Wesco, Inc. v. City of Montpelier

739 A.2d 1241, 169 Vt. 520, 1999 Vt. LEXIS 241
CourtSupreme Court of Vermont
DecidedSeptember 3, 1999
Docket98-454 & 98-455
StatusPublished
Cited by40 cases

This text of 739 A.2d 1241 (Wesco, Inc. v. City of Montpelier) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wesco, Inc. v. City of Montpelier, 739 A.2d 1241, 169 Vt. 520, 1999 Vt. LEXIS 241 (Vt. 1999).

Opinion

Morse, J.

This consolidated appeal involves two properties, one owned by Timberlake Associates and the other by Wesco, Inc. (referred to jointly as “Wesco”), located on State Street in Montpelier. The Environmental Court granted summary judgment in favor of the City of Montpelier determining that conditional use permits were necessary for both properties. Wesco contends that the court erred in its determination because (1) the zoning board of adjustment was barred from requiring a conditional use permit when the zoning administrator’s determination had not been appealed within fifteen days as required by 24 V.S.A. §§ 4464(a) and 4472(d); (2) the City should be estopped from requiring conditional use approval; (3) conditional use approval is not required under the City’s zoning regulations; and (4) the applications for zoning permits should be deemed approved under 24 V.S.A. § 4407(2). We affirm.

The relevant facts are as follows. In March 1989, Wesco applied to the Montpelier zoning administrator for a zoning permit to convert its 107 State Street gas station from a gas station and service garage to a gas station and convenience store. * The application sought approval to renovate the building, modify the layout of the gas pumps, and discontinue motor vehicle repair or servicing. The zoning administrator sent the application to the department of planning and development in order to schedule planning commission review. At a planning commission review of the design and site plan, the application in that *522 respect was denied because traffic access was inadequate, creating parking and pedestrian safety concerns. Wesco appealed to the superior court.

In April 1995, after protracted litigation, the superior court under 24 Y.S.A. § 4471(a) (interested persons may appeal decision of development review board) granted design review and site plan approval to the property at 107 State Street and site plan approval to the 108 State Street property. In June 1996, Wesco applied for building permits for both properties. The zoning administrator denied the building permits because zoning permits had not been issued, and ruled that conditional use approval was required for the renovations. Wesco appealed to the zoning board, which affirmed the zoning administrator’s decision. On appeal to the Environmental Court, the court ruled that conditional use approval was necessary for both properties. This appeal followed.

I.

Wesco first contends that when the zoning administrator reviewed the initial application in 1989 and sent it to the planning commission for design and site plan approval, the zoning administrator’s action constituted a decision that a conditional use permit was not required under 24 V.S.A. § 4464(a). They claim that because this “determination” was not appealed within the fifteen-day appeals period under 24 V.S.A. §■ 4464(a), the requisite appeal period had passed. Therefore, they argue, the zoning board is barred from requiring conditional use approval and the decision may not be contested under 24 V.S.A. § 4472(d). We disagree.

Title 24 V.S.A. § 4464(a) provides:

[A]n interested person may appeal any decision or act taken, by the administrative officer, in any municipality by filing a notice of appeal with the secretary of the board of adjustment .... If the appeal is taken -with respect to a decision or act of an administrative officer, such notice of appeal must be filed within fifteen days of the date of such decision or act. . . . If the administrative officer fails to act with regard to an application for a permit, within thirty days, a permit shall be deemed issued on the 31st day.

(emphasis added). Furthermore, 24 V.S.A. § 4472(d) provides:

Upon the failure of any interested person to appeal to a board of adjustment under section 4464 of this title, or to *523 appeal to a superior court under section 4471 of this title, all interested persons affected shall be bound by such decision or act of such officer . . . and shall not thereafter contest, either directly or indirectly, such decision or act... .

(emphasis added).

Upon receiving a zoning permit application, the zoning administrator has three options. The administrator may grant or deny the application, or may refer it to the zoning board for a conditional use permit or to the planning commission for site plan or design plan review. As noted in the application form, the zoning administrator’s grant or denial may be appealed to the board of adjustment within fifteen days of its issuance. See 24 V.S.A. § 4464(a) (providing only a fifteen-day appeal period when appeal is regarding a decision or act of the zoning administrator).

Here, in 1989, the zoning administrator scheduled Wesco’s initial zoning permit application with the planning commission for design review within the statutory period. After denial by the planning commission and lengthy litigation, the trial court granted design review approval. Up to that point in time, the zoning administrator had not made a decision on the merits. The zoning administrator had never granted or denied a zoning permit, but merely referred Wesco’s application to the planning commission.

We conclude that it was only when the zoning administrator denied the zoning permit on the basis that a conditional use permit was required that the zoning administrator acted upon Wesco’s application. It was this decision that was subject to appeal. See 24 V.S.A. § 4443(a)(1) (no land development may be initiated within an area affected by zoning regulations without permit issued by the zoning administrator); see also 24 V.S.A. § 4303(3) (“Land development” defined as including “any change in the use of any building or other structure”). Because no decision on the merits was rendered until the denial of the application, the fifteen-day time period for an appeal did not run, see 24 V.S.A. § 4464(a), and the zoning board is not barred from requiring conditional use approval.

II.

Wesco next contends that equity demands that the City be es-topped and the permits be issued as a matter of law based on fairness. The doctrine of equitable estoppel is “based upon the grounds of public policy, fair dealing, good faith, and justice,” see Fisher v. Poole, *524 142 Vt. 162, 168, 453 A.2d 408, 411 (1982); however, “[e]stoppels against the government are rare and are to be invoked only in extraordinary circumstances.” See In re McDonald’s Corp., 146 Vt. 380, 383, 505 A.2d 1202, 1203-04 (1985). Wesco claims that the City is charged with knowing the zoning regulations and their interpretation. They contend that they relied on the fact that when their attorney called the zoning administrator to ask whether a conditional use permit was required for the conversion, the zoning administrator said that no approval by the zoning board was necessary. After the telephone conversation, their attorney sent a letter to the zoning administrator stating his understanding of the conversation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams NOV - Decision on Motions
Vermont Superior Court, 2019
Lee NOV
Vermont Superior Court, 2016
Langlois Novicki Variance
Vermont Superior Court, 2016
ANR v. Bacon
Vermont Superior Court, 2015
Laverack v. Town of Landgrove
Vermont Superior Court, 2015
In re Bjerke Zoning Permit Denial
195 Vt. 586 (Supreme Court of Vermont, 2014)
Moore Accessory Structure Permit
Vermont Superior Court, 2010
Benning Accessory Use Permit
Vermont Superior Court, 2010
Cushing Family, LLC Site Plan Application
Vermont Superior Court, 2009
Garbitelli v. Town of Brookfield
2009 VT 109 (Supreme Court of Vermont, 2009)
McDermott Site Plan Review
Vermont Superior Court, 2009
Paynter 2-Lot Subdivision
Vermont Superior Court, 2009
Mastelli Construction Application
Vermont Superior Court, 2008
Honora Vineyard Application
Vermont Superior Court, 2008
In Re Appeal of Trahan Nov
2008 VT 90 (Supreme Court of Vermont, 2008)
In re Lakatos
182 Vt. 487 (Supreme Court of Vermont, 2007)
Sisters & Brothers Investment Group, LLP
Vermont Superior Court, 2007
McDermott Conditional Use Application
Vermont Superior Court, 2006

Cite This Page — Counsel Stack

Bluebook (online)
739 A.2d 1241, 169 Vt. 520, 1999 Vt. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wesco-inc-v-city-of-montpelier-vt-1999.