McDevitt & Street Co. v. Marriott Corp.

754 F. Supp. 513, 1991 U.S. Dist. LEXIS 563, 1991 WL 4173
CourtDistrict Court, E.D. Virginia
DecidedJanuary 17, 1991
DocketCiv. A. 88-0102-A
StatusPublished
Cited by12 cases

This text of 754 F. Supp. 513 (McDevitt & Street Co. v. Marriott Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDevitt & Street Co. v. Marriott Corp., 754 F. Supp. 513, 1991 U.S. Dist. LEXIS 563, 1991 WL 4173 (E.D. Va. 1991).

Opinion

ORDER

ELLIS, District Judge.

This matter is before the Court on remand from the Fourth Circuit Court of Appeals for recalculation of two aspects of damages: 1) the damages attributable to a particular 19-day construction delay, and 2) *514 defendant’s lost-interest award. For the reasons stated below, the Court concludes that plaintiff is entitled to a revised total principal judgment of $183,386.98.

Background

The facts of this case are set forth in detail in McDevitt & Street Co. v. Marriott Corp., 713 F.Supp. 906 (E.D.Va.1989), and need not be fully recounted here. In brief, McDevitt & Street Co. (“McDevitt”) contracted with Marriott Corporation (“Marriott”) to construct a hotel in Herndon, Virginia. The adjusted contract price was $4,946,668. The contract called for completion by December 21, 1986, but the hotel was not substantially completed until May 1, 1987. Citing losses incurred from this delay, Marriott withheld $424,998 from the contract price, asserting that the delay was McDevitt’s fault. McDevitt sued for the amounts withheld, and Marriott counterclaimed for damages arising from the delay.

After a bench trial, the Court made findings of fact on each facet of the delay and accordingly determined the liabilities of the parties. The Court essentially concluded that McDevitt was responsible for the 132-day delay and consequently offset the retained portion of the contract price by various delay-related costs and losses incurred by Marriott. The Court found that the total amount due McDevitt was $514,986.68 and that McDevitt’s breaches of the contract rendered it liable to Marriott for $416,823.00. As a result, the court awarded judgment to McDevitt in the amount of $98,163.68. See McDevitt & Street Co., 713 F.Supp. 906 passim.

On appeal, the Fourth Circuit affirmed this Court’s decision in all but two respects. McDevitt & Street Co. v. Marriott Corp., No. 89-2099, 2111, slip op. (4th Cir. August 17, 1990) [911 F.2d 723 (table)]. First, the Fourth Circuit concluded that this Court erred in holding McDevitt liable for the 19-day delay involving the question of what type of foundation to use in Building D. Consequently, the Fourth Circuit directed that McDevitt be absolved of responsibility for this 19-day delay. Second, the Fourth Circuit held that this Court “should have offset the lost-interest award to Marriott by the interest earned on amounts retained by Marriott due to the delay.” Id. at 5. Absent this offset, Marriott would be in a better position than it would have been in had the breach of contract not occurred. .The Fourth Circuit therefore directed this Court to recompute the lost interest on the sale price of the hotel ($7,745,000) to allow McDevitt a credit for the interest earned on the retainage.

Following the remand, this Court entered an order directing the parties to attempt to settle the remanded issues or, failing settlement, to submit memoranda on specified questions regarding these issues. McDevitt & Street Co. v. Marriott Corp., CA No. 88-0102-A, Order dated September 20, 1990. No overall settlement was achieved. The parties have filed their memoranda, and the remanded issues are now ripe for disposition.

Analysis

I. 19-Day Delay

McDevitt has calculated that the 19-day credit involving Building D reduces Marriott’s counterclaim damages to $343,-145.38. Marriott agrees with this recalculation and stipulates to the $343,145.38 figure. Consequently, the sole issue remaining for resolution is the credit for interest on retained amounts.

II. Interest on Retainage

The Fourth Circuit directed that Marriott’s lost-interest award be offset by the interest earned on “amounts retained” by Marriott. Slip op. at 8. McDevitt argues that the “amounts retained” should not be limited to funds that were due to McDevitt under the construction contract. Instead, McDevitt contends that the “amounts retained” should also include various Marriott expenses that were postponed. In support, McDevitt notes that the sale price of $7,745,000 for the completed project was allocated by the Purchase Agreement across three categories — (i) Building, (ii) Furniture, Fixtures & Equip *515 ment and Fixed Asset Supplies, and (iii) Working Capital. The retained amounts under the contract formed only part of the Building category. According to McDevitt, Marriott must also have postponed expenditures under the other categories and thereby earned interest on the amounts involved in these postponed expenditures. From this, McDevitt argues that if the interest credit is limited to the contract retainage, Marriott would still be in a better position than if the project had been completed on time by virtue of its interest earned on the non-contract amounts.

This argument is unpersuasive. To begin with, it conflicts with the Fourth Circuit’s direction that “McDevitt should be given credit ... for the interest earned by Marriott on the contract amounts retained due to the delay.” Slip op. at 8 (emphasis added). See also id. (“On remand, the lost interest figure should be recomputed to allow for the retainage during the delay”). The meaning of “amounts retained” and “retainage” is unmistakable; both terms refer to the $424,998 retained by Marriott under the building contract with McDevitt. Any other construction of these terms is contrived and unsupported. Second, there is no persuasive record evidence that Marriott postponed any non-contract expenditures because of McDevitt’s performance delay. McDevitt concedes as much when it states that “[t]o the extent these expenditures were postponed by the construction delay they should be included in the computation of the interest credit.” Plaintiff’s Memorandum on Remand at 3. See also id. at 6 (“The interest credit due to postponed expenditures for FF & E and Fixed Asset Supplies depends on how Marriott’s expenditures for these items were affected by the delay”). Moreover, even if the postponement of some of Marriott’s non-contract expenditures was in some sense causally related to McDevitt’s delay, there is no persuasive evidence in the record indicating when these payments would have been made. The interest credit is therefore properly limited to the interest earned by Marriott on the contract retain-age of $424,998.

McDevitt also argues, Memorandum on Remand at 5, that because Marriott withheld the $424,998 retainage through the date of this Court’s initial judgment, the interest earned by Marriott on this amount during the entire period, rather than just the 113-day delay, should be included in the compulsory interest credit. This claim is also unpersuasive. To begin with, the Fourth Circuit directed to the contrary, stating “[o]n remand, the lost interest figure should be recomputed to allow for the retainage during the delay.” Slip. op. at 8 (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JTH Tax LLC v. Caswell
E.D. Virginia, 2022
Key Government Finance, Inc. v. E3 Enterprises Inc.
2 F. Supp. 3d 741 (D. Maryland, 2014)
Moore Brothers Co v. Brown & Root Inc
207 F.3d 717 (Fourth Circuit, 2000)
Continental Insurance v. City of Virginia Beach
908 F. Supp. 341 (E.D. Virginia, 1995)
McDevitt and Street Company v. Marriott Corporation
948 F.2d 1281 (Fourth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
754 F. Supp. 513, 1991 U.S. Dist. LEXIS 563, 1991 WL 4173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdevitt-street-co-v-marriott-corp-vaed-1991.