Massachusetts Bonding & Insurance v. Realty Trust Co.

83 S.E. 210, 142 Ga. 499, 1914 Ga. LEXIS 442
CourtSupreme Court of Georgia
DecidedSeptember 29, 1914
StatusPublished
Cited by25 cases

This text of 83 S.E. 210 (Massachusetts Bonding & Insurance v. Realty Trust Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massachusetts Bonding & Insurance v. Realty Trust Co., 83 S.E. 210, 142 Ga. 499, 1914 Ga. LEXIS 442 (Ga. 1914).

Opinion

Atkinson, J.

(After stating the foregoing facts.)

1. It was contended that the finding of the auditor, that the subcontractors were entitled to liens for the several amounts reported by him, was erroneous for a number of reasons: among them, because the material furnished by the subcontractors was furnished after March 1, 1910, and that up to that time all material purchased or used by the contractor in the construction of the building had been paid for. Several arguments were presented in support of this contention, but the evidence introduced before the [503]*503auditor does not appear in the record before the Supreme Court, and there is nothing to show the dates upon which the materials were furnished, which constituted the basis for the several liens which were sought to be set up. In the absence of evidence introduced before the auditor, or admissions in the pleadings on the subject, we can not say -that, for the reason mentioned, the auditor erred in his finding.

2. Another contention was because, inasmuch as the owner, the Realty Trust Company, procured an affidavit from the contractor upon the payment of each installment, there was a compliance with the statute, which defeats liens of materialmen by the owner’s taking a specified affidavit. The statute mentioned is embodied in the Civil Code, § 3352, and provides that when work is done or material furnished on the employment of a contractor, a lien shall attach upon the real estate improved as against the true owner for the amount of work done and material furnished, unless such true owner shows that such lien has been waived in writing, or produces the sworn statement of the contractor, or other person at whose instance the work was done or material furnished, that the agreed price or reasonable, value thereof has been paid. The manifest purpose of this statute is to make the property of the owner liable for material which entered into the construction of the improvement on the employment of a contractor, within the limits of the. contract price, unless the materialman waives his lien, or. unless, upon the final completion of the work, the true owner, before payment of the contract price, takes from his contractor a sworn statement that all work done or material furnished has been paid for at the agreed price or reasonable value. Only one affidavit by a contractor is contemplated by the statute. To say that a contractor can destroy or perfect a lien, which the statute was designed to establish, by the mere making of a sworn statement, or by the omission to make one, states a very broad power; one that could be exercised without the concurrence or knowledge of the person claiming a lien. The statute contemplated a provision for affording the owner a truthful representation upon which he might act in making final settlement with his contractor, but it was not designed to open wide the doors for the perpetration of wrongs. If more than one affidavit were allowed, it would tend to amplify the opportunity for imposing upon persons claiming liens, particularly so where a num[504]*504ber of persons were asserting liens for material furnished to a contractor for the improvement of the same property. Whether fraudulently or by mistake, the contractor might give sworn statements that some of the claims had been paid, and omit to give sworn statements as to others; thus producing the result that those claims of lien sworn to have been paid for would be lost, and those not mentioned would stand against the property. Such a result would defeat the object of the provisions of another statute, which declares the dignity of liens and the order in which they should be paid. Civil Code, § 3353 (3). This is less apt to occur where only one sworn statement is permitted. Under this construction, ‘if the owner of the premises pays the contractor by installments before completion of the work, he does so at the peril of showing that it was properly applied in discharge of debts for material furnished or work done in the construction of the improvement. He may refuse to pay the contractor until the work is completed and protect himself against liability upon compliance with the statute, or he may pay the contractor from time to time during the progress of the work; but he is not protected by taking separate affidavits that all work done and materials furnished up to that time have been paid for.

3. Another contention was that the statute (Civil Code, § 3352) gives the contractor a lien of equal rank with the lien provided for materialmen, and that the payment to the contractor in discharge of his lien was properly credited upon the contract price, thus reducing to the extent of such payment the amount for which the materialmen could otherwise assert liens. This contention rests upon an improper construction of the statute. The obvious purpose of the statute is to protect materialmen who comply with its terms. If it is held that mere payments to the contractor in discharge of the contract price would defeat the lien of materialmen, the whole statute which undertakes to authorize liens for material-men would be avoided. There would be no necessity for doing more than pay the contractor. If mere payments to the contractor would suffice, why the provision that the owner may be protected by taking the specified affidavit from the contractor? On the subject of contractor’s liens see Tuck v. Moss Mfg. Co., 127 Ga. 729 (56 S. E. 1001); Savannah &c. R. Co. v. Callahan, 49 Ga. 506.

4. Another contention was, that, with four or five exceptions, [505]*505the materialmen, have waived their right to a lien. This waiver is said to have resulted from a contract between the materialmen and the contractor, stipulating that the materialmen will not allow any mechanic’s lien of any kind or character, for materials furnished or work done, to be filed against the improvements therein contracted for, or the ground on which they are to be erected; but will pay for and satisfy as they mature each and every claim incurred by the contractor in and after the furnishing of the material and labor, and will hold him harmless against all such demands and liens as they may be asserted by any persons under or employed by him, or for furnishing materials; and further, that in the event any suits are filed, asserting a claim upon the building or the ground upon which it is to be erected, because of any work done or material furnished in connection with said building, the materialmen will pay off and satisfy such judgments; and that the amounts due them for the material shall not be paid until the contractor shall have received his money from the owner. The argument advanced is, that the tenor and effect of the statute is that the materialmen shall be paid before the contractor shall be entitled to receive his money from the owner, and that the contractor, in order to induce the owner to pay him without liability to the materialmen, contracted with the materialmen that their accounts for material should be paid only from moneys collected by the contractor from the owner; in other words, that such agreement is tantamount to an authorization to the owner to pay the entire contract price (so far as the materialmen are concerned) to the contractor; and that this provision, being in writing, amounted to the waiver contemplated in the statute. There is nothing in the record to show that the owner knew of this contract and acted thereon to his detriment; so that no question of estoppel can arise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Concrete Construction Co. v. Hall
422 S.E.2d 663 (Court of Appeals of Georgia, 1992)
CC & B Industries, Inc. v. Stroud
402 S.E.2d 527 (Court of Appeals of Georgia, 1991)
Mayer Electric Supply Co. v. Federal Insurance
393 S.E.2d 270 (Court of Appeals of Georgia, 1990)
Star Manufacturing, Inc. v. Edenfield
382 S.E.2d 706 (Court of Appeals of Georgia, 1989)
Amafra Enterprises, Inc. v. All-Steel Buildings, Inc.
313 S.E.2d 110 (Court of Appeals of Georgia, 1984)
M.C. Anderson v. Golden
569 F. Supp. 122 (S.D. Georgia, 1982)
C. E. Self & Son v. Jerome
288 S.E.2d 359 (Court of Appeals of Georgia, 1982)
AAA Plastering Co. v. TPM Constructors, Inc.
277 S.E.2d 910 (Supreme Court of Georgia, 1981)
Henderson v. Mitchell Engineering Co.
279 S.E.2d 750 (Court of Appeals of Georgia, 1981)
M. Shapiro & Sons, Inc. v. Yates Construction Co.
231 S.E.2d 497 (Court of Appeals of Georgia, 1976)
Bankston v. Smith
216 S.E.2d 634 (Court of Appeals of Georgia, 1975)
Short & Paulk Supply Co. v. Dykes
171 S.E.2d 782 (Court of Appeals of Georgia, 1969)
Solomon v. Robert Spector Lumber Co.
137 S.E.2d 473 (Court of Appeals of Georgia, 1964)
Peachtree Roxboro Corp. v. United States Casualty Co.
114 S.E.2d 49 (Court of Appeals of Georgia, 1960)
Cheshire v. Engelhart
61 S.E.2d 434 (Court of Appeals of Georgia, 1950)
Gignilliat v. West Lumber Co.
56 S.E.2d 841 (Court of Appeals of Georgia, 1949)
Herb v. Wolfe
41 S.E.2d 817 (Court of Appeals of Georgia, 1947)
J. B. Withers Cigar Co. v. Kirkpatrick
26 S.E.2d 255 (Supreme Court of Georgia, 1943)
Smith v. Walker
22 S.E.2d 160 (Supreme Court of Georgia, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
83 S.E. 210, 142 Ga. 499, 1914 Ga. LEXIS 442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massachusetts-bonding-insurance-v-realty-trust-co-ga-1914.