M. W. Kellogg Co. v. Concrete Accessories Corp.

204 S.E.2d 61, 157 W. Va. 763, 1974 W. Va. LEXIS 214
CourtWest Virginia Supreme Court
DecidedApril 9, 1974
Docket13329
StatusPublished
Cited by16 cases

This text of 204 S.E.2d 61 (M. W. Kellogg Co. v. Concrete Accessories Corp.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. W. Kellogg Co. v. Concrete Accessories Corp., 204 S.E.2d 61, 157 W. Va. 763, 1974 W. Va. LEXIS 214 (W. Va. 1974).

Opinion

Haden, Justice:

This is an appeal pursuant to West Virginia Code, Chapter 58, Article 5, Section 1(h) by M. W. Kellogg Company, a corporation, from an order of the Circuit Court of Harrison County, quashing an attachment and garnishment sued out concurrent with the institution of a civil action. At issue is the correctness of the lower court’s ruling quashing the attachment and garnishment.

Prior to the institution of the civil action, Kellogg had entered into a contract with the Allegheny Power System assuming the duty of constructing certain smoke stacks and chimneys at the Harrison Power Station located in Harrison County, West Virginia. Kellogg then subcontracted with Fombell Fabricating & Welding, Inc., a Pennsylvania corporation, which was to fabricate and *765 furnish two “slip form towers,” integral parts of two of the smoke stacks to be contracted at the power station. Fombell, in turn, contracted with Concrete Accessories Corporation, also a Pennsylvania corporation, for the fabrication and delivery of all or a substantial portion of the towers.

Upon receipt of the fabricated towers from Fombell, Kellogg paid Fombell the contract price of $55,819.50 and did not withhold a retainage.

Apparently, Concrete was not paid its contractual consideration by Fombell. Consequently, it served and recorded a notice of mechanic’s lien in the amount of $24,508.69 against the real estate described as the Harrison Power Station.

Subsequently, Monongahela Power Company, one of the member-owners of the Allegheny Power System and the Harrison Power Station facility, in accordance with prerogatives contained in the contract between the Allegheny Power System and Kellogg, made formal demand upon Kellogg to satisfy the mechanic’s lien and to obtain a release of the recorded lien. Kellogg refused to satisfy the lien on the basis that it had made full payment to Fombell for the fabrication and delivery of the slip form towers.

As a consequence of Kellogg’s refusal to satisfy the mechanic’s lien, Monongalia Power voluntarily agreed to pay Concrete’s attorney the sum of $24,692.50 to secure a release of the lien.

With knowledge that Monongalia Power was intending to satisfy the mechanic’s lien, and upon the assumption that the Allegheny Power System or its member-owners would then deduct the amount paid to satisfy the lien from retainages owed by the Allegheny Power System to Kellogg, Kellogg instituted its civil action against Fombell and Concrete. Ancillary to that action, Kellogg issued an attachment with a garnishment endorsed thereon and had the same served upon Concrete’s attorney *766 contemporaneously with the acquisition by the attorney of the funds tendered by Monongahela Power to Concrete in satisfaction of .the mechanic’s lien.

Then Concrete moved to quash the attachment and garnishment and moved to dismiss the complaint on the ground that both pleadings failed to state a cause of action upon which relief could be granted. At a hearing on the motion, upon argument of counsel, the filing of written memorandum and upon the affidavits of the parties in support and in opposition to the motion, the trial court denied the motion to dismiss Kellogg’s complaint but sustained the motion to quash the attachment and garnishment. This is the order appealed from.

On this appeal Kellogg contends the order of the court to have been in error and to its prejudice because the “form” of Concrete’s challenge was allegedly directed to defects in the complaint and failed to challenge the existence of the grounds of attachment or the sufficiency of the affidavit of attachment as required by the provisions of West Virginia Code, Chapter 38, Article 7, Sections 32 and 33. In pertinent part, these sections provide as follows:

“38-7-32. Quashing of attachment for insufficiency of affidavit.
“The right to sue out an attachment may be contested, and when the court is of opinion that the facts stated in the affidavit or amended affidavit were not sufficient to authorize the issuing thereof, or that the affidavit is otherwise insufficient, judgment shall be entered that the attachment be quashed.”
“38-7-33. Denial of grounds of attachment; trial; new trial; appeal.
“Any person entitled to defend in any attachment proceeding may controvert the existence of thé grounds of the attachment and of the facts relied upon to show the existence of such grounds, as such grounds and facts are stated in the affidavit, or in any amendment thereto, and may file an answer in writing denying the *767 existence of such grounds and facts in any-proceeding at law or in equity, such answer to be verified as any other pleading.”

Necessarily, both the language contained in the affidavit of attachment and the complaint in the civil action are in issue and material to the resolution of this appeal. The affidavit names Concrete and. Fombell and says that Kellogg is about to institute a civil action against both for monies due Kellogg “from defendants or one of them” for a claim arising out of contract under which “the defendants or one of them have been overpaid and unjustly enriched to the extent of $24,692.50,” concluding with an assertion that Concrete “is a foreign corporation.” There is also an affirmative allegation that the sum in question is presently due from either one or the other of Fombell and Concrete.

Comparatively, the complaint provides that it is being instituted on the assumption that “Allegheny Power Systems [sic] will deduct from retainages subject to its control,”: monies that would be otherwise due and payable to Kellogg upon the completion of its contract. (Emphasis supplied.) This language of the complaint implies or expressly concedes that monies were not currently due Kellogg at the time the complaint was instituted; thereby indicating that Kellogg was suing Concrete and Fombell for a liability which would mature at a future time.

Furthermore, both the attachment affidavit and the language of the complaint state a claim in the alternative, that is, based on the threshold allegation that Kellogg had previously paid Fombell all monies due Fombell, Kellogg further alleges that either Fombell or Concrete has been overpaid and has been unjustly enriched to the extent of Concrete’s recovery of $24,692.50 from Allegheny Power System through the use of the mechanic’s lien. By the use of this language making alternative claims, Kellogg premises its attachment and claim upon an unliquidated and contingent liability.

*768 On this appeal, Concrete relies upon the juridical rule that the judgment of the trial court is presumed to be correct. In this respect, we are in strong agreement with the appellee that the presumptions favor the judgment when the record in support of the judgment is bereft of testimony or other proof to the contrary:

“An appellant must carry the burden of showing error in the judgment of which he complains. This Court will not reverse the judgment of a trial court unless error affirmatively appears from the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of West Virginia v. Michael Faulkner
West Virginia Supreme Court, 2023
IPacesetters, LLC v. Kace Douglas and Randi Dampha
806 S.E.2d 476 (West Virginia Supreme Court, 2017)
Hose ex rel. K.M.H. v. Estate of Hose
736 S.E.2d 61 (West Virginia Supreme Court, 2012)
State Ex Rel. Leung v. Sanders
584 S.E.2d 203 (West Virginia Supreme Court, 2003)
Stewart v. Johnson
549 S.E.2d 670 (West Virginia Supreme Court, 2001)
Robinson v. Cabell Huntington Hospital, Inc.
498 S.E.2d 27 (West Virginia Supreme Court, 1997)
State Ex Rel. Evans v. Robinson
475 S.E.2d 858 (West Virginia Supreme Court, 1996)
Sleigh v. Sleigh
445 S.E.2d 509 (West Virginia Supreme Court, 1994)
Waco Equipment Co. v. B.C. Hale Construction Co.
387 S.E.2d 848 (West Virginia Supreme Court, 1989)
Divel v. Divel
363 S.E.2d 243 (West Virginia Supreme Court, 1987)
Crain v. Lightner
364 S.E.2d 778 (West Virginia Supreme Court, 1987)
Persinger v. Edwin Associates, Inc.
230 S.E.2d 460 (West Virginia Supreme Court, 1976)
Englebrecht v. DEVELOP. CORP. FOR EVERGR. VAL.
361 A.2d 908 (Supreme Judicial Court of Maine, 1976)
Englebrecht v. Development Corp. for Evergreen Valley
361 A.2d 908 (Supreme Judicial Court of Maine, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
204 S.E.2d 61, 157 W. Va. 763, 1974 W. Va. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-w-kellogg-co-v-concrete-accessories-corp-wva-1974.