M.C. Dean, Inc. v. Secretary of Labor

505 F. App'x 929
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 1, 2013
Docket11-13748
StatusUnpublished
Cited by1 cases

This text of 505 F. App'x 929 (M.C. Dean, Inc. v. Secretary of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.C. Dean, Inc. v. Secretary of Labor, 505 F. App'x 929 (11th Cir. 2013).

Opinion

PER CURIAM:

M.C. Dean petitions for review of a final decision of the Occupational Safety and Health Review Commission finding that M.C. Dean violated the Occupational Safety and Health Act (“OSHA”) by failing to guard a skylight which resulted in an employee’s fall and subsequent death. After careful review of the record and briefs, and with the benefit of oral argument, we deny the petition for review and affirm the Commission’s decision.

I. BACKGROUND

Because the facts underlying M.C. Dean’s citation are central to this appeal, we recount them below.

A. The Underlying Incident

Petitioner M.C. Dean is an electrical contractor that, among other things, services existing electrical installations. In August 2009, Ryder Transportation Services (“Ryder”) hired M.C. Dean to perform electrical equipment upgrades and maintenance at Ryder’s warehouse. Tommy McGregor, M.C. Dean’s service group manager, selected a three-person team to complete the Ryder project: Boyd Young, Lewis Quinn, and Sam Dittmore. Young *931 and Quinn were both journeymen electricians, while Dittmore was an apprentice electrician.

While McGregor was the team’s supervisor, a lead electrician was selected to manage the Ryder project onsite. Because Young had more knowledge and experience with motor controls, service panels, and breakers, Young became the “lead” or “senior man” on the Ryder project.

As lead, Young served as the direct contact with Ryder and managed the project onsite. A Ryder representative communicated directly to Young the tasks to be performed át the job; Young then relayed that information to supervisor McGregor. But if a new task was required, McGregor was not always called before it was added to the task list, and Young had the latitude to service additional work requests. Also in his capacity as lead, Young obtained any necessary materials missing from the jobsite; answered any inquiries from Ryder; and generally determined the manner in which the tasks of the job would be executed. However, Young could not discipline any employee. That duty remained with McGregor. McGregor was also responsible for safety.

The work required for the Ryder project included running conduit and mounting junction boxes along the roof inside the warehouse. The work was completed using an articulating boom lift inside the facility. While working inside the warehouse, the crew noticed rectangular skylights located on the roof of the building.

M.C. Dean’s crew had been onsite for approximately two weeks, when on August 27, 2009, Dittmore completed the daily pre-task planner for the Ryder job. The pre-task planner assessed the risks involved in the day’s tasks. After Dittmore filled out the planner, Young and Quinn reviewed it, and all three crew members signed it. The pre-task planner noted as safety hazards for the day “[o]thers working in the area” and “finish unenergized circuits using lift.” In two places, the pre-task planner noted that the crew would need “100% Fall Protection.” 1 The pre-task planner did not mention any hazard related to the skylights or roof. At the time the crew completed the pre-task planner on August 27, they did not know they would have to access the roof that day.

Later that morning, the crew learned that the facility’s exhaust fans did not come on with the flip of the switch as they should have after the crew finished rewiring. The crew determined it would have to access the roof to verify the voltage at the exhaust fans. Prior to accessing the roof, Young discussed it with Jeff Thompson, a Ryder employee. Thompson told Young that there was no roof access, but the roof had been accessed in the past via a series of ladders.

As noted above, the Ryder facility’s roof had a number of skylights that were apparent from the ground inside the building. However, on the roof, the skylights were nearly invisible, as the color and texture of the corrugated roof and skylight panels were virtually identical. The skylight panels were approximately 25 feet apart on the roof, and no skylight was within six feet of either exhaust fan that the crew would be required to access. Thompson and Young did not discuss the skylights on the roof, and Young did not inquire as to whether the skylights had a guardrail or screen, or whether they were clearly marked.

*932 The crew decided to access the roof using the boom lift. Because Quinn had the most experience with the lift, Quinn used the lift to access the roof. Quinn wore a safety harness (i.e., fall protection) while transported in the lift from the ground to the roof. Once he exited the lift onto the roof, Quinn did not use a harness. Quinn was on the roof for 15 or 20 minutes and remained in constant radio contact with Young. After testing the two exhaust fans, Quinn fell through a skylight 25 feet to the facility’s concrete floor below. Two weeks later, Quinn died from his injuries.

B. The OSHA Inspection and Citation

On September 11, 2009, Reinaldo White, an OSHA compliance officer, conducted an investigation at the Ryder facility after Quinn’s death. After his investigation, White recommended, and the Secretary of Labor issued, a single “serious” citation to M.C. Dean for failing to guard the skylight openings in violation of 29 C.F.R. § 1910.28(a)(4). 2 White recommended its categorization as a “serious” violation because of Quinn’s death. The proposed penalty was $7,000. M.C. Dean contested the citation and penalty to an administrative law judge of the Occupational Safety and Health Review Commission (the “Commission”). 3

C. The Administrative Law Hearing and Decision

On September 2 and 8, 2010, an administrative hearing was held before an administrative law judge (“ALJ”). The ALJ heard testimony from Reinaldo White, Boyd Young, Tommy McGregor, and M.C. Dean’s Vice-President of Safety John Bennett.

Boyd Young testified as to the events of August 27, 2009. Young estimated that the skylights were located 25 feet away from the exhaust fans on the roof. Young also testified about the six-foot rule, and stated that he and Quinn had been trained on the six-foot rule. Young had no reason to believe Quinn would go within six feet of any of the skylights. But Young testified that he had never before seen those kinds of flush skylight panels.

Tommy McGregor testified that on the day of the accident, Young was designated lead, but neither Quinn nor Young were considered supervisors. McGregor defined the term “field supervisor” as a “general term” referring to when “someone is watching over or dictating the task.” But if a serious problem arose on the jobsite, the crew would have called McGregor, as it was his duty to take care of those issues. Specifically, if an employee violated safety requirements, it was McGregor’s responsibility to take care of it. McGregor would visit jobsites, but it would vary as to how often he visited. McGregor did not go to the Ryder jobsite until after the accident.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. DNRB, Inc.
320 F. Supp. 3d 1054 (E.D. Missouri, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
505 F. App'x 929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mc-dean-inc-v-secretary-of-labor-ca11-2013.