Matter of Coalition of Concerned Citizens v. New York State Bd. On Elec. Generation Siting & The Envt. & Alle-Catt Wind Energy, LLC
This text of 2021 NY Slip Op 06221 (Matter of Coalition of Concerned Citizens v. New York State Bd. On Elec. Generation Siting & The Envt. & Alle-Catt Wind Energy, LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
| Matter of Coalition of Concerned Citizens v New York State Bd. On Elec. Generation Siting & The Envt. & Alle-Catt Wind Energy, LLC |
| 2021 NY Slip Op 06221 |
| Decided on November 12, 2021 |
| Appellate Division, Fourth Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and subject to revision before publication in the Official Reports. |
Decided on November 12, 2021 SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
PRESENT: WHALEN, P.J., SMITH, LINDLEY, TROUTMAN, AND WINSLOW, JJ.
681 OP 20-01405
v
NEW YORK STATE BOARD ON ELECTRIC GENERATION SITING AND THE ENVIRONMENT AND ALLE-CATT WIND ENERGY, LLC, RESPONDENTS. (PROCEEDING NO. 1.)
LAW OFFICE OF GARY A. ABRAHAM, GREAT VALLEY (GARY A. ABRAHAM OF COUNSEL), FOR PETITIONERS.
ROBERT A. ROSENTHAL, GENERAL COUNSEL, ALBANY (JOHN C. GRAHAM OF COUNSEL), FOR RESPONDENT NEW YORK STATE BOARD ON ELECTRIC GENERATION
Proceeding pursuant to Public Service Law § 170 (1) (initiated in the Appellate Division of the Supreme Court in the Fourth Judicial Department) to annul a determination granting a Certificate of Environmental Compatibility and Public Need, and for other relief.
It is hereby ORDERED that the determination is unanimously confirmed without costs and the petition is dismissed.
Memorandum: Alle-Catt Wind Energy, LLC (Alle-Catt), a respondent in both of these proceedings, submitted a proposal to the New York State Board on Electric Generation Siting and the Environment (Board), also a respondent in both proceedings, seeking approval of a project involving the construction of a wind-powered electric generating facility consisting of numerous wind turbines in several Western New York counties. In response to the proposal, the Board issued a "Certificate of Environmental Compatibility and Public Need" (Certificate) that permitted the project to go forward. The Coalition of Concerned Citizens (Coalition) and Dennis Gaffin, as its president (collectively, Coalition petitioners), commenced the first of these two CPLR article 78 proceedings (proceeding No. 1), initiated in this Court pursuant to Public Service Law § 170 (1), seeking to annul the Board's determination to grant the Certificate. The Town of Farmersville (Farmersville) commenced the second CPLR article 78 proceeding (proceeding No. 2), also initiated in this Court pursuant to Public Service Law § 170 (1), seeking to annul the same determination. We confirm the determination, and therefore we dismiss both petitions.
In proceeding No. 1, the Coalition petitioners contend that the Board exceeded its authority by applying Town of Freedom (Freedom) Local Law No. 1 of 2019 (Freedom's 2019 Law), because Supreme Court had determined in a separate proceeding and action that Freedom Local Law No. 3 of 2007 (Freedom's 2007 Law) was in effect at the time of the proceedings before the Board. We reject that contention.
As the Board correctly noted concerning that issue, "[t]he situation is complicated" [*2](Application of Alle-Catt Wind Energy LLC, 2020 WL 3036287, *45, 2020 NY PUC LEXIS 653, *100 [NY St Bd on Elec Generation Siting & Envt, Case 17-F-0282, June 3, 2020]). Before this project began, Freedom's 2007 Law governed applications for wind energy projects such as this one within that town. While the project was in its infancy, the Freedom Town Board enacted Local Law No. 1 of 2018 (Freedom's 2018 Law), which changed several provisions related to wind energy projects, including the maximum height permitted for wind turbines and the required setbacks from residences, churches and other facilities. Freedom's 2018 Law was challenged in a hybrid CPLR article 78 proceeding and declaratory judgment action (separate action) in which Supreme Court eventually annulled that local law and declared that Freedom's 2007 Law remained in effect (Matter of Freedom United v Town of Freedom Town Bd., Sup Ct, Cattaraugus County, Oct. 25, 2019, Parker, A.J., index No. 87572/2019, appeal dismissed 2020 NY Slip Op 61184[U] [4th Dept 2020]). While that litigation was pending, however, the Freedom Town Board enacted Freedom's 2019 Law, which the parties agree concerns the same subjects as Freedom's 2018 Law. Consequently, inasmuch as Freedom's 2018 Law had been superseded by Freedom's 2019 Law, the litigation in the separate action was rendered moot (see generally Lasky v Town Bd. of Town of Amherst, 57 AD3d 1392, 1392-1393 [4th Dept 2008]; Matter of Group for S. Fork v Town Bd. of Town of Southampton, 285 AD2d 506, 508 [2d Dept 2001]). Because the Freedom Town Board enacted Freedom's 2019 Law and it was not at issue in the separate action, that was the operative local law for purposes of the proceedings before the Board, and the Board was required to apply it (see Public Service Law § 168 [3] [e]), regardless of Supreme Court's declaration in the separate action.
Also in proceeding No. 1, the Coalition petitioners contend that the Board gave insufficient weight to the character of the community, that the Board failed to balance the severe adverse impact on that character against the project's modest and theoretical benefits, and that the Board's determination that the project would have beneficial effects on the climate was impermissibly based on speculation. We reject those contentions.
Pursuant to its enabling statute, the Board must determine, inter alia, whether a proposed electric generating facility "is a beneficial addition to or substitution for the electric generation capacity of the state" and whether "the adverse environmental effects of the construction and operation of the facility will be minimized or avoided to the maximum extent practicable" (Public Service Law § 168 [3] [a], [c]), and the Board must consider, inter alia, "the impact on community character" and any additional "social, economic, visual or other aesthetic, environmental and other conditions" deemed pertinent by the Board (§ 168 [4] [f], [g]). "[T]he Board was created to provide for an expeditious review process and 'to balance, in a single proceeding, the people's need for electricity and their environmental concerns' " (Matter of TransGas Energy Sys., LLC v New York State Bd. on Elec. Generation Siting & Envt., 65 AD3d 1247, 1252 [2d Dept 2009], lv denied 13 NY3d 715 [2010]; see generally Matter of Citizens for Hudson Val. v New York State Bd. on Elec. Generation Siting & Envt., 281 AD2d 89, 92 [3d Dept 2001]). Furthermore, it is settled that "[t]his [C]ourt's scope of review is limited to whether the decision and opinion of the [B]oard, inter alia, are . . . supported by substantial evidence in the record and matters of judicial notice properly considered and applied in the opinion . . . , are made in accordance with proper procedure . . . and are not arbitrary, capricious or an abuse of discretion" (Koch v Dyson, 85 AD2d 346, 364 [2d Dept 1982] [internal quotation marks omitted]). "The task of weighing conflicting evidence . . . is properly left to the . . . Board" (id. at 373).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2021 NY Slip Op 06221, 158 N.Y.S.3d 444, 199 A.D.3d 1310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-coalition-of-concerned-citizens-v-new-york-state-bd-on-elec-nyappdiv-2021.