.
“114.
“The agreement reached between the parties on February 22, 2001 was a compromise of [plaintiffs] disputed and unliquidated claims against US Gypsum and BE&K.”

BE&K also included a counterclaim captioned “Declaratory Judgment and Specific Performance of Settlement Agreement.” That counterclaim stated: “As alleged above, on February 22, 2001, the parties reached a compromise and settlement of [plaintiffs] claims.”

BE&K filed a motion asking the trial court to bifurcate the proceedings and try its counterclaim before trying plaintiffs claims against it. BE&K reasoned that, if the trial court found that plaintiff had agreed to settle its claims, that determination would obviate the need to try plaintiffs breach of contract claims against BE&K and US Gypsum. BE&K also argued that, because its counterclaim sought specific performance, the court rather than a jury should resolve the factual issues that the counterclaim raised. The trial court granted BE&K’s motion.

After the trial court granted BE&K’s motion, plaintiff filed a demand for a jury trial, which BE&K moved to *277 strike. BE&K reasoned that, because its counterclaim was equitable, plaintiff had no right to a jury trial on the counterclaim. The trial court granted BE&K’s motion to strike plaintiffs jury trial demand and, sitting as the trier of fact, found that plaintiff had accepted defendants’ offer to settle its claims in return for defendants’ promise to pay plaintiff $800,000. 1

Based on its resolution of defendants’ counterclaim, 2 the trial court entered a limited judgment directing defendants to tender $800,000 to the court clerk and directing plaintiff, after defendants tendered that sum, to execute releases of its claims against defendants. After the trial court entered the limited judgment, defendants tendered $800,000 to the court clerk and then moved for summary judgment on plaintiffs claims against them. The trial court granted defendants’ motion and entered a general judgment that dismissed plaintiffs claims with prejudice.

On appeal, plaintiff argued, among other things, that the trial court had erred in denying its jury demand on the question whether it had accepted defendants’ settlement offer. As noted, a divided Court of Appeals affirmed. The majority started from the proposition that plaintiff had not assigned error to the trial court’s ruling bifurcating the trial and agreeing to try defendants’ counterclaim first. McDowell Welding & Pipefitting, 209 Or App at 445-46. Rather, plaintiff had assigned error only to the trial court’s ruling striking plaintiffs demand for a jury trial. Id. 3 On that issue, the majority explained that this court and the Court of Appeals *278 have held that there is no constitutional right to a jury trial on a claim for specific performance of a settlement agreement. Id. at 447. It followed, the majority reasoned, that the trial court had correctly denied plaintiffs jury demand for a trial on that claim. Id.

The dissent took a different tack. The dissent did not disagree that plaintiff had no right to a jury trial on defendants’ counterclaim. The dissent, however, would have held that plaintiff had a right to a jury trial on defendants’ affirmative defense; that is, the dissent concluded that defendants’ affirmative defense would have been legal rather than equitable when the Oregon Constitution was adopted. 4 Id. at 473 (Armstrong, J., dissenting). Following the reasoning in Beacon Theatres, Inc. v. Westover, 359 US 500, 79 S Ct 948, 3 L Ed 2d 988 (1959), the dissent would have held that, when a legal claim (defendants’ affirmative defense) and an equitable claim (defendants’ counterclaim) share common factual issues, Article I, section 17, of the Oregon Constitution requires courts to try the legal claim before the equitable one.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brookings Property, LLC v. Shigley
Court of Appeals of Oregon, 2026
Boldt v. Brookdale Senior Living Communities
340 Or. App. 333 (Court of Appeals of Oregon, 2025)
Rivera v. Perlo Construction, LLC
336 Or. App. 307 (Court of Appeals of Oregon, 2024)
Deep Photonics Corp. v. LaChapelle
491 P.3d 60 (Oregon Supreme Court, 2021)
Precision Strip, Inc. v. Dircksen
2020 Ohio 6668 (Ohio Court of Appeals, 2020)
State/Klamath County v. Hershey
466 P.3d 987 (Court of Appeals of Oregon, 2020)
Deep Photonics Corp. v. LaChapelle
466 P.3d 660 (Court of Appeals of Oregon, 2020)
Horton v. OHSU
Oregon Supreme Court, 2016
Horton v. Oregon Health & Science University
376 P.3d 998 (Oregon Supreme Court, 2016)
McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.
320 P.3d 579 (Court of Appeals of Oregon, 2014)
Rucker v. Rucker
307 P.3d 498 (Court of Appeals of Oregon, 2013)
Strawn v. Farmers Insurance
297 P.3d 439 (Oregon Supreme Court, 2013)
M. K. F. v. Miramontes
287 P.3d 1045 (Oregon Supreme Court, 2012)
Kollman v. Cell Tech International, Inc.
279 P.3d 324 (Court of Appeals of Oregon, 2012)
Ackerman v. Sobol Family Partnership, LLP
4 A.3d 288 (Supreme Court of Connecticut, 2010)
Foster v. MIRAMONTES
236 P.3d 782 (Court of Appeals of Oregon, 2010)
Malan v. Tipton
222 P.3d 754 (Court of Appeals of Oregon, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
193 P.3d 9, 345 Or. 272, 2008 Ore. LEXIS 672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdowell-welding-pipefitting-inc-v-united-states-gypsum-co-or-2008.