Massaponax Sand & Gravel Corp. v. Virginia Electric & Power Co.

186 S.E. 3, 166 Va. 405, 1936 Va. LEXIS 203
Supreme Court of Virginia·Decided June 11, 1936·Published·Cited by 7 cases

Opinion

Hudgins, J.,

delivered the opinion of the court.

The plaintiff in the trial court, Virginia Electric & Power Company, instituted this action to recover $2,681.83, alleged to be due for electric energy sold and delivered to defendant. Defendant plead the general issue, filed a special plea of set-off, and subsequently offered to amend the special plea. On motion of plaintiff the trial court rejected the special and amended pleas, and on proof of the correctness of the account for power supplied, the court, without a jury, entered a judgment for plaintiff in the sum of $2,437.70.

The only assignment of error is to the ruling of the trial court in rejecting the special pleas. In considering this question, all facts properly alleged and set forth in the pleas are assumed to be true.

The pleas allege that sometime in 1926 plaintiff extended its power line into the Fredericksburg area, and began supplying 60-cycle electric current to defendant and other consumers of the electric energy in that area. The current formerly supplied to defendant and others, was a 25-cycle current; thus it became necessary either to install new motors at defendant’s plant, or to rewind [408] the old motors, so that power could be supplied from 60-cycle current. Plaintiff verbally agreed to make the change in defendant’s motors, and to do so in such a manner as to avoid any increase to defendant in cost of power supplied.

Plaintiff performed this agreement by rewinding all defendant’s motors. When this was done, it was found that the rewound motors consumed much more current than formerly, but plaintiff charged defendant only the monthly sum it had previously paid for power consumed when the 25-cycle current was used.

About this time, but unknown to defendant, on applicacation of plaintiff, the Corporation Commission prescribed a new and higher tariff for power supplied in the Fredericksburg area. Prior to the time the new tariff became effective the charge for power had been based on the electric energy consumed. Under the new tariff there was a provision for both an energy charge, and a demand charge. The form of contract which plaintiff was authorized by the Commission to execute with the consumers of electric energy, provided that:

“Note:—The ‘Demand’ and ‘Energy’ charges included in this schedule are independent of each other, the former covering the demand for which the customer requires the company to provide, the latter covering electrical energy used.

“The demand charges are to cover the company’s fixed investment and operating charges in establishing service and standing ready to serve, and do not include the supply of electricity.

“Wholesale Power Service

“Demand Charge:

First 25 K. W. or less, of Demand—$37.50 per month.

Next 25 K. W. of Demand—$1.25 per K. W. per month. Over 50 K. W. of Demand—$1.00 per K. W. per month.

The above demands shall be taken in accordance with the company’s standard method of fixing demands.

[409] “Energy Charge:

In addition to the demand charges above specified á meter rate will be charged for electricity consumed as follows:

First 1,000 K. W. H. Consumed per month—$0.025.

Next 4,000 K. W. H. Consumed per month—$0.02.

Next 10,000 K. W. H. Consumed per month—$0.015.

Next 35,000 K. W. H. Consumed per month—$0.0125. Excess over 50,000 K. W. H. Consumed per month—$0.01.

“If a minimum demand of 50 K. W. is paid for under a contract for three years the first 10,000 K. W. H. of monthly consumption will be charged for at the rate of .015 per K. W. H., the next 40,000 K. W. H. will be charged for at the rate of 0.125 per K. W. H.

“METHOD OF DETERMINING DEMAND

“The demand is the greatest amount of electricity normally used by the customer at any one period of time. It may be estimated or determined by measurement by the company from time to time, according to the customer’s use of electricity.

“During the construction period, the demand may be estimated as the minimum demand provided for by the rate applied.

“Where service is started under any contract which provides for a demand charge and an additional meter charge, or for a guaranteed consumption based on the customer’s demand, the demand is obtained in the following manner:

“First—By instruments installed to measure the demand:

“(a) When demand measurements are taken, the demand to be used as a basis of charges shall be the maximum thirty (30) minute kilowatt load measured during [410] the current month. This maximum shall he determined by standard meters, or other suitable instruments.

“(b) The demand, when once established, shall never be less than 25 per cent of the highest demand established during the previous eleven months.

“Second—By Estimate:

“(a) When estimated, the demand shall not be taken as less than the minimum provided for under the standard rate in the contract.

“(b) When estimated, the demand shall not be taken as less than one-half of the installation as defined above.

“(c) The company reserves the right at any time to measure the demand where it has been previously estimated, and when so measured, the service shall be paid for on that basis.”

Free access — add to your briefcase to read the full text and ask questions with AI

Massaponax Sand & Gravel Corp. v. Virginia Electric & Power Co., 186 S.E. 3, 166 Va. 405, 1936 Va. LEXIS 203 (Va. 1936).

186 S.E. 3 (Massaponax Sand & Gravel Corp. v. Virginia Electric & Power Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ashland, LLC v. Virginia-American Water Co.
Supreme Court of Virginia, 2022
MCI Telecommunications Corp. v. Graphnet, Inc.
881 F. Supp. 126 (D. New Jersey, 1995)
Cooperative Communications, Inc. v. AT & T CORP.
867 F. Supp. 1511 (D. Utah, 1994)
Pettit v. Chesapeake & Potomac Telephone Co.
28 Va. Cir. 112 (Stafford County Circuit Court, 1992)
Chesapeake & Potomac Tel. Co. of Va. v. Bles
243 S.E.2d 473 (Supreme Court of Virginia, 1978)
Commonwealth v. Virginia Electric & Power Co.
201 S.E.2d 771 (Supreme Court of Virginia, 1974)