Marvin Safe Co. v. Ward

46 N.J.L. 19
CourtSupreme Court of New Jersey
DecidedFebruary 15, 1884
StatusPublished
Cited by8 cases

This text of 46 N.J.L. 19 (Marvin Safe Co. v. Ward) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marvin Safe Co. v. Ward, 46 N.J.L. 19 (N.J. 1884).

Opinion

The opinion of the court was delivered by

Depue, J.

The principal defendants, the boards of chosen freeholders of the counties of Essex and Hudson, became entitled to the property and franchises of “ The Proprietors of the Bridges over the Rivers Passaic and Hackensack,” under proceedings taken under an act of the legislature passed March 14th, 1871. Pamph. L., p. 500. The legislation in relation to those bridges prior to the act of 1871, is stated in Ripley v. Chosen Freeholders, 11 Vroom 45.

The bridge over the Passaic having become unsafe and unfit for use, the boards of chosen freeholders of the two counties, on the 21st of August, 1881, contracted with Ward, the other defendant, for the erection of a new bridge. This contract is under seal, and in two parts—each board having made a separate contract for the same work, identical in terms, and each covenanting to pay a sum which is one-half of the contract price. Each contract provides for a temporary roadway or bridge, to accommodate the travel whilst the permanent bridge was being constructed.

Ward entered upon the performance of the work, and constructed a temporary bridge. This temporary bridge, on the 15th of November, 1881, gave way whilst a team of the plaintiff was being driven over it, whereby the plaintiff’s team and truck, and its load were precipitated into the river. For the damages sustained the plaintiff’s sued the boards of freeholders of the two counties, and Ward, the contractor, in one suit in the form of an action on the case. Tlie case is before the court at this time on a demurrer to one of the pleas filed by Ward.

The contracts between Ward and his co-defendants stipulate that the work should be commenced on or before the 15th of September, 1881, and that the permanent bridge should be completed and ready for travel within twenty-nine working [21]*21days from that date, with an agreement that $50 should be deducted from the contract price for each day the work should be delayed beyond the specified time; and there are allegations in the declaration of negligence in the failure to complete the bridge within the time fixed by the contract. The stipulation on this subject must be laid out of the case in every phase of this litigation; for the duty to provide bridges suitable and proper for travel, is a public duty, and the general rule is that, independent of a statute, no suit will lie against the public authorities for the recovery of damages occasioned by the mere non-performance of such a duty—the remedy being by indictment or mandamus. Reock v. Mayor, &c., of Newark, 4 Vroom 129; Pray v. Jersey City, 3 Vroom 394; Stew. Dig., tit. “Bridges,” p. 112, § 14. The statute (Rev., p. 1017, § 121,) which was before the court in Livermore v. Freeholders, 5 Dutcher 245; S. C., 2 Vroom 507, does not apply to the mere omission or delay in the completion of the work. It relates to injuries sustained by travelers, arising from the insufficiency or want of repair of a. bridge in actual use, and leaves intact, in other respects, the general doctrine of the law that a suit cannot be maintained for the omission by public authorities to perform a public duty. Nor will the act of 1860, (Rev.,p. 86, § 9,) which was before the court in Ripley v. Freeholders, aid the plaintiff in this respect. The engagement of Ward to complete the work within a designated time was wholly a matter of contract between him and the boards of freeholders. If the freeholders saw fit, they might give the contractor further time, or indulge him in delays in the progress of the work, without subjecting him to liability for the inconvenience suffered by individuals, and they provided the means of securing the completion of the work within the stipulated time by a per diem deduction from the contract price.

The plaintiff’s case, as it relates to each and all of the defendants, is restricted to the cause of actioa arising from the alleged unsafe condition of the temporary bridge.

The declaration commences with an allegation of the duty of the board of freeholders of the two counties to keep and [22]*22maintain the bridge and draw in good repair, so that it would at all times be safe and in good condition for the passage of horses and vehicles, with their loads, over and across said bridge.

The allegations on this head, so far as they relate to Ward, are that, by his contracts with his co-defendants, he agreed that he would, on or before the 15th day of September, 1881, erect a good, substantial temporary roadway over said river and the approaches to the same, according to the specifications to the said contract annexed—such temporary roadway to remain until the completion of the bridge, and that he, the said Ward,' should be liable for all damages sustained by reason of any defective or improper construction of said work. It is also averred that, by the specifications annexed to the contracts and referred to therein and made part thereof, it was provided that the said contractor should execute the whole work provided for, and that the travel should be accommodated by means of a temporary roadway at least twenty feet wide, and a draw forty feet opening, that could be easily worked by one man, and that if more than one man was required, said Ward was to furnish another.

The declaration then avers that by reason of the premises, it became and was the duty of all the defendants to construct and cause to be constructed the said temporary roadway and draw in a good and sufficient manner, so as to make it sufficiently strong and safe for the passage of horses, wagons and their loads, over and across the same.

The breach assigned, is, that the defendants did not construct or cause to be constructed across said river the temporary roadway and draw in a good and sufficient manner, &c.,. but did construct said temporary roadway and draw in such a weak, unsafe, improper and insecure manner as to render the same wholly unfit for the accommodation of the public travel.

To this declaration Ward filed several pleas, in one of which he pleaded that he constructed the said temporary roadway and draw in the manner and according to the plans and specifications mentioned and referred to in his said contracts, [23]*23and according to the directions of the said boards of freeholders, and that he did not omit anything required of him by the terms of the said contracts; so that, if the said temporary roadway and draw were not sufficient for the purpose intended, and for the accommodation of the public travel, it was not his neglect or default.

To the latter plea this demurrer was filed.

The declaration sets out in detail the terms of the contract between Ward and his co-defendants. His undertakings with them under his contracts are minutely and with particularity spread upon the face of the declaration in the form of averments, which make his contractual duties the gravamen of the plaintiff’s cause of action against him-. His undertakings with his co-defendants are prominently made a premise from which is deduced the duty on his part on the non-performance of which the plaintiffs place their right to recover of him, in common with the other defendants, damages for the injury sustained, and his covenant to make good to his co-defendants damages sustained by reason of defective or improper construction of the work, appears among the averments which lead to the duty counted upon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gold Mills, Inc. v. Orbit Processing Corp.
297 A.2d 203 (New Jersey Superior Court App Division, 1972)
Westerhold v. Carroll
419 S.W.2d 73 (Supreme Court of Missouri, 1967)
Miller v. Muscarelle
170 A.2d 437 (New Jersey Superior Court App Division, 1961)
Sandler v. NJ Realty Title Ins. Co.
169 A.2d 735 (New Jersey Superior Court App Division, 1961)
Trecartin v. Mahony-Troast Construction Co.
87 A.2d 349 (New Jersey Superior Court App Division, 1952)
Roberts v. Geo. M. Brewster & Son, Inc.
80 A.2d 638 (New Jersey Superior Court App Division, 1951)
Colligan v. 680 Newark Avenue Realty Corp.
37 A.2d 206 (Supreme Court of New Jersey, 1944)
Sterchi Bros. Stores, Inc. v. Castleberry
182 So. 474 (Supreme Court of Alabama, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
46 N.J.L. 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marvin-safe-co-v-ward-nj-1884.