Agid, J.
Hydraulic Fishing Supply, Inc., appeals from an order denying its motion to vacate the judgment confirming the arbitration award made to respondent, Patrick C. Martin. In October 1985, Hydraulic Fishing Supply, Inc. (HFS) entered into a contract with Patrick C. Martin (Martin) to build an aluminum fishing boat pursuant to Martin's specifications for use in the False Pass gill net fishery in Alaska. The contract specified January 15,1986, as the date by which construction was to be completed and provided for liquidated damages if sea trials were not completed by specific dates. At the time the contract was entered into, the parties anticipated that Martin would complete substantial portions of the vessel himself after the delivery date. On December 3, 1985, a document was signed reratifying the contract and acknowledging that changes in certain specifications were within the contract.
Construction was not completed by the date specified in the contract. As HFS continued its work on the vessel, Martin worked simultaneously to complete his portions. On May 23, 1986, prior to launching the vessel and turning it over to Martin, HFS and Martin entered into an agreement providing that Martin would sign a $10,000 promissory note in consideration for extra engineering time, and that liquidated damages provided for in the October 29, 1985, agreement would be waived by Martin upon satisfactory completion of sea trials. The vessel was launched on May 24, 1986. Additional work was performed on the vessel in Seattle, and sea trials were conducted on June 4, 1986. The vessel left for False Pass, Alaska, on June 8 and arrived approximately 10 days later. After the fishing season, Martin returned the vessel to HFS for certain warranty repairs and disputes again arose between the parties. Martin failed [372]*372to make the payment on the $10,000 promissory note which was due October 1, 1987.
HFS filed suit in Seattle District Court on December 1, 1987, to recover payment on the $10,000 promissory note. On March 28, 1988, the Seattle District Court ordered that the case be arbitrated pursuant to contract and, as required by RCW 7.04.030, stayed further court action pending completion of the arbitration proceedings. In response to a motion by HFS to compel arbitration pursuant to RCW 7.04.040, the parties stipulated that an arbitrator would be appointed by September 1990. The arbitration hearing was conducted by Arbitrator Michael Barcott on December 11, 1990, and the arbitration award was issued December 21, 1990.
On December 28, 1990, Martin filed a petition seeking confirmation of the arbitration award in King County Superior Court. The King County Superior Court entered judgment on January 9, 1991, confirming the arbitration award with costs in the amount of $112,703. HFS filed a motion to vacate the arbitration award and judgment on February 28, 1991.1 That motion was denied on March 21, 1991, and a notice of appeal was filed April 2, 1991. HFS appeals the trial court's order denying its motion to vacate the judgment confirming the arbitration award and requests that this matter be remanded to the Superior Court for resubmission of the counterclaim to arbitration.
I
Arbitration in Washington is regulated by statute. Puget Sound Bridge & Dredging Co. v. Lake Wash. Shipyards, 1 Wn.2d 401, 405, 96 P.2d 257 (1939); RCW 7.04. RCW 7.04-.180 provides that notice of a motion to vacate an arbitration award must be served upon the adverse party within 3 months after the award is delivered to the party or his or her attorney.2 The motion to vacate here was filed on February 28, 1991, within the 3-month statutory period.
[373]*373Respondent argues, however, that the language of RCW 7.04.150, which gives parties the option of applying to a court for an order confirming an arbitration award within 1 year of the award, requires that a motion to vacate be made prior to the entry of a judgment confirming the award.3 That section provides that "the court shall grant such an order... unless the award is vacated, modified, or corrected, as provided in RCW 7.04.160 and 7.04.170." Martin argues that this language presumes that vacation, modification or correction of the award would precede its confirmation.
Martin applied for the order confirming the arbitration award 1 week after it was issued and 2 months before the motion to vacate permitted by RCW 7.04.180 was filed. The judgment confirming the award was entered on Januaiy 9, 1991. Although it is clear that a court cannot confirm in its original form an arbitration award that has been modified, vacated or corrected, neither RCW 7.04.150 nor RCW 7.04-.180 directly addresses the question of whether, once a judgment has been entered confirming an award, a motion to vacate can still be made within the statutory 3-month period. The 5 days' notice required by RCW 7.04.150 for a motion to confirm, taken together with RCW 7.04.180's grant of authority to a judge to stay proceedings on a motion to confirm brought under RCW 7.04.150, could be construed as requiring a party to make known any intention to file a motion to vacate, modify, or correct an award within the [374]*374notice period and prior to entry of an order and judgment confirming the award.
On the other hand, the fact that RCW 7.04.150 refers to the vacation, modification or correction of an award in the present rather than the past tense appears to mean that RCW 7.04.150 is not intended to cut off a party's rights under RCW 7.04.180 before the 3-month period it provides for has expired. While RCW 7.04.220
Free access — add to your briefcase to read the full text and ask questions with AI
Agid, J.
Hydraulic Fishing Supply, Inc., appeals from an order denying its motion to vacate the judgment confirming the arbitration award made to respondent, Patrick C. Martin. In October 1985, Hydraulic Fishing Supply, Inc. (HFS) entered into a contract with Patrick C. Martin (Martin) to build an aluminum fishing boat pursuant to Martin's specifications for use in the False Pass gill net fishery in Alaska. The contract specified January 15,1986, as the date by which construction was to be completed and provided for liquidated damages if sea trials were not completed by specific dates. At the time the contract was entered into, the parties anticipated that Martin would complete substantial portions of the vessel himself after the delivery date. On December 3, 1985, a document was signed reratifying the contract and acknowledging that changes in certain specifications were within the contract.
Construction was not completed by the date specified in the contract. As HFS continued its work on the vessel, Martin worked simultaneously to complete his portions. On May 23, 1986, prior to launching the vessel and turning it over to Martin, HFS and Martin entered into an agreement providing that Martin would sign a $10,000 promissory note in consideration for extra engineering time, and that liquidated damages provided for in the October 29, 1985, agreement would be waived by Martin upon satisfactory completion of sea trials. The vessel was launched on May 24, 1986. Additional work was performed on the vessel in Seattle, and sea trials were conducted on June 4, 1986. The vessel left for False Pass, Alaska, on June 8 and arrived approximately 10 days later. After the fishing season, Martin returned the vessel to HFS for certain warranty repairs and disputes again arose between the parties. Martin failed [372]*372to make the payment on the $10,000 promissory note which was due October 1, 1987.
HFS filed suit in Seattle District Court on December 1, 1987, to recover payment on the $10,000 promissory note. On March 28, 1988, the Seattle District Court ordered that the case be arbitrated pursuant to contract and, as required by RCW 7.04.030, stayed further court action pending completion of the arbitration proceedings. In response to a motion by HFS to compel arbitration pursuant to RCW 7.04.040, the parties stipulated that an arbitrator would be appointed by September 1990. The arbitration hearing was conducted by Arbitrator Michael Barcott on December 11, 1990, and the arbitration award was issued December 21, 1990.
On December 28, 1990, Martin filed a petition seeking confirmation of the arbitration award in King County Superior Court. The King County Superior Court entered judgment on January 9, 1991, confirming the arbitration award with costs in the amount of $112,703. HFS filed a motion to vacate the arbitration award and judgment on February 28, 1991.1 That motion was denied on March 21, 1991, and a notice of appeal was filed April 2, 1991. HFS appeals the trial court's order denying its motion to vacate the judgment confirming the arbitration award and requests that this matter be remanded to the Superior Court for resubmission of the counterclaim to arbitration.
I
Arbitration in Washington is regulated by statute. Puget Sound Bridge & Dredging Co. v. Lake Wash. Shipyards, 1 Wn.2d 401, 405, 96 P.2d 257 (1939); RCW 7.04. RCW 7.04-.180 provides that notice of a motion to vacate an arbitration award must be served upon the adverse party within 3 months after the award is delivered to the party or his or her attorney.2 The motion to vacate here was filed on February 28, 1991, within the 3-month statutory period.
[373]*373Respondent argues, however, that the language of RCW 7.04.150, which gives parties the option of applying to a court for an order confirming an arbitration award within 1 year of the award, requires that a motion to vacate be made prior to the entry of a judgment confirming the award.3 That section provides that "the court shall grant such an order... unless the award is vacated, modified, or corrected, as provided in RCW 7.04.160 and 7.04.170." Martin argues that this language presumes that vacation, modification or correction of the award would precede its confirmation.
Martin applied for the order confirming the arbitration award 1 week after it was issued and 2 months before the motion to vacate permitted by RCW 7.04.180 was filed. The judgment confirming the award was entered on Januaiy 9, 1991. Although it is clear that a court cannot confirm in its original form an arbitration award that has been modified, vacated or corrected, neither RCW 7.04.150 nor RCW 7.04-.180 directly addresses the question of whether, once a judgment has been entered confirming an award, a motion to vacate can still be made within the statutory 3-month period. The 5 days' notice required by RCW 7.04.150 for a motion to confirm, taken together with RCW 7.04.180's grant of authority to a judge to stay proceedings on a motion to confirm brought under RCW 7.04.150, could be construed as requiring a party to make known any intention to file a motion to vacate, modify, or correct an award within the [374]*374notice period and prior to entry of an order and judgment confirming the award.
On the other hand, the fact that RCW 7.04.150 refers to the vacation, modification or correction of an award in the present rather than the past tense appears to mean that RCW 7.04.150 is not intended to cut off a party's rights under RCW 7.04.180 before the 3-month period it provides for has expired. While RCW 7.04.220 provides that an appeal may be taken from a judgment entered upon an award as from an order or judgment on any civil action, it too does not explicitly limit any further review of such a judgment to a direct appeal from that judgment. In the absence of any provision explicitly providing that a party's rights under RCW 7.04.180 are limited by the entry of an order confirming the judgment under RCW 7.04.150, we must conclude that the motion to vacate the judgment here was permissible under RCW 7.04.180.4
II
Review of an arbitration proceeding by an appellate court is controlled by RCW 7.04, which strictly limits review to the grounds contained in RCW 7.04.160-.170. Barnett v. Hicks, 119 Wn.2d 151, 154, 829 P.2d 1087 (1992). Review on the merits other than on statutory grounds is not permitted. Barnett, 119 Wn.2d at 153. RCW 7.04.220, which provides that an order affirming an arbitration award be treated as a civil judgment, does not alter this proscription. Barnett, 119 Wn.2d at 157.
RCW 7.04.160 permits a motion to vacate an arbitration award to be brought in certain specific circumstances, including:
[375]*375Vacation of award — Rehearing. In any of the following cases the court shall after notice and hearing make an order vacating the award, upon the application of any party to the arbitration:
(3) Where the arbitrators were guilty of misconduct, in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence, pertinent and material to the controversy; or of any other misbehavior, by which the rights of any party have been prejudiced.
(5) If there was no valid submission or arbitration agreement and the proceeding was instituted without either serving a notice of intention to arbitrate, as provided in RCW 7.04-.060, or without serving a motion to compel arbitration, as provided in RCW 7.04.040(1).
In its motion to vacate the arbitration award, HFS relied on RCW 7.04.160(3) (misconduct) and (5) (lack of valid submission of Martin's counterclaim to arbitration), arguing that, because Martin failed to give notice under RCW 7.04-.060 of his intent to arbitrate his claim as a counterclaim, the arbitrator was guilty of misconduct in failing to postpone the hearing.5
RCW 7.04.060 provides that when a controversy arises from a written agreement containing an arbitration provision, a party shall serve upon the other party written notice of his intention to arbitrate. Nothing in the language of RCW 7.04.060, however, requires particularized notice of any individual claims or counterclaims or suggests that the notice is intended to communicate anything more than the parly's general intention to proceed to arbitration.6 Because [376]*376RCW 7.04.060 does not require inclusion of the specific nature of individual counterclaims in a notice of intent to arbitrate, there is no basis for vacating the award under RCW 7.04.160(5).
Further, although HFS was not formally notified of the specific nature of Martin's counterclaims for lost fishing profits and liquidated damages until 4 days prior to the date of the arbitration hearing, HFS was effectively notified of those claims on approximately November 16, 1990, by copy of Martin's letter of that date to the arbitrator.7
HFS also argues that, because the dispute here was limited to the May 1986 agreement in which Martin agreed to sign the promissory note upon which its claim was brought, the arbitration clause in that agreement did not encompass Martin's counterclaims. However, the terms of the May 1986 agreement provided that Martin would waive the liquidated damages to which he was entitled under the October 1985 agreement. As a result, any dispute about whether payment was due under the May 1986 agreement necessarily implicated the October 1985 agreement. HFS therefore can hardly have been surprised, let alone prejudiced, to discover that Martin's defense to his failure to pay the $10,000 note would be that payment was not due because the agreement was not binding and, as a consequence, he was entitled to liquidated damages under the original agreement.
[377]*377The question remains whether there is a basis for vacating the judgment under RCW 7.04.160(3). That provision permits the court to modify, vacate or correct an agreement where there has been misconduct on the part of an arbitrator in refusing to postpone a hearing. Although HFS apparently objected at the arbitration hearing on the ground that it lacked adequate notice of Martin's counterclaim, it made no request for a continuance on that basis, either during the proceedings or in its postafbitration brief. In the absence of any request that the hearing be continued, the arbitrator's failure to postpone the hearing cannot amount to misconduct. Endicott Educ. Ass'n v. Endicott Sch. Dist. 308, 43 Wn. App. 392, 396, 717 P.2d 763 (1986). Absent misconduct on the part of the arbitrator, there is no basis for vacating the judgment under RCW 7.04.160(3). The trial court properly denied the motion to vacate the judgment confirming the arbitration award.
Affirmed.
Webster, A.C.J., concurs.