McCorkle Eastside Neighborhood Grp. v. City of St. Helena

242 Cal. Rptr. 3d 379, 31 Cal. App. 5th 80
CourtCalifornia Court of Appeal, 5th District
DecidedDecember 18, 2018
DocketA153238
StatusPublished
Cited by3 cases

This text of 242 Cal. Rptr. 3d 379 (McCorkle Eastside Neighborhood Grp. v. City of St. Helena) is published on Counsel Stack Legal Research, covering California Court of Appeal, 5th District primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCorkle Eastside Neighborhood Grp. v. City of St. Helena, 242 Cal. Rptr. 3d 379, 31 Cal. App. 5th 80 (Cal. Ct. App. 2018).

Opinion

NEEDHAM, J.

*85Appellants McCorkle Eastside Neighborhood Group and St. Helena Residents for an Equitable General Plan opposed the development of an eight-unit multifamily residential building at 632 McCorkle Avenue. They filed a lawsuit challenging the actions of respondents the City of St. Helena (City) and the City Council of St. Helena (City Council) in approving a resolution granting demolition and design review permits to property owner and real party in interest Joe McGrath. When the trial court denied their petition for peremptory and administrative writ of mandate ( Code Civ. Proc., §§ 1085, 1094.5 ), appellants filed this appeal. Appellants contend (1) the City violated the California Environmental Quality Act (CEQA; Govt. Code, § 21000 et seq. ) because the City Council failed to consider aspects of the project other than design review; and (2) the City abused its discretion under CEQA by approving the demolition permit and design review without requiring an environmental impact report (EIR) based on its determination that the proposed project met the requirements for a Class 32 (infill) categorical exemption under 14 California Administrative Code section 15332 (CEQA Guidelines). We affirm.

I. BACKGROUND

The planning and zoning law establishes the authority of most local governmental entities to regulate the use of land. ( Topanga Assn. for a Scenic Community v. County of Los Angeles (1974) 11 Cal.3d 506, 518-519, fn. 18, 113 Cal.Rptr. 836, 522 P.2d 12.) "Zoning laws regulate land uses in two basic ways. Some uses are permitted as a matter of right if the uses conform to the zoning ordinance. Other sensitive land uses require discretionary administrative approval pursuant to criteria in the zoning ordinance. ( [Govt. Code,] § 65901.) They require a conditional use permit." ( Neighborhood Action Group v. County of Calaveras (1984) 156 Cal.App.3d 1176, 1183, 203 Cal.Rptr. 401.) A conditional use permit contemplates the review of *383individual applications using sound principles of zoning and planning and is discretionary by nature. (See Breakzone Billiards v. City of Torrance (2000) 81 Cal.App.4th 1205, 1224, 97 Cal.Rptr.2d 467.)

In 2015, the City began the process for amending the housing element of its general plan to conform with state policies by committing to eliminate the conditional use permit requirement for multi-family dwellings within High Density Residential (HR) districts. In 2016, the City amended its zoning *86ordinance to comply with this commitment. Section 17.44.020(C) of the St. Helena Municipal Code makes "[m]ultiple-family dwellings, apartments and dwelling groups consistent with the density requirements of this chapter" a permitted use within the HR district. Section 17.44.030 provides a list of uses requiring use permits, and multi-family dwellings are not on that list. Design review is still required for multi-family residential units within an HR district under section 17.44.040.

Real party in interest Joe McGrath purchased the half-acre lot at 632 McCorkle Avenue, an area within the City's HR district, intending to build multi-family dwellings on the property. The lot contained a dilapidated single-family home and its soil had been contaminated with lead by a prior occupant. McGrath committed to remediating this contamination with Napa County. He submitted an application for a demolition permit to demolish the existing structure as well as a design review plan for the proposed eight units. The application was deemed complete by the City's Planning Commission staff in October 2016, who prepared a report concluding (1) the proposed project fell within the Class 32 infill exemption of CEQA Guidelines section 15332 and was thus exempt from CEQA; and (2) the project met the criteria for design review.

The project came before the full Planning Commission in a hearing held on December 6, 2016. It was opposed by several neighbors and by appellants, who argued the project should not be approved because: (1) the site of the proposed development was contaminated; (2) McCorkle Avenue contains no storm drains and routinely floods; (3) there is little public open space in the area and children are required to play in the street; (4) the space required for a firetruck turnaround was not adequate; (5) the proposed project was located in a historical district, and was not consistent with the design of four historical homes located across the street; and (6) the proposed project was next door to the pending multi-family Brenkle project, and the cumulative effects of those projects would be significant.1 The City Attorney advised the Planning Commission that because the St. Helena Municipal Code now did not require issuance of a use permit for multifamily dwellings in HR districts, the Commission was required to approve the project so long as it met the design review criteria. Issues pertaining to use, such as parking, traffic, safety and soil remediation, were not to be considered. The City Attorney indicated he was confident that a Class 32 exemption applied to the project under CEQA Guidelines section 15332, but that in any event CEQA would not apply to a nondiscretionary project such as this.

*87The Planning Commission approved the demolition and design review permits by a 2-1 vote in a resolution dated December 6, 2016. It found the project was exempt *384from CEQA under CEQA Guidelines section 15332 and would not cause any significant environmental effects. One commissioner who voted in favor of the project noted on the record this was "a tough one," but she had voted to approve "based on what the restrictions of our discussion and our-our jurisdiction are, specific to design review."

Appellants appealed to the City Council.2 A hearing was held on January 24, 2017. The City Attorney advised the City Council it was limited to "the design aspects of this project" and reiterated that a Class 32 exemption applied but if it did not, review was still limited due to there being no use permit required.

The City Council voted 3-2 to deny the appeal and approve the action of the Planning Commission. It issued a resolution making findings in support of its approval for design review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
242 Cal. Rptr. 3d 379, 31 Cal. App. 5th 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccorkle-eastside-neighborhood-grp-v-city-of-st-helena-calctapp5d-2018.