Commonwealth ex. rel. Page Milling Co. v. Shenandoah River Light & Power Corp.

115 S.E. 695, 135 Va. 47, 1923 Va. LEXIS 2
CourtSupreme Court of Virginia
DecidedJanuary 18, 1923
StatusPublished
Cited by16 cases

This text of 115 S.E. 695 (Commonwealth ex. rel. Page Milling Co. v. Shenandoah River Light & Power Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth ex. rel. Page Milling Co. v. Shenandoah River Light & Power Corp., 115 S.E. 695, 135 Va. 47, 1923 Va. LEXIS 2 (Va. 1923).

Opinion

Prentis, J.,

delivered the opinion of the conrt.

The jurisdictional question raised in this case has been well argued and a number of questions closely re[52]*52lated to each other have been discussed. We do not think it necessary to follow these elaborate arguments in detail, because, in our view, this question is no longer debatable in this State.

The question is raised by The Page Milling Company, Incorporated (hereinafter called the milling company), which denies the jurisdiction of the State Corporation Commission (hereinafter called the Commission), to regulate the rates to be charged the milling company by the power company, upon the ground that those rates are prescribed and fixed by their contract of January 1, 1907. This question has been so recently examined and passed upon by this court with reference to franchise contracts between municipalities and public service corporations that we deem it unnecessary to do more than to cite these cases and a few decisions from the Supreme Court of the United States and other jurisdictions, relating directly to, such contracts between public utilities and private consumers of their products. Virginia Western Power Co. v. Clifton Forge, 125 Va. 469, 99 S. E. 729, 9 A. L. R. 1148; City of Richmond v. Ches. & Potomac Telephone Co., 127 Va. 612, 105 S. E. 127; Clifton Forge v. Virginia Western Power Co., 129 Va. 377, 106 S. E. 400; Town of Victoria v. Victoria Ice, Light & Power Co., Inc., 134 Va. 134, 114 S. E. 92. In order, however, to appreciate the basis of the contention made for the milling company, it is necessary to make certain recitals of facts. The facts relied on are thus stated in the petition for appeal:

“That The Luray Electric Company, Incorporated, was chartered under the laws of Virginia in the year 1904, with the general powers of an electric company, the charter for which is filed with the petition in this cause. That, by virtue of a contract entered into on February 1, 1905, between The Page Milling Company [53]*53and The Luray Electric Company for a period of three years, The Page Milling Company was to furnish The Luray Electric Company whatever power it needed during that period, in return for which The Luray Electric Company was to furnish, free of charge, electric current for the lighting of the mill of The Page Milling Company, and also to give The Page Milling Company a certain per cent, of the profits derived from the operation of its business, and it was necessary that The Page Milling Company should consent before The Luray Electric Company had power to sell or to dispose of its plant, or any portion thereof. The Luray Electric Company had acquired easements in the streets of the town of Luray and all of the principal service contracts which were available in said town. Its business was a growing and paying one. That, prior to the incorporation of the Luray Electric Company, there existed in the town of Luray a company whose object and duty it was to furnish gas for lighting purposes. After the Luray Electric Company was incorporated and developed, it became necessary' for the owners of the gas company either to go out of business entirely, because the electric service was so far superior to the gas service that every one was beginning to partonize The Luray Electric Company, or else develop an electric plant themselves. Facing this condition, the owners of the gas company incorporated what is known as The Shenandoah River Light and Power Corporation, the defendant in this cause, for the purpose of developing electricity from the water power which they had acquired on the Shenandoah river. So it can be seen, as is also pointed out in the evidence in this cause, that from the very beginning of the operation of The Luray Electric Company it was in competition with the incorporators and stockholders of the then gas company, [54]*54who afterwards incorporated the Shenandoah River Light and Power Corporation, and from the very inception of the incorporation and organization of the Shenandoah River Light and Power Corporation that company was in competition with the Lnray Electric Company. That by virtue of the contract of 1906 between the Shenandoah River Light and Power Corporation and The Page Milling Company, the former obligated itself to furnish to the latter a certain amount of electric power at a stipulated price for a term of twenty years. The consideration for said power on the part of the Page Milling Company was in part the purchase price of its interest in certain property easements and franchises owned by The Luray Electric Company, in part its agreement to furnish the transformers and other electric equipment, as stated in said contract, in part the agreement of The Page Milling Company not to use any other power than that furnished by the Shenandoah River Light and Power Corporation, and in part $.00626561 per K. W. H. for the power to be furnished. * * * The power, as called for under the contract, was in the main, and so far as we are now concerned, furnished by the Shenandoah River Light and Power Corporation to The Page Milling Company, without question, until September 1, 1921, when new rates are claimed to have gone into effect.”

The new rates, of which the milling company is complaining, were made effective merely because they were not suspended by the Commission, in accordance with the regulative statutes first enacted in 1914, now Code, sections 4066 to 4072, inclusive, as amended by the Acts of 1918, page 413.

There is much emphasis placed upon the relations between the milling company and the Luray Electric Company, based upon the fact that the milling [55]*55company organized that company and its stockholders owned a controlling interest in the stock of the Lnray company. While this fact may be worthy of consideration by the Commission if it shall in future undertake or be asked to accord a favorable classification and rate to the milling company, this circumstance does not deny or limit the jurisdiction of the Commission, or affect the proper determination of the jurisdictional question, because it is apparent that there was no copartnership nor identity between these two companies. Indeed there could not be, for they were organized for different purposes and were in every respect separate legal entities. The consideration paid by the appellee, the power company, to the Luray company for its assets constituted the full and complete consideration for that transfer. That there was a consideration for the contract between the milling company and the power company at the time it was entered into is also apparent, but this feature is common to all rate contracts between public service corporations and their patrons claiming thereunder.

Taking up the several contentions of the appellant, •so far as it seems to be necessary, it is claimed:

1. That the acts of 1914 and subsequent enactments, which vested the Commission with the power to control, regulate and prescribe the light and power rates of such public service corporations, operate prospectively only, and that to apply the new schedule of rates which became effective September 1, 1921, to the service furnished the milling company by the power company would be to give these acts a retroactive effect.

The Commission deals with this contention thus:

“Prior to the enactment of the utilities act, all rates of public utility companies were the result of agreement, express or implied, between those companies and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson-Bey v. Commonwealth
Supreme Court of Virginia, 2024
VEPCO v. SCC
Supreme Court of Virginia, 2021
Po River Water & Sewer Co. v. Indian Acres Club of Thornburg, Inc.
495 S.E.2d 478 (Supreme Court of Virginia, 1998)
Chesapeake & Potomac Tel. Co. of Va. v. Bles
243 S.E.2d 473 (Supreme Court of Virginia, 1978)
Appalachian Power Co. v. Federal Power Commission
529 F.2d 342 (D.C. Circuit, 1976)
Commonwealth v. Virginia Electric & Power Co.
201 S.E.2d 771 (Supreme Court of Virginia, 1974)
Bond Bros. v. Louisville & Jefferson County Metropolitan Sewer Dist.
211 S.W.2d 867 (Court of Appeals of Kentucky (pre-1976), 1948)
City of New Haven v. New Haven Water Co.
45 A.2d 831 (Supreme Court of Connecticut, 1946)
Massaponax Sand & Gravel Corp. v. Virginia Electric & Power Co.
186 S.E. 3 (Supreme Court of Virginia, 1936)
Tyrrell & Garth Inv. Co. v. American Title Guaranty Co.
79 S.W.2d 153 (Court of Appeals of Texas, 1934)
Blackwood Coal & Coke Co. v. Old Dominion Power Co.
144 S.E. 439 (Supreme Court of Virginia, 1928)
Chippewa Power Co. v. Railroad Commission
205 N.W. 900 (Wisconsin Supreme Court, 1925)
State v. Andy Scurlock
130 S.E. 263 (West Virginia Supreme Court, 1925)
City of Portsmouth v. Virginia Railway & Power Co.
126 S.E. 366 (Supreme Court of Virginia, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
115 S.E. 695, 135 Va. 47, 1923 Va. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-ex-rel-page-milling-co-v-shenandoah-river-light-power-va-1923.