Manatee County v. Gorsuch

554 F. Supp. 778, 18 ERC 2168, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20180, 18 ERC (BNA) 2168, 1982 U.S. Dist. LEXIS 17841
CourtDistrict Court, M.D. Florida
DecidedDecember 22, 1982
Docket82-248-Civ-T-GC
StatusPublished
Cited by13 cases

This text of 554 F. Supp. 778 (Manatee County v. Gorsuch) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manatee County v. Gorsuch, 554 F. Supp. 778, 18 ERC 2168, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20180, 18 ERC (BNA) 2168, 1982 U.S. Dist. LEXIS 17841 (M.D. Fla. 1982).

Opinion

MEMORANDUM OPINION AND RESTRAINING ORDER

GEORGE C. CARR, District Judge.

The plaintiffs, Manatee County, the City of Holmes Beach, and the City of Anna Maria Island [Manatee], have sued the Environmental Protection Agency [EPA] and the U.S. Army Corps of Engineers [Corps] alleging various violations of the National Environmental Protection Act, 42 U.S.C. § 4331, [NEPA], the Marine Protection Research, and Sanctuaries Act of 1972, 33 U.S.C. § 1401 et seq., [Ocean Dumping Act], and the Convention on the Prevention of Marine Pollution by Dumping of Wastes and Other Matter, Art. IV, 26 U.S.T. 2403, T.I.A.S. No. 8165 (1972). [Ocean Dumping Convention] Although the plaintiffs have made a number of specific allegations, the essence of their contentions can be summarized in one sentence. Put simply, it is the plaintiffs’ position that the defendants have illegally dumped dredged material on an interim ocean disposal site in the Gulf of Mexico (i.e., “Site A”) without taking into account the serious environmental consequences of their actions. Following a nine day trial and an extensive review of the administrative record, the Court finds, for the reasons explained more fully herein, that the federal defendants have not properly considered the effects of disposal at *780 Site A and that dumping at the site should be stopped until the required studies are completed.

The material being dumped has been dredged from the Tampa Harbor shipping channel as part of the 43-Foot Tampa Harbor Project, a project authorized by Congress for the widening and deepening of the Tampa Harbor channels. Consequently, several witnesses and parties expressed concern over the effect an injunction of dumping at Site A would have on the completion of the Tampa Harbor Project. In particular, the Tampa Port Authority suggested that even the threat of a delay of the project should be avoided. Therefore, it is important at the outset of this opinion to clarify the scope of the relief which the plaintiffs have requested and which the Court has granted.

The Court is enjoining dumping at Site A, not the deepening project. Since the Corps has admitted that the deepening project is not scheduled to be completed until October of 1984, at the earliest, and that the benefits of the project can not be realized until the entire project is completed, nothing ordered in this Opinion should delay the ultimate completion of the project. To recapitulate, the plaintiffs have not asked that the project be stopped and this Opinion should not be read as stopping it. 1

I.

As noted above, both the EPA and the Corps are defendants in this action and the plaintiffs have brought different counts against each agency. The plaintiffs contend that EPA violated NEPA by failing to complete an environmental impact statement prior to designating Site A as a disposal site (Count II). EPA is also charged with violating NEPA, the Ocean Dumping Act and the Ocean Dumping Convention by improperly designating Site A as an “interim” disposal site. (Counts V and VI).

It is EPA’s position that it was not required to do any studies of Site A prior to designating it as an interim site, see National Wildlife Federation v. Costle, 629 F.2d 118 (D.C.Cir.1980), and that, even if it were a requirement, any error has been cured by the EPA’s recent issuance of a Draft Environmental Impact Statement which evaluates both the use of Site A and the potential use of other open water sites. Moreover, because of this ongoing evaluation and decision-making process concerning Site A, the defendants argue that there is no final agency decision before the Court that is ripe for review and that the case against the EPA should be dismissed.

The plaintiffs also contend that the Corps’ use of Site A as an ocean disposal site without completing an environmental impact statement constitutes a violation of NEPA. (Count I). In addition, the plaintiffs charge that the Corps violated the Ocean Dumping Act, the Ocean Dumping Convention and its own regulations by failing to do independent studies of the site and the effects dumping would have on marine resources. (Counts IV and VI). Finally, the plaintiffs assert that the Corps violated the Ocean Dumping Act and its regulations by dumping toxic materials on the site and by failing to provide adequate public notices of its dumping project. (Counts III and VII).

Although the Corps admits that it did not complete an EIS on Site A, it contends that the FEIS it prepared in anticipation of the Tampa Harbor Project did take a “hard look” at the environmental consequences of open water disposal and that it has continued to consider these effects throughout all stages of the project. The Corps also contends that it has not dumped toxic materials at the site and that any procedural errors in the issuance of its public notices have been cured.

II.

Before considering the merits of the plaintiffs’ claims or the defendants’ defens *781 es, it is appropriate to outline the provisions of the controlling statutes, laws and precedents.

NEPA

Congress passed NEPA in 1969 with the avowed purpose of creating and maintaining “conditions under which man and nature can exist in productive harmony, and fulfill the social, economic, and other requirements of present and future generations of Americans.” 42 U.S.C. § 4331. See H.R.Rep. No. 91-378, 91st Cong., 1st Sess. 2, reprinted in 1969 U.S.Code Cong. & Ad.News 2751. To carry out this purpose, Congress required all federal agencies to prepare detailed environmental impact statements for “major Federal actions significantly affecting the quality of the human environment.” A chief bone of contention in most NEPA lawsuits is whether an action is a “major Federal action” with the potential of “significantly affecting the human environment.” Unfortunately, the language of the statute offers little specific guidance as to the meaning of these terms. As a result, an agency’s determination that an action is not a “major action” or that it will not have a “significant” impact is tested by a standard of reasonableness and will not be disturbed unless it is not fairly supported by the facts. Sierra Club v. Hassell, 636 F.2d 1095, 1097-98 (5th Cir.1981). Moreover, since the depth of detail required in each case depends upon its unique facts, the Courts in NEPA cases have focused on whether an agency has taken a “hard look” at the environmental consequences of its proposed action. Kleppe v. Sierra Club, 427 U.S. 390, 410 n. 21, 96 S.Ct. 2718, 2730 n. 21, 49 L.Ed.2d 576 (1976).

The Ocean Dumping Act

Congress passed the Ocean Dumping Act in 1972.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
554 F. Supp. 778, 18 ERC 2168, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20180, 18 ERC (BNA) 2168, 1982 U.S. Dist. LEXIS 17841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manatee-county-v-gorsuch-flmd-1982.