Matter of Village of Haverstraw
This text of 2020 NY Slip Op 1068 (Matter of Village of Haverstraw) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
| Matter of Village of Haverstraw |
| 2020 NY Slip Op 01068 |
| Decided on February 13, 2020 |
| Appellate Division, Second Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and subject to revision before publication in the Official Reports. |
Decided on February 13, 2020 SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
RUTH C. BALKIN, J.P.
JEFFREY A. COHEN
ROBERT J. MILLER
COLLEEN D. DUFFY, JJ.
2017-04033
2017-04034
2017-04505
2017-04724
(Index No. 1843/06)
Zarin & Steinmetz, White Plains, NY (Michael D. Zarin and Zachary R. Mintz of counsel), for appellant.
Goldstein, Rikon, Rikon & Houghton, P.C., New York, NY (Joshua H. Rikon of counsel), for respondents.
DECISION & ORDER
In a condemnation proceeding, the condemnor appeals from (1) an order of the Supreme Court, Rockland County (Bruce E. Tolbert, J.), entered March 2, 2017, (2) an order of the same court also entered March 2, 2017, (3) an order and judgment (one paper) of the same court dated March 30, 2017, and (4) an order and judgment (one paper) of the same court also dated March 30, 2017. The first order granted the motion of the claimant Ferguson Management Company, LLC, for an additional allowance pursuant to EDPL 701 to the extent of awarding it the principal sum of $106,480.73. The second order granted the motion of the claimant Executive Touch Landscaping & Construction, LLC, for an additional allowance pursuant to EDPL 701 to the extent of awarding it the principal sum of $127,064.82. The first order and judgment granted the motion of the claimant Ferguson Management Company, LLC, for an additional allowance pursuant to EDPL 701 to the extent of awarding it the principal sum of $106,480.73, and is in favor of that claimant and against the condemnor in that principal sum, with postjudgment interest at the rate of 9% annually. The second order and judgment granted the motion of the claimant Executive Touch Landscaping & Construction, LLC, for an additional allowance pursuant to EDPL 701 to the extent of awarding it the principal sum of $127,064.82, and is in favor of that claimant and against the condemnor in that principal sum, with postjudgment interest at the rate of 9% annually.
ORDERED that the appeals from the orders entered March 2, 2017, are dismissed, as the orders were superseded by the orders and judgments dated March 30, 2017; and it is further,
ORDERED that the first order and judgment is reversed, on the facts, the motion of the claimant Ferguson Management Company, LLC, for an additional allowance pursuant to EDPL 701 is denied, and the first order is modified accordingly; and it is further,
ORDERED that the second order and judgment is modified, on the law, on the facts, and in the exercise of discretion, (1) by deleting the provision thereof granting the motion of the [*2]claimant Executive Touch Landscaping & Construction, LLC, for an additional allowance pursuant to EDPL 701 to the extent of awarding it the principal sum of $127,064.82 and awarding it that principal sum, and substituting therefor a provision granting the motion to the extent of awarding Executive Touch Landscaping & Construction, LLC, the principal sum of $70,831.40 and awarding it that principal sum, and (2) by deleting the provision thereof awarding postjudgment interest at the rate of 9% annually, and substituting therefor a provision awarding postjudgment interest at the rate of 6% annually; as so modified, the second order and judgment is affirmed, and the second order is modified accordingly; and it is further,
ORDERED that one bill of costs is awarded to the condemnor, payable by the claimant Ferguson Management Company, LLC.
In 2006, the condemnor, Village of Haverstraw, condemned property owned by the claimant Ferguson Management Company, LLC (hereinafter Ferguson), and leased by the claimant Executive Touch Landscaping & Construction, LLC (hereinafter Executive). The Village made advance payments of $575,000 to Ferguson for the fee and $61,044 to Executive for its fixtures. Both Ferguson and Executive challenged the sufficiency of the compensation paid by the Village.
Notwithstanding its advance payment to Ferguson of $575,000, at the trial on valuation, the Village offered an appraisal of the fee valuing it at $316,500, whereas Ferguson's appraiser valued it at $800,000. The Supreme Court concluded that, "[o]n the whole, [Ferguson] ha[d] provided more competent evidence to support [its] calculations than [the Village]," and that the fair market value of the property on the title vesting date was $721,671. With respect to Executive's trade fixture claim, the court deemed the Village's appraisal "irrelevant" to the issue before it and, thus, precluded the Village from proffering testimony regarding the value of the trade fixtures. The court found that Executive was not entitled to compensation for 142 of the fixtures for which it sought compensation, and that it was entitled to installation costs for only eight additional items. The court concluded that Executive was entitled to compensation for 58 fixtures and awarded it only $159,596 of the $973,000 it sought.
Both Ferguson and Executive moved for additional allowances pursuant to EDPL 701, contending that their respective awards substantially exceeded the Village's proof, and that additional allowances were necessary to achieve just and adequate compensation. The Supreme Court granted the claimants' motions to the extent of awarding an additional allowance of $106,480.73 to Ferguson and an additional allowance of $127,064.82 to Executive, with postjudgment interest at the rate of 9% annually. The Village appeals.
Pursuant to EDPL 701, where a court's award to a claimant in a condemnation proceeding is "substantially in excess of the amount of the condemnor's proof" and where the court deems it necessary to "achieve just and adequate compensation," the court may award the claimant an additional sum for costs including attorneys' and other fees. The goal of this statute is to " assure[ ] that a condemnee receives a fair recovery by providing an opportunity for condemnees whose property has been substantially undervalued to recover the costs of litigation establishing the inadequacy of the condemnor's offer'" (Matter of Village of Spring Val., N.Y., 171 AD3d 934, 935, quoting Hakes v State of New York, 81 NY2d 392, 397; see Matter of Village of Haverstraw [AAA Electricians, Inc.], 165 AD3d 955, 956; Matter of City of Long Beach v Sun NLF L.P., 146 AD3d 775, 776).
"The statute requires two determinations: first, whether the award is substantially in excess of the amount of the condemnor's proof' and second, whether the court deems the award necessary for the condemnee to achieve just and adequate compensation'" (Hakes v State of New York, 81 NY2d at 397, quoting EDPL 701; see Matter of Village of Spring Val., N.Y., 171 AD3d at 935; Matter of Village of Haverstraw [AAA Electricians, Inc.], 165 AD3d at 956; Matter of City of Long Beach v Sun NLF L.P., 146 AD3d at 776). " Where both tests are satisfied, the court may award reasonable fees'" (
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2020 NY Slip Op 1068, 120 N.Y.S.3d 380, 180 A.D.3d 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-village-of-haverstraw-nyappdiv-2020.