Masterclean v. Dept. of Administrative, Unpublished Decision (5-13-1999)

CourtOhio Court of Appeals
DecidedMay 13, 1999
DocketNo. 98AP-727
StatusUnpublished

This text of Masterclean v. Dept. of Administrative, Unpublished Decision (5-13-1999) (Masterclean v. Dept. of Administrative, Unpublished Decision (5-13-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Masterclean v. Dept. of Administrative, Unpublished Decision (5-13-1999), (Ohio Ct. App. 1999).

Opinion

This is an appeal by plaintiff, Masterclean, Inc., from a judgment of the Ohio Court of Claims awarding plaintiff $28,518 on two claims arising from an asbestos abatement contract. The court denied various other claims brought by plaintiff, resulting in the instant appeal.

The underlying action, involving a contract dispute between plaintiff, an asbestos abatement provider, and defendant, the Ohio Department of Administrative Services, was tried before the Court of Claims without a jury. Plaintiff was the successful bidder on a project to perform asbestos abatement of underground tunnels located at the Western Reserve Psychiatric Hospital ("Western Reserve") and the Massillon Psychiatric Hospital ("Massillon"). Plaintiff entered into a contract (contract No. 580-91-027-003-002) with defendant on January 22, 1993, under which plaintiff was to perform the abatement work for a price of $113,459.

Defendant hired Chryatech, Inc. ("Chryatech"), an expert in asbestos abatement, as the contract associate. The contract between plaintiff and defendant provided that plaintiff would do the work according to plans and specifications provided by Chryatech for the removal of asbestos and reinsulation of underground utility pipes. The abatement work first took place at the Massillon site. At issue in the instant case are facts and circumstances surrounding only the work performed at Western Reserve.

Work at the Western Reserve site began on April 4, 1993. Throughout the course of the project, plaintiff submitted to defendant a number of change order requests seeking additional compensation totaling approximately $220,000. While the subject of the various claims will be more fully discussed under the specific assignments of error, the claims at issue include plaintiffs contention that it was entitled to additional compensation for: (1) complying with the preparation of work area requirements set forth in Articles 3.02(I) and 3.02(J) of Section 02080 of the contract; (2) removing debris from tunnels C-21, C-30, C-31 and C-32; (3) removing sidewalk slabs and constructing an above-ground containment structure over certain tunnels; (4) delay by defendant in carrying out a required work inspection; (5) costs attributable to a shutdown of the work site from May 13, 1993 through July 12, 1993; (6) a deduct change order issued by the state reflecting $15,200 paid to Cardinal Environmental Services; and, (7) a theft loss incurred when certain property owned by plaintiff was stolen during a shutdown period.

Plaintiff filed its complaint in the Court of Claims on April 13, 1995, alleging breach of contract and breach of an implied covenant of good faith and fair dealing. Plaintiff's complaint sought damages against defendant in the amount of $224,409.97, plus interest and costs. The matter was tried by the court beginning on June 16, 1997.

The trial court issued a decision on May 11, 1998, finding in favor of plaintiff in the amount of $28,543 on claims involving a shutdown delay period ($23,572) and insulation work ($4,946). The trial court denied plaintiff's claims related to work preparation, debris removal, the removal of sidewalk and construction of an above-ground containment, an alleged inspection delay, plaintiff's theft loss and deduct change order.

On appeal, plaintiff sets forth the following eleven assignments of error for review:

1. THE TRIAL COURT ERRED IN FINDING THAT CONTRACTOR FAILED TO ASSESS THE SCOPE OF THE WORK THROUGH AN INSPECTION WHEN THE WORK TO BE PERFORMED IS EXPRESSLY SET FORTH AND IDENTIFIED BY THE CONTRACT.

2. THE COURT ERRED IN FINDING THAT PLAINTIFF WAS OBLIGATED TO PERFORM ADDITIONAL WORK, WITHOUT COMPENSATION WHEN THE PARTIES ARE UTILIZING A GENERIC SET OF ASBESTOS ABATEMENT SPECIFICATIONS WHICH CONTAIN SPECIFIC EXPRESS PROCEDURES APPLICABLE TO THE ABATEMENT OF TUNNELS, AND THE COURT RELIES UPON SPECIFICATIONS PERTAINING TO ASBESTOS REMOVAL IN AREAS OTHER THAN TUNNELS.

3. WHEN PARTIES CONTRACT ON THE BASIS OF AN AGREEMENT WHICH SPECIFICALLY IDENTIFIES THE TUNNELS FROM WHICH DEBRIS IS TO BE REMOVED, THE COURT ERRED IN FINDING THAT THE CONTRACTOR'S DUTIES WERE EXPANDED BY AN INSPECTION WHICH MAY HAVE DISCLOSED THE EXISTENCE OF DEBRIS IN OTHER TUNNELS ABSENT AN AMENDMENT TO THE CONTRACT RELATING TO SUCH ADDITIONAL WORK.

4. THE COURT ERRED IN FINDING THAT AN AGREEMENT WAS REACHED FOR ADDITIONAL WORK TO BE PERFORMED AT CONTRACTORS COST WHEN THE CONTRACT PROVIDES THAT CONTRACTOR SHALL BE COMPENSATED FOR ADDITIONAL WORK, THE TESTIMONY OF CONTACTORS' WITNESSES IS THAT COMPENSATION WOULD BE PAID; NO TESTIMONY IS PRESENTED IN SUPPORT OF THE ALLEGED AGREEMENT BY THE INDIVIDUAL WHO ALLEGEDLY ENTERED INTO THE AGREEMENT AND NO WRITTEN WAIVER OF PAYMENT WAS OBTAINED EVEN THOUGH THE PRACTICE OF THE PARTIES WAS TO EXECUTE WRITTEN WAIVERS.

5. THE COURT ERRED IN DENYING A CHANGE ORDER REQUEST BASED UPON A FINDING THAT AN EPA CEASE AND DESIST ORDER WAS COMMUNICATED ON MAY 11, 1993, WHEN IN FACT, SAID ORDER WAS NOT COMMUNICATED TO THE CONTRACTING PARTIES UNTIL MAY 13, 1993.

6. WHEN THE COURT FINDS DEFENDANT RESPONSIBLE FOR EQUIPMENT CHARGES ARISING FROM DELAYS IN PERFORMANCE OF WORK ATTRIBUTABLE TO A WRONGFUL CONTRACT TERMINATION; WRONGFUL IMPOSITION OF "DRY REMOVAL" REQUIREMENTS, AND THE UNAVAILABILITY OF ITS ON-SITE REPRESENTATIVE, AND SUCH DELAYS TOTAL 36 DAYS, IT IS ERROR TO AWARD DAMAGES ON THE BASIS OF DEFENDANT BEING RESPONSIBLE FOR A DELAY OF JUST 28 DAYS.

7. GIVEN THAT THE TRIAL COURT FOUND THAT DETERIORATION OF CONDITIONS CAUSING COSTS OF $23,235.91 COULD EASILY HAVE TAKEN PLACE WITHIN JUST 33 DAYS, THE COURT ERRED IN DENYING RECOVERY WHEN THE COURT'S OWN FINDINGS PLACE RESPONSIBILITY FOR MUCH OF THE INITIAL DELAY UPON DEFENDANT.

8. WHERE DEFENDANT HAS ORDERED A CONTRACTOR OFF A WORK SITE AT A STATE MENTAL HEALTH HOSPITAL; HAS ISSUED A CONTRACT TERMINATION NOTICE PURSUANT TO WHICH ALL OF CONTRACTORS EQUIPMENT BECOMES THE PROPERTY OF THE STATE OF OHIO; AND CONTRACTOR IS NOT ALLOWED TO RETURN TO THE SITE WITHOUT APPROVAL FROM DEFENDANT, THE TRIAL COURT ERRED IN DENYING A CHANGE ORDER REIMBURSING CONTRACTOR FOR THE THEFT OF THE EQUIPMENT LOCATED AT THE HOSPITAL BASED UPON A FINDING THAT THE DEFENDANT DID NOT HAVE CONTROL OF CONTRACTORS PROPERTY AT THE TIME SAID PROPERTY WAS STOLEN.

9. THE TRIAL COURT ERRED IN SETTING OFF AGAINST MONIES OTHERWISE PAYABLE TO CONTRACTOR $15,200 IN CHARGES BY A SUBSTITUTE CONTRACTOR WHEN DEFENDANT FAILED TO MEET CONDITIONS PRECEDENT FOR A SET OFF.

10. THE TRIAL COURT ERRED IN MAKING FINDINGS THAT THE WORK OF A SUBSTITUTE CONTRACTOR: (1) WAS FOR THE PURPOSE OF PREVENTING CONTAMINATION OF THE ENTIRE SITE; (2) WAS COSTLY DUE TO HIGH RISK; (3) WAS PERFORMED AT THE LAST MINUTE; AND (4) THAT THE SUBSTITUTE CONTRACTOR STOPPED OTHER PROJECTS TO WORK AT THE SITE, BASED UPON A COMPLETE ABSENCE OF ADMISSIBLE EVIDENCE SUPPORTING SUCH FINDINGS.

11. PREJUDGMENT INTEREST SHOULD BE AWARDED IN ORDER TO COMPENSATE A CONTRACTOR FOR SERVICES RENDERED UNDER A CONTRACT ACCEPTED BY THE STATE OF OHIO ON SEPTEMBER 12, 1994, AND THE TRIAL COURT ERRED IN NEITHER ADDRESSING NOR AWARDING PREJUDGMENT INTEREST.

The instant case involves issues dealing with the interpretation of contract language, as well as the trial court's findings of fact as to circumstances related to the contract. In general, the construction and interpretation of contracts involve matters of law, and an appellate court applies a de novo review of questions of law. Tabeling v. CBCCompanies, Inc. (Mar. 10, 1997), Stark App. No. 1996CA00175, unreported. However, regarding findings of fact, "we will not substitute our judgment for that of the trial court where some competent, credible evidence exists to support the findings of fact and conclusions of law rendered by the trial court."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Masterclean v. Dept. of Administrative, Unpublished Decision (5-13-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/masterclean-v-dept-of-administrative-unpublished-decision-5-13-1999-ohioctapp-1999.