McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.

320 P.3d 579, 260 Or. App. 589, 2014 WL 255519, 2014 Ore. App. LEXIS 94
CourtCourt of Appeals of Oregon
DecidedJanuary 23, 2014
Docket012126; A149831
StatusPublished
Cited by14 cases

This text of 320 P.3d 579 (McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co., 320 P.3d 579, 260 Or. App. 589, 2014 WL 255519, 2014 Ore. App. LEXIS 94 (Or. Ct. App. 2014).

Opinion

ORTEGA, P. J.

Plaintiff, McDowell Welding & Pipefitting, Inc., appeals a supplemental judgment entered by the trial court following a remand from the Oregon Supreme Court for the trial court to determine the amount of prejudgment interest to which plaintiff was entitled. See McDowell Welding & Pipefitting v. US Gypsum Co., 345 Or 272, 290-91, 193 P3d 9 (2008). On appeal, plaintiff contends that the trial court incorrectly ruled that plaintiff was entitled to only one day of prejudgment interest. Defendants BE&K Construction Co., Inc. (BE&K) and United States Gypsum Company (U.S. Gypsum) cross-appeal, asserting that the trial court erred in (1) awarding plaintiff prejudgment interest at the statutory rate; (2) not conditioning the payment of net settlement proceeds to plaintiff on execution of a settlement release; (3) reducing U.S. Gypsum’s attorney fee award; and (4) reducing BE &K’s attorney fee award. We reject without discussion defendants’ contentions on cross-appeal and, on appeal, reverse and remand.

The general background facts, some of which are set forth in the Supreme Court’s decision, are as follows. This case arose out of a construction project in Columbia County. U.S. Gypsum was constructing a new plant and hired BE&K as the general contractor on the project. 345 Or at 275. “BE&K subcontracted with plaintiff to perform work on the project. During construction, defendants asked plaintiff to perform additional tasks, over and above plaintiffs contractual obligations, and defendants promised to pay plaintiff for doing so.” Id. Plaintiff completed its work on the construction project, and a disagreement arose among the parties “over the amount that defendants owed for the additional work that plaintiff had performed.” Id.

On February 22, 2001, defendants made an oral offer to settle the parties’ dispute for $800,000 and plaintiff accepted that offer. “The parties also agreed that, to the extent that plaintiff owed money to its suppliers, defendants would issue joint checks to plaintiff and its suppliers out of the $800,000 payment.” Id. at 287. As part of those discussions, defendants “asked plaintiff to provide them with the suppliers’ names and the amount that plaintiff owed each [592]*592supplier so that defendants could prepare the joint checks.” Id. One day after the parties reached that agreement, BE & K sent plaintiff a document, dated February 23, 2001, entitled “Modification to Subcontract Agreement” (Modification 29). Modification 29 provides as follows:

“Upon your acceptance hereof, this letter will constitute a Modification of the Subcontract previously entered into, dated August 7, 2000.
“In accordance with the provisions of Article III of the Subcontract Agreement, you are directed to:
“This is a final settlement to [plaintiff] on both contracts at the U.S. Gypsum plant site in Rainier, Oregon S0063 and S0075. S0063 covers the Auxiliary Package and S0075 covers the Pipe and Instrumentation Installation. This is a one time final settlement.
“Increase $800,000.00
“Accordingly, the price of your Subcontract is hereby 1. [ ] left unchanged, 2. [x] increased, 3. [ ] decreased; by $800,000. In all other respects, however, your Subcontract shall be and remain the same.
“If the foregoing Modification is satisfactory to you, please note your acceptance thereof in the space provided below on all copies hereof. Please return all signed copies to us.”

After the signature block for BE&K’s representative, the document states “Effective as of the date stated above, the foregoing Modification is hereby accepted by Subcontractor.” That acceptance clause is followed by a signature block for plaintiffs representative to complete.

Plaintiff did not sign and return Modification 29. Instead, approximately one week after the parties reached their agreement, “plaintiff repudiated the settlement; plaintiff took the position that the parties’ discussions on February 22, 2001, had not resulted in a final, binding agreement.” Id.

Plaintiff filed this action alleging, among other things, claims for lien foreclosure and breach of contract. Defendants filed counterclaims seeking, among other things, specific performance of the settlement agreement. After a bench trial on [593]*593the counterclaims, the trial court concluded that there was an enforceable settlement agreement under which plaintiff had agreed to settle its claims in return for defendants’ promise to pay $800,000. The trial court entered a limited judgment directing that defendants deposit $800,000 with the clerk of court. However, although plaintiff asserted that defendant should be required to pay prejudgment interest on the $800,000, the “trial court overruled [that] objection.” Id. at 287. In June 2004, “defendants tendered $800,000 to the court clerk.” Id. at 277. The trial court later entered a general judgment dismissing plaintiffs claims with prejudice.

As relevant here, before the Supreme Court, plaintiff asserted that the trial court had erred in denying it prejudgment interest. In particular, it argued that “once defendants chose to seek the benefits of the settlement agreement and asked the trial court to order specific performance, the trial court should have conditioned plaintiffs performance of the settlement agreement on defendants’ payment of the agreed sum plus interest” Id. at 288-89 (emphasis added). The Supreme Court agreed, holding that “the trial court should have conditioned its judgment granting specific performance of the settlement agreement on defendants’ paying $800,000 plus interest from the date of the agreement.” Id. at 289-90.

Defendants, however, argued that,

“even if they otherwise would be liable for prejudgment interest, they tendered payment to plaintiff and thus cut off plaintiffs right to seek prejudgment interest. Defendants note that the trial court found that defendants ‘were ready, willing and able to perform and plaintiff was denied access to the money because of its wrongful refusal to perform under the terms of the settlement agreement.’”

Id. at 290 (citation omitted). The court disagreed. It explained that,

“[t]he trial court’s findings do not show that defendants tendered payment to plaintiff. Rather, as the trial court found, the record reflects that the parties entered into a settlement agreement, that defendants requested information that would permit them to issue checks to plaintiff and [594]*594its suppliers in the future, and that defendants were prepared to do so. The prospect, however, that payment might occur at some point in the future is not sufficient to defeat plaintiff’s claim for prejudgment interest.”

Id. Because it concluded that plaintiff was entitled to prejudgment interest, the court reversed on that issue and remanded the case to the trial court so that the court could “determine th[e] amount of prejudgment interest owed.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
320 P.3d 579, 260 Or. App. 589, 2014 WL 255519, 2014 Ore. App. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdowell-welding-pipefitting-inc-v-united-states-gypsum-co-orctapp-2014.