McDermott Site Plan Review

Vermont Superior Court·Decided October 19, 2009·No. 34-2-09 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

}

In re: McDermott Site Plan Review } Docket No. 34-2-09 Vtec (Appeal of McDermott) } }

Decision and Order on Cross-Motions for Summary Judgment

Appellant-Applicants Gerald and Mary McDermott (Applicants1) appealed from a January 29, 2009 decision of the Planning Commission of the Village of Waterbury denying them site plan approval for a nine-unit, multi-family housing development. Appellant-Applicants are represented by Allan W. Ruggles, Esq.; the Village of Waterbury is represented by William E. Flender, Esq. Interested parties David and Denise Russo are represented by Sarah L. Field, Esq., but did not file memoranda on the pending motions.

Applicants and the Village of Waterbury have each moved for summary judgment on the remaining questions (Questions 1 through 7) of the Statement of Questions.2 Summary judgment is appropriate if “taking the allegations of the nonmoving party as true, it is evident that there exist no genuine issues of material fact and the movant is entitled to judgment as a matter of law.” Fritzeen v. Trudell Consulting Engineers, 170 Vt. 632, 633 (2000) (mem.). When presented with cross-motions for summary judgment, the Court considers each motion independently and “afford[s] all

1 Although only Gerald McDermott signed the zoning application forms at issue in this case, for ease of reference this decision will use the term “Applicants” throughout. 2 The Statement of Questions originally contained ten questions; however, Appellants

withdrew Question 9 on May 15, 2009, and withdrew Questions 8 and 10 on July 20, 2009.

reasonable doubts and inferences to the party opposing the particular motion under consideration.” In re Chimney Ridge Road Merged Parcels, No. 208-9-08 Vtec, slip op. at 2 (Vt. Envtl. Ct. July 31, 2009) (Durkin, J.) (citing DeBartolo v. Underwriters at Lloyd’s of London, 2007 VT 31, ¶ 8, 181 Vt. 609).

The following facts are undisputed except as otherwise noted.

Applicants own approximately ten acres3 of land off Blush Hill Road in the Village of Waterbury. Two acres of Applicants’ property are located in the Route 100 zoning district, with the remaining approximately eight acres located in the Village Commercial zoning district. The application at issue in this appeal proposes to build a nine-unit, multi-family housing development on the two acres of the overall parcel located in the Route 100 zoning district.

The parties have not provided any plans, even the sketches required on the zoning permit application forms, relating to any of the various applications on either the two-acre or the eight-acre portions of this property. The parties have not provided any of the applications filed with the state for Act 250 approval by the District Commission, or for water supply and wastewater system approval or stormwater approval by the Agency of Natural Resources (ANR).

On April 14, 2004, Applicants applied for a zoning permit for a nine-unit project on what their application characterizes as a “10.5” acre parcel. The application was referred to the Planning Commission, which granted site plan approval for the nine- unit project on June 24, 2004; this decision has not been provided to the Court. The application was also referred to the Zoning Board of Adjustment (ZBA), which granted conditional use approval as a multi-family use on August 16, 2004; this decision has not been provided to the Court. The Zoning Administrator issued the corresponding

3 The April 29, 2008 Act 250 decision relating to this property refers to it as 10.17 acres, while the municipal application form filed in 2004 refers to it as 10.5 acres.

zoning permit (No. 10-04-V) (the 2004 Zoning Permit) on August 16, 2004. Neither the application nor the 2004 Zoning Permit makes any reference to any other project proposed for the remainder of the property.

The 2004 application was considered by the Planning Commission, ZBA, and Zoning Administrator under the 2001 Zoning Regulations as amended. The parties have not provided the zoning ordinance considered by the Planning Commission or the Zoning Administrator in 2004, but neither party disputes that the nine-unit project complied with that ordinance. The 2004 Zoning Permit states on its face that the permit “is void in the event of . . . failure to complete construction within two years of the date of approval.” The 2004 Zoning Permit became final without appeal, and could not thereafter be challenged, either directly or indirectly. 24 V.S.A. § 4472(d).

On October 25, 2004, the Agency of Natural Resources (ANR) issued Wastewater System and Potable Water Supply Permit No. WW-5-2935 (the 2004 ANR WWWS Permit) for the “9-unit, 18-bedroom apartment building on a 10.17± acre lot,” referring to engineering plans dated August 30, 2004. This permit authorized an on-site water supply from a drilled well and connection to the municipal wastewater treatment facility.

The parties have not stated when the Interim Zoning Regulations (adopted some time in 2005) were first noticed for a first public hearing. Under 24 V.S.A. § 4449(d),4 applications filed within the first 150 days after the date of such notice regarding the adoption or amendment of a bylaw are required to be reviewed under the proposed new or amended bylaw, rather than under the old or existing bylaw. The Town and Village of Waterbury adopted interim zoning regulations in 2005. 24 V.S.A. § 4415.5

4 This section has been in effect since July of 2001; prior to 2004 it was codified at 24 V.S.A. § 4443(d). 5 Interim regulations have a two-year duration, which may be extended or reenacted for an additional year. 24 V.S.A. § 4415(a), (f).

Under the 2005 Interim Zoning Regulations, the density requirement for the Route 100 zoning district was reduced to a maximum of two multi-family dwelling units per acre.

At some time in early 2005 Applicants filed application No. 09-05-V for a zoning permit for 92 (later apparently reduced to 81) units of multi-family housing on the remainder of the parcel; that application was also referred for site plan and conditional use approval.6 The parties have not provided any of the zoning permit applications for the 59-unit project. The Planning Commission deliberated on the application on July 12, 2005, and denied it due to concerns with pedestrian safety and vehicular circulation. The parties have not provided the Planning Commission’s decision or meeting minutes for that denial. On appeal to this Court, Applicants and the Village resolved the appeal by a January 18, 2006 consent order allowing the application to be revised to propose no more than 59 dwelling units, but to be considered under the Zoning Regulations and site plan review criteria in effect on April 8, 2005 (referring to the 2001 Zoning Regulations as last amended on May 4, 2004).

On August 1, 2005, the state’s District Environmental Office issued a Project Review Sheet, submitted based on information provided by Applicants’ engineer. The project is described as being on a 10.17-acre tract of land, to “realign sewer line for previously approved 9-unit7 residential project, add stormwater detention pond and storm drain line[,] plus identify three lots on the project plans, and map wetland.” The permit specialist for the ANR noted that a wastewater permit would be required. The Act 250 District Coordinator noted that an Act 250 permit would be required, stating as

6 Facts as to this application are derived from the January 18, 2006 consent order in No. 163-8-05 Vtec, entered into by Applicants and the Village, copies of which were provided by both parties to the present appeal, and from the narrative in the Planning Commission’s May 3, 2007 letter to the District 5 Environmental Commission. 7 The number “9” is cut off on the photocopy of this document provided to the Court; however, the internal context of the Act 250 District Coordinator’s comment shows that the number must have been “9.”

Free access — add to your briefcase to read the full text and ask questions with AI

McDermott Site Plan Review, (Vt. Ct. App. 2009).

McDermott Site Plan Review (McDermott Site Plan Review) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Miller
2009 VT 36 (Supreme Court of Vermont, 2009)
In re Pierce Subdivision Application
2008 VT 100 (Supreme Court of Vermont, 2008)
In Re Stowe Club Highlands
668 A.2d 1271 (Supreme Court of Vermont, 1995)
Slocum v. Department of Social Welfare
580 A.2d 951 (Supreme Court of Vermont, 1990)
Preseault v. Wheel
315 A.2d 244 (Supreme Court of Vermont, 1974)
State v. Tierney
412 A.2d 298 (Supreme Court of Vermont, 1980)
Wesco, Inc. v. City of Montpelier
739 A.2d 1241 (Supreme Court of Vermont, 1999)
Fritzeen v. Trudell Consulting Engineers, Inc.
751 A.2d 293 (Supreme Court of Vermont, 2000)
Loiselle v. Barsalow
2006 VT 61 (Supreme Court of Vermont, 2006)
Levy v. Town of St. Albans Zoning Board of Adjustment
564 A.2d 1361 (Supreme Court of Vermont, 1989)