Marion County v. Foxworth

83 Miss. 677
CourtMississippi Supreme Court
DecidedOctober 15, 1903
StatusPublished
Cited by18 cases

This text of 83 Miss. 677 (Marion County v. Foxworth) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marion County v. Foxworth, 83 Miss. 677 (Mich. 1903).

Opinion

Truly, J'.,

delivered the opinion of the court.

The board of supervisors of Marion county, at s. meeting regularly held in December, 1896, awarded to appellee a contract to construct a steel bridge across Pearl river- near Columbia, in that county, for the sum of 816,000, to be paid on the 1st of January, 1898. The order recites that the bid of Fox-worth to furnish and construct said bridge according to the plans and specifications on file was accepted by the board, and “the president hereof authorized to sign on behalf of this board any and all contracts (which contract for the building of such bridge was and is approved by this board in open session, and signed by the president for the board by its direction).” The said order further provided that the president of the board was “specially authorized to release said contractor or his assigns from the time limit in said contract for the completion of said [685]*685bridge as be may deem fit and proper, and all according to tbe term's of said contract read to, and thereby fully approved by, said board.” The contract referred to in the order contained this provision: “It is further agreed that in case any change, modification or addition shall be made in the plans and specifications of said bridge or any change in the location thereof shall be made, then and in that event, additional time for completion and additional compensation shall be agreed to in writing between the parties hereto. Nor shall the contractor be held responsible for unavoidable delays caused by the United States authorities failing to approve the location of the bridge, or in the transportation, or by the elements, mobs or enemies of the government, strikes of working men in the employ of the contractor or his assigns, or of manufactories under contract with him for the furnishing of materials, for such acts of providence, or delays over which they have no control.” Subsequently, and before work was actually commenced upon the structure, the contractor notified the board, on June 8, 1897, that certain extra work was necessary for the stability and protection of the proposed bridge, and that this extra work consisted of certain piles to be driven in the center and end cylinders at a location shown by plans which accompanied the communication, wdiich entailed the use of additional lumber, concrete, spikes, etc. Further, a fender for the protection of the center pier, to extend from the -center cylinder up stream far enough to completely protect the upstream end of the bridge when swung open, and a cluster of piles to be built below the bridge for the protection of the downstream end of the bridge when swung open; and the end cylinders of the bridge were to be increased in size as shown by the plans. This proposal stated definitely the price which was to be charged for the material to be used in each particular portion of the proposed extra work. This proposal was, by order of the board, filed with the bridge plans, and the following order was pláeed on the minutes of the board: “It is ordered by the board that the plans proposed by the bridge contractor to pile center [686]*686and west pier of bridge across Pearl river be adopted by the board. Also erection of fenders above bridge, and rest piles below the bridge, all of which is shown in drawing and specifications presented and ordered filed with the old plans and specifications of the bridge.” The plan and location of the bridge were not approved by the United States authorities until July 1, 1897. Subsequently, at its September meeting, the board, by order, extended the time for the completion of the bridge until the 1st day of December, 1897. The bridge was not completed until 111 days thereafter. After the bridge was completed and accepted by the board the contractor filed his account before the board for $19,215.40; $16,000 being the contract price for the bridge and $3,215.40 being the extra work, including the fenders both above and below the bridge. The boai’d refused to pay any of the account for extra work, and deducted $10 per day for the 111 days’ delay in the completion of the bridge after the 1st day of December, 1897. Thereupon the appellee filed his bill of complaint in the chancery court, setting up these facts, and averring that the delay was caused by the contingencies mentioned and provided against in his contract, and that therefore the board had no right to penalize him by reserving this. $1,110; further, that the bill for extra work was in accordance with the proposal for the same which had been adopted by the board, and that all of such extra work was absolutely necessary for the proper construction of the bridge, -and to insure its safety and stability after it was erected. The board of supervisors, in their answer, admitted the awarding of the contract, but contended that the delay in the completion of the bridge was not caused by any of the contingencies mentioned in the contract, and, as to • the extra work, averred .that the same was not necessary for the proper construction of the bridge, or for its stability and protection, and further, that the county was not bound to pay for said extra work, because there was no contract agreement to pay therefor duly and legally made; that the order adopting the plans for the extra work was not an acceptance thereof, nor did [687]*687it constitute a contract to pay for the same; that this extra work was in fact the nature of another piece of work; and that the board could not have contracted for such work without first advertising for sealed bids ag' required by law. It was admitted that no advertisement was made in reference to the extra work. On final hearing the chancellor decreed that the appellee was entitled to recover the $1,110 withheld by the county as a penalty for failure to complete the bridge at the date contracted for, and that he was entitled to recover the full amount charged for the .extra work. From that decree the county prosecutes this appeal.

The question here presented is what power the board of supervisors of a county has in reference to additional or extra work thought necessary for the completion of any public work already contracted for. This subject has been treated of by this court on several occasions heretofore, and we see no reason for changing the rule announced in previous adjudications, so far as applicable to the state of the ease here made. In every public work of any considerable magnitude it must often, if not invariably, happen during the progress of the building that some deviations from the plans and specifications as originally adopted will be found necessary: some difference in the nature and character of the foundation, some change of location deemed advisable, will inevitably demand modifications, to a greater or lesser extent, in the original plan. This is peculiarly the case in constructing bridges over streams. A trivial mistake in the measurement of the channel to be spanned, a slight change of location, a difference in the nature of the soil in which the foundation must be imbedded, will each require certain absolutely necessary changes, which must be made in order to insure a secure and stable structure. The board of supervisors, as a body, had the right to contract for such changes and additions without going through the formality of an advertisement for sealed bids. The exigencies of the occasion, the fact that these defects can only be discovered while the work is in actual progress, render it im[688]*688practicable, if not impossible, to delay until such advertisements should b© made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KPMG, LLP v. Singing River Health System
Mississippi Supreme Court, 2018
Greene County v. Corporate Management, Inc.
10 So. 3d 424 (Mississippi Supreme Court, 2009)
Community Extended Care Centers, Inc. v. Board of Supervisors
756 So. 2d 798 (Court of Appeals of Mississippi, 1999)
Thompson v. JONES CTY. COMMUNITY HOSPITAL
352 So. 2d 795 (Mississippi Supreme Court, 1977)
Arkansas Fuel Oil Co. v. City of Oxford
195 So. 316 (Mississippi Supreme Court, 1940)
Columbian Iron Works v. Town of Decatur
159 So. 97 (Mississippi Supreme Court, 1935)
Pearl Realty Co. v. State Highway Commission
154 So. 292 (Mississippi Supreme Court, 1934)
Board of Sup'rs v. Cooper
112 So. 682 (Mississippi Supreme Court, 1927)
Corinth to Gulf Highway v. Carothers & Co.
92 So. 696 (Mississippi Supreme Court, 1922)
Smith County v. Mangum
89 So. 913 (Mississippi Supreme Court, 1921)
Campbell v. Morrison
81 So. 120 (Mississippi Supreme Court, 1919)
County of Escambia v. Blount Construction Co.
62 So. 650 (Supreme Court of Florida, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
83 Miss. 677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marion-county-v-foxworth-miss-1903.