Matter of Broome County Concerned Residents v. New York State Bd. on Elec. Generation Siting & the Envt.

2021 NY Slip Op 05903, 157 N.Y.S.3d 166, 200 A.D.3d 26
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 28, 2021
Docket531357
StatusPublished
Cited by1 cases

This text of 2021 NY Slip Op 05903 (Matter of Broome County Concerned Residents v. New York State Bd. on Elec. Generation Siting & the Envt.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of Broome County Concerned Residents v. New York State Bd. on Elec. Generation Siting & the Envt., 2021 NY Slip Op 05903, 157 N.Y.S.3d 166, 200 A.D.3d 26 (N.Y. Ct. App. 2021).

Opinion

Matter of Broome County Concerned Residents v New York State Bd. on Elec. Generation Siting & the Envt. (2021 NY Slip Op 05903)
Matter of Broome County Concerned Residents v New York State Bd. on Elec. Generation Siting & the Envt.
2021 NY Slip Op 05903
Decided on October 28, 2021
Appellate Division, Third Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered:October 28, 2021

531357

[*1]In the Matter of Broome County Concerned Residents et al., Petitioners,

v

New York State Board on Electric Generation Siting and the Environment et al., Respondents, et al., Respondents.


Calendar Date:September 14, 2021
Before: Garry, P.J., Aarons, Pritzker, Reynolds Fitzgerald and Colangelo, JJ.

The Zoghlin Group, PLLC, Rochester (Benjamin E. Wisniewski of counsel), for petitioners.

Robert Rosenthal, Public Service Commission, Albany (John C. Graham of counsel), for New York State Board on Electric Generation Siting and the Environment, respondent.

Young/Sommer LLC, Albany (William A. Hurst of counsel), for Bluestone Wind, LLC, respondent.



Pritzker, J.

Proceeding pursuant to CPLR article 78 (initiated in this Court pursuant to Public Service Law § 170 [1]) to review a determination of respondent State Board on Electric Generation Siting and the Environment granting an application by respondent Bluestone Wind, LLC for a certificate of environmental compatibility and public need to construct a wind farm.

Public Service Law article 10 provides for a comprehensive review of environmental and public interest impacts and the issuance of a certificate of environmental compatibility and public need as a precondition to the siting of a major electric generating facility within the state (see Public Service Law §§ 160 [2]; 162). Ultimate authority for this review is delegated to respondent State Board on Electric Generation Siting and the Environment (hereinafter the Siting Board) within the Department of Public Service (hereinafter DPS) (see Public Service Law § 160 [4]). In October 2016, respondent Bluestone Wind, LLC (hereinafter Bluestone) submitted to DPS a notice of intent seeking a certificate to construct the Bluestone Wind Farm Project — an approximately 125-megawatt wind powered electric generating facility with a proposed location in the Town of Sanford (hereinafter the Town) and the Town of Windsor, both in Broome County. This was accompanied by Bluestone's preliminary Public Involvement Program Plan (hereinafter PIP). As initially proposed, the project included the construction and operation of up to 40 wind turbines. The October 2016 PIP noted that Bluestone had already begun engaging with stakeholders, including the Town, regarding the project plans. Following a review and in consideration of recommendations from DPS staff, Bluestone submitted a revised PIP in December 2016.

In January 2017, the Sanford Town Board adopted Local Law No. 1-2017 of the Town of Sanford (hereinafter Local Law No. 1) amending the Town's Land Use Management Local Law and setting forth regulations for the design, siting and installation of renewable energy systems, including wind energy conversion systems. In its subsequent application to the Siting Board, submitted in September 2018, Bluestone outlined the various local laws and ordinances that could impact the project. As relevant here, Bluestone stipulated, after consulting with the Town, to the applicability of Local Law No. 1 in regard to both its procedural and substantive requirements. Bluestone expressly noted that "[t]he location of the proposed [f]acility will conform to all such local substantive requirements" and that, as such, it was not requesting that the Siting Board grant any waivers for provisions of local law.

The Siting Board deemed Bluestone's application complete on December 27, 2018, thus triggering a statutorily imposed one-year period for it to render a determination (see Public Service Law § 165 [4] [a]). As part of its application, Bluestone submitted a required intervenor fee of $124,000, "to be disbursed at the [Siting [*2]Board's] direction, to defray expenses incurred by municipal and other local parties to the proceeding . . . for expert witness, consultant, administrative and legal fees" (Public Service Law § 164 [6] [a]; see Public Service Law § 163 [4] [a]). Upon each of their timely requests, this funding was distributed among the Town, the Town of Windsor, petitioner Delaware-Otsego Audubon Society, Inc. (hereinafter DOAS) and petitioner Broome County Concerned Residents (hereinafter BCCR) (see Public Service Law § 164 [6] [b]). Administrative Law Judges from the Department of Environmental Conservation (hereinafter DEC) and DPS were appointed to serve as Hearing Examiners. Following prefiled testimony on all issues, hearings were held over a period of three days, from July 9 through 11, 2019.

After the evidentiary hearing was closed, on August 13, 2019, the Sanford Town Board approved Local Law No. 2-2019 of the Town of Sanford (hereinafter Local Law No. 2) affecting a temporary, three-month moratorium within the Town on the development and construction of wind energy conversion systems "so as to allow the Town time to study the potential impacts, effects, and possible controls over such activities." Considering this development, BCCR — but not the Town — filed a motion with the Siting Board to stay the proceedings for three months. The Hearing Examiners denied said motion, finding that it was statutorily bound to render a decision within 12 months of Bluestone's application (see Public Service Law § 165 [4] [a]).

In October 2019, the Hearing Examiners issued a recommended decision to the Siting Board which, in part, took judicial notice of Local Law No. 2, but determined that it was a procedural law that was inapplicable to the proceeding. Ultimately, the Hearing Examiners recommended that the Siting Board grant Bluestone a conditional certificate for the project, subject to a number of specified terms. Nearly all involved parties in opposition to the project — notably, excluding the Town — then filed briefs on exception in October 2019. Following the completion of this briefing process, the Sanford Town Board approved Local Law No. 3-2019 of the Town of Sanford on November 12, 2019, extending the moratorium created in Local Law No. 2 until the earlier of either its repeal or March 1, 2020.

On December 9, 2019, the Siting Board issued a press release indicating that it would meet on December 16, 2019 to consider Bluestone's application. On December 11, 2019, BCRR (again, not the Town) notified the Siting Board that the Town had adopted a new superseding local law regulating, among other things, wind energy generating facilities. On December 13, 2019, the Town submitted a letter indicating that it had approved and filed, on that same date, Local Law No. 4-2019 of the Town of Sanford (hereinafter Local Law No. 4).[FN1] The Town did not otherwise comment on Local Law No. 4, which superseded Local Law No. 1 and imposed substantial additional restrictions [*3]on wind energy converting systems. Nonetheless, the Siting Board convened on December 16, 2019 and granted Bluestone's application and issued the certificate, subject to nearly 150 conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2021 NY Slip Op 05903, 157 N.Y.S.3d 166, 200 A.D.3d 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-broome-county-concerned-residents-v-new-york-state-bd-on-elec-nyappdiv-2021.