Mathis v. United Engineers & Constructors, Inc.

554 A.2d 96, 381 Pa. Super. 466, 1989 Pa. Super. LEXIS 144, 1989 WL 9811
CourtSupreme Court of Pennsylvania
DecidedFebruary 10, 1989
Docket03496, 03497
StatusPublished
Cited by17 cases

This text of 554 A.2d 96 (Mathis v. United Engineers & Constructors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mathis v. United Engineers & Constructors, Inc., 554 A.2d 96, 381 Pa. Super. 466, 1989 Pa. Super. LEXIS 144, 1989 WL 9811 (Pa. 1989).

Opinion

BECK, Judge:

In this case, we consider consolidated appeals by the Philadelphia Electric Company (PECO) and by United Engineers and Constructors, Inc. (UE & C) from a judgment entered following a jury verdict in favor of plaintiff-appellees John and Elaine Mathis.

John Mathis is a laborer who was assigned by his employer, Henkels and McCoy, Inc., to perform maintenance work at the Eddystone Plant, an electric generating station which is owned and operated by PECO. On May 5, 1981, while John Mathis was dismantling a scaffold which had been erected on a grated catwalk, a portion of the catwalk collapsed beneath his feet. Mathis fell twenty-five feet and sustained serious injuries. He and his wife Elaine initially filed suit against PECO for negligently maintaining the catwalk. The Mathises later brought a separate suit against UE & C, the manufacturer of the catwalk, based on the theory that UE & C had designed and installed the catwalk in a negligent manner. The two suits were consolidated and were tried before a jury in the Court of Common Pleas of Philadelphia County. On May 29, 1986, the jury returned a verdict finding PECO 70% negligent and finding UE & C 30% negligent. The jury awarded John Mathis $161,000 for pain and suffering, loss of earnings, and loss of future earning capacity, and awarded Elaine Mathis $17,000 for loss of consortium.

Both defendants filed timely post-trial motions which were denied. Plaintiffs moved for the award of delay damages pursuant to Pennsylvania Rule of Civil Procedure *471 238. On November 19, 1982, the court issued an order entering judgment in favor of the Mathises and assessing total delay damages of over $67,000. From this final order, UE & C and PECO filed timely appeals.

Counsel for UE & C contends that UE & C is entitled to judgment n.o.v. on the grounds that the company did not breach any duty to the plaintiffs and that UE & C’s actions were not the proximate cause of John Mathis’ injury. In the alternative, counsel for UE & C also argues that the trial court erred: 1) by failing to mold the verdict by ordering PECO to indemnify UE & C; 2) by failing to strike the testimony of plaintiffs’ expert witness on catwalk design; 3) by charging the jury in accordance with the principles of causation set forth in section 447 of the Restatement (Second) of Torts; and 4) by assessing delay damages. After careful consideration, we grant judgment n.o.v. for UE & C. Accordingly, we need not consider UE & C’s remaining allegations of error.

Counsel for PECO contends that the electric company is immune from suit under the provisions of the Pennsylvania Workmen’s Compensation Act. In the alternative, counsel for PECO argues that the trial court erred: 1) by refusing to submit to the jury the issue of whether UE & C is liable to indemnify PECO; 2) by allowing the jury to consider the testimony of plaintiff’s expert witness on damages for loss of earning capacity; and 3) by assessing delay damages. We find that PECO is not immune from suit and is not entitled to either indemnity from UE & C or a new trial. PECO is therefore liable for the full amount of the verdict awarded by the jury. However, we must remand for a recalculation of delay damages.

I. UE & C’s Appeal

We first consider UE & C’s claim that the evidence was insufficient to establish that UE & C was negligent. Since UE & C appeals from the denial of a motion for judgment n.o.v., we must view all of the evidence, together with all of the reasonable inferences therefrom, in the light most favorable to appellees as verdict winners. Tua v. Brentwood *472 Motor Coach Company, 371 Pa. 570, 572, 92 A.2d 209, 210 (1952); Olson v. Dietz, 347 Pa.Super. 1, 6-8, 500 A.2d 125, 129 (1985). We find that UE & C cannot be held legally responsible for the accident at the Eddystone Plant.

The facts relating to the collapse of the catwalk are as follows. In 1972, PECO entered into a contract with UE & C for the construction of waste water facilities on the premises of the Eddystone Plant. Pursuant to the contract, UE & C was required to design, construct and install a catwalk which would encircle a waste water holding tank at an elevation of twenty-five feet. Both PECO and UE & C were aware that the catwalk would block an access door on the side of the tank which needed to be opened once every few years so that the tank could be cleaned. In order to address this problem, UE & C selected a structural design which would enable PECO to dismantle the portion of the catwalk closest to the access door. UE & C erected a catwalk which consisted of metal grates that were tack-welded to underlying structural supports. This design permitted PECO to gain entrance to the tank by burning through the tackwelds and lifting off the metal grates. PECO approved the design, and never notified UE & C of any problem with how the catwalk was constructed.

In 1978, PECO ordered its employees to remove three grates immediately adjacent to the side of the tank and raise the access door. A welder, with the assistance of a machinist, riggers, and helpers, used an oxygen acetylene torch to melt all of the tackwelds on the grating. William MacGregor, the former head of PECO’s maintenance department, testified at trial that the workers were never instructed to reweld the grates to the supports after the tank had been serviced. MacGregor said that he had simply assumed that the workers would properly reassemble the catwalk.

In 1980, the same process was repeated. PECO employees were directed to open the access door, but the maintenance department did not instruct anyone to restore the welds. The maintenance department also failed to conduct *473 any subsequent inspection to ensure that the structure was in good condition.

On May 5, 1981, the three grates adjacent to the side of the tank slipped out from beneath John Mathis causing him to fall and injure his back. William Mustard, an accident investigator employed by PECO, arrived on the scene and determined that the displaced grates had never been rewelded. Mustard testified that after the welds were removed, the position of the grates had shifted until they no longer rested on their structural supports. Mustard described the condition created by the removal of the welds as an obvious hazard, but he noted that the hazard was apparently not recognized by the PECO craftsmen who left the grates unwelded. PECO had a safety education program for the work force but did not include in this program any instruction on proper catwalk maintenance.

Under these circumstances, there can be little doubt that PECO’s negligent maintenance of the catwalk was the direct cause of John Mathis’ injury. The question on appeal, however, is not whether PECO was negligent but whether UE & C was negligent. Appellees’ theory at trial was that UE & C breached a duty of care owed to workers at the Eddystone Plant by designing a catwalk which could become unstable if PECO did not take necessary safety precautions. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shamis v. James Moon C/O Geppert Brothers, Inc.
81 A.3d 962 (Superior Court of Pennsylvania, 2013)
Claudio v. MGS MacHine Corp.
798 F. Supp. 2d 575 (E.D. Pennsylvania, 2011)
Mahan v. Am-Gard, Inc.
841 A.2d 1052 (Superior Court of Pennsylvania, 2003)
Stout v. Morrisville Supply Corp.
61 Pa. D. & C.4th 191 (Philadelphia County Court of Common Pleas, 2001)
Fye v. Woodland Forrest Products Inc.
39 Pa. D. & C.4th 420 (Clearfield County Court of Common Pleas, 1998)
Connor v. Catagnus
38 Pa. D. & C.4th 27 (Philadelphia County Court of Common Pleas, 1997)
Dougherty v. Conduit & Foundation Corp.
674 A.2d 262 (Superior Court of Pennsylvania, 1996)
Dougherty v. Edward J. Meloney, Inc.
661 A.2d 375 (Superior Court of Pennsylvania, 1995)
Smith v. Workmen's Compensation Appeal Board
618 A.2d 1101 (Commonwealth Court of Pennsylvania, 1992)
Dudley v. USX Corp.
606 A.2d 916 (Superior Court of Pennsylvania, 1992)
Gottshall v. Consolidated Rail Corp.
773 F. Supp. 778 (E.D. Pennsylvania, 1991)
Snyder v. ISC Alloys, Ltd.
772 F. Supp. 244 (W.D. Pennsylvania, 1991)
Rogers v. Johnson & Johnson Products, Inc.
585 A.2d 1004 (Superior Court of Pennsylvania, 1990)
Barlow v. Greenridge Oil Co.
744 F. Supp. 108 (W.D. Pennsylvania, 1990)
Remy v. Michael D'S Carpet Outlets
571 A.2d 446 (Supreme Court of Pennsylvania, 1990)
Jistarri v. Fentress
568 A.2d 618 (Supreme Court of Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
554 A.2d 96, 381 Pa. Super. 466, 1989 Pa. Super. LEXIS 144, 1989 WL 9811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mathis-v-united-engineers-constructors-inc-pa-1989.