Mann v. Town of Rochester

63 N.E. 874, 29 Ind. App. 12, 1902 Ind. App. LEXIS 95
CourtIndiana Court of Appeals
DecidedApril 29, 1902
DocketNo. 3,588
StatusPublished
Cited by4 cases

This text of 63 N.E. 874 (Mann v. Town of Rochester) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mann v. Town of Rochester, 63 N.E. 874, 29 Ind. App. 12, 1902 Ind. App. LEXIS 95 (Ind. Ct. App. 1902).

Opinion

Black, J.

It was further alleged that the board, having so adopted plans and specifications, and having thus given notice, decided, on the 25th of April, 1893, to purchase the pipe for the system, and that it would let only the laying of the pipe, with the necessary work of putting it down and furnishing [14]*14the lead and hemp therefor; that the appellants were informed by the board of its purpose to so let the work, and therefore submitted a bid, accompanied by a deposit check as provided for in said notice or letting, which bid was sealed and handed in to the board, as follows: “Proposal for pipe laying by Mann & Andrew, of Dowagiac, Mich. To the honorable, the president and board of trustees of the corporation of Bochester, Ind. We beg leave to submit the following proposal: We will furnish all lead, hemp, and all tools necessary, and lay your pipe in the best possible manner, for the following prices for cast iron pipe: For 4-in. pipe, 12c. per foot; for 6in. pipe, 14c. per foot; for 8in. pipe, 16c. per foot; for 10in. pipe, 18c. per foot; for 12in. pipe, 21c. per foot,- — we setting all gates, gate-boxes, spen cials, and hydrants without extra cost to the corporation. Annexed find certified check for $250,” — signed by the appellants. It was alleged that this bid was in the aggregate sum of $5,200; that the board accepted the bid “and caused to be entered of record the following: ‘Mann & Andrew, of Dowagiac, Mich., was awarded the contract for laying of pipe,’ etc.; and in pursuance of said award, the said board directed its attorney, Virgil S. Beiter, by an entry of record as follows: ‘The board then instructed said Beiter to prepare a contract for said work, and forward the same to Mann & Andrew, at Dowagiac, Michigan, which he did.’ ”

It was alleged that it was stipulated in said contract that the appellants would lay the pipes for the system of water-works as proposed in said town, to the extent of seven and one-fourth miles, furnishing all lead, hemp, and all tools necessary, ■ and labor, and lay the pipe in the best possible manner, for the following prices: Oast iron pipe, etc., setting out the prices as in the bid of the appellants, they setting all gates, gate-boxes, specials and hydrants, without extra cost to the corporation, for the aggregate sum of $5,200; that they would begin the work as soon as [15]*15the weather would permit, and complete the same within six months, which cost of construction was to "be paid when the work should be completed; that the appellants received the contract in due course of mail, and signed and accepted the same; that they also procured a bond conformably with the requirements and conditions of the letting of the work, which bond was executed by the American Surety Company of Mew York City; that after the signing of the contract by the appellants and the execution of the bond, the appellants sealed up the same in a large envelope, and addressed the same to the appellee, at Rochester, Indiana, and duly mailed the same to it; that the appellee received and accepted the same; “since which time, however, the said plaintiffs, nor either of them, have not seen said bond or contract, and they say the same, at the commencement of this cause of action, was either lost or destroyed, wholly without fault or negligence of said plaintiffs or either of them, and cannot now be ;found, for which reason no exact copy of either can be given, and they have to make oral proof thereof;” that immediately following the mailing of the contract they gathered together, at great expense, their necessary tools, engaged the necessary lead and hemp to lay the pipe, according to the plans and specifications and the terms and conditions of the contract, and employed laborers to perform the work; “and that they did then and there and do now stand ready and willing to perform all and singular the obligations incident to the completion of the work of laying the pipes for a system of water-works, and the performance of said contract as adopted by said defendant, at and before the letting of said contract;” that, although the appellants “did then and do now stand ready to perform all and singular the obligations under the terms and conditions of their contract and bond,” the appellee refused to allow them to do the work or any part of it, notwithstanding all of the work was within the corporate limits of the town, and was under the control of the board of trustees and the [16]*16officers of the town; that, by reason of the refusal of the appellee to allow the work to be done according to the terms and conditions of the contract, the appellants have suffered a great loss of money and time, “and that a reasonable compensation of their rights and profits, the loss of which they have suffered wholly by reason of the violation of the terms and conditions of the contract by the defendant, is in the sum of $2,000; wherefore,” etc. The second paragraph of complaint was like the first, with the additional averment that the appellants incurred in expenses with respect to preparation for the performance of the contract the sum of $122.95, an itemized account thereof being attached to the complaint, which sum, it was alleged, was due and wholly unpaid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCormick v. Oklahoma
203 F. 921 (Eighth Circuit, 1913)
Burki v. Pleasanton School District
123 P. 546 (California Court of Appeal, 1912)
Silver, Burdett & Co. v. Indiana State Board of Education
72 N.E. 829 (Indiana Court of Appeals, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
63 N.E. 874, 29 Ind. App. 12, 1902 Ind. App. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mann-v-town-of-rochester-indctapp-1902.