M ELectric Corp. v. PHIL-GETS Guam

Superior Court of Guam·Decided March 22, 2018·No. CV1423-10·Unknown

Opinion

pl

man SUPERWR CBURT 1 GF GUAH 2 zm a tla n H z a n Q: 0 2 3 k'DF cow 4 5 86 6 IN THE SUPERIOR COURT 7 OF GUAM

8 M ELECTRIC CORP., ) Case No. CV1423- 10 9 ) plaintiff, ) 10 ) vs. 11 ) PHIL-GETS (GUAM) INTERNATIONAL) FINDINGS OF FACT AND 12 TRADING CORP., DBA J&B MODERN) CONCLUSIONS OF LAW TECH, AND CHUNG KUO INSURANCE) 13 COMPANY, LTD., ) 14 ) Defendants. ) 15

16 INTRODUCTION 17 This matter came before the Honorable Michael J. Bordallo on remand from the 18 19 Supreme Court of Guam's December 28, 2016 Opinion in M Electric Corp. v. Phil-Gets

20 (Guam) Int'l Trading Corp., 2016 Guam 35. Plaintiff M Electric Corporation is represented by

21 Attorney Thomas Talley. Defendants Phil-Gets (Guam) krtemational Trading Corporation

22 and Chung Kuo Insurance are represented by Attorney Seth Forman. On remand, the Court

23 ordered the parties to submit briefs on the no damages for delay issue by October 27, 2017.

7; Having reviewed the briefs, arguments, record, and applicable law, the Court issues the

26 following Findings of Fact and Conclusions of Law.

27 __| 28

Page 1of 12 Q' or O \ BACKGROUND 2 This matter arises out of Plaintiff M Electric Corp.'s ("MEC") August 19, 2010 3 Complaint alleging non-payment for two subcontracts with Defendant Phil-Gets (Guam) 4 5 International Trading Corp. ("J&B"). On February 10, 2012, the Court granted Defendants'

6 Motion for Sulmnary Judgment finding that the "no damage for delay" ("NDFD") clauses in

7 the subcontracts exculpated J&B from liability to Plaintiff for damages resulting from delays in

8 the pedorrnance of Plaintiffs work. Dec. & Order, 7 (Feb. 10, 2012). On March21, 2012,

9 MEC tiled a Notice of Appeal. On December 27, 2012, the Supreme Court of Guam reversed

:Of this Court's Decision and Order and remanded the matter for further proceedings. The

12 Supreme Court of Guam determined that NDFD clauses are enforceable in Guam and that

13 surmnary judgment was improper because exceptions to theNDFD could apply in tllis matter.

14 M Electric Corp. v. Phil-Gets (Guam) Int'l Trading Corp., 2012 Guam 23 'I 49.

15 The Court conducted a bench Md on November 5 and 13, 2014 where the parties

: presented the testimony of witnesses and other evidence. Based on the Court's factual findings,

18 it concluded that no exceptions to the NDFD clauses applied to the subcontracts. Additionally,

19 the Court denied MEC's excavation claim. On June 17, 2015, MEC filed a Notice of Appeal.

20 The Supreme Court of Guam found, inter alia, that the NDFD clauses stated in the prime

21 contracts covers the type of delays incurred by MEC. M Electric Corp. v. Phil-Gets (Guam)

Z Int'l Trading Corp., 2016 Guam 35 'I 98 ("M Elec. I"). The Supreme Court of Guam remanded

24 the issue back to this Court, tasking it to "determine whether the delays giving rise to MEC's

25 standby claim satisfy the fist recognized exception, given the facts and circumstances." M- 'I

26 88. On remand, the Court ordered the parties to submit supplemental briefs on the NDFD issue

27 by October 27, 2017. The Court took the matter under advisement on November 20, 2017. 28

Page 2 of 12 l ISSUE 2 1. Whether the first exception to a No Damage for Delay clause applies in this matter. 3 FINDINGS OF FACTS 4

By a preponderance of evidence, the Court makes the following Findings of Fact: 5

6 1. Guam Power Authority ("GPA") solicited bids for the Macheche-GIAA and Macheche-

7 Harmon San Vitores projects in local newspapers of general circulation. 8 2. A pre-bid conference was held on September 13, 2007 and was open to the public. 9 3. At the Conference GPA's Joven Acosta informed those in attendance that GPA was 10 unsure of the location of underground utilities and that it had been challenging to secure 11

12 encroachment permits from the Department of Public Works ("DPW"). Acosta warned

13 bidders of the no damages for delay clauses in the contracts and indicated that bidders 14 should increase their bids if they were concerned about delays. GPA anticipated that 15 project delays were likely. Further, because GPA knew its design work was prepared 16 with insufficient data and adjustments would have to be made in the field, it wanted to 17

18 make sure that bidders would not be surprised with addidonad costs.

19 4. Noel Lon tong and Carlos Nunez were present at the pre-bid conference. Both Mr.

20 Nunez and Mr. Lon tong identified their company as "M Electric" on the sign in sheet. 21 Mr. Nunez was employed by MEC at the time of the conference and gave MEC's phone 22 number as his contact number. Mr. Lon tong was MEC's project engineer. 23

24 5. GPA awarded J&B the contracts for the Macheche-GIAA and Macheche-Harmon San .

25 Vitores projects.

26 6. On March 24, 2008, MEC became a subcontractor to J&B, the prime contractor on the 27 Machete GIAA project pursuant to the plans and specifications prepared by TG 28 Engineer. MEC's subcontract was for $2,000,000.00 and had a completion date of

Page 3 of 12 1 December 2008. 2 7. On April 16, 2008, MEC became a subcontractor to J&B, the prime contractor for the 3 Machete-Harmon San Vitores project pursuant to the plans and specification prepared 4 by W inzler & Kelly. MEC's subcontract was for $3,490,000.00 and had a completion 5

6 date of January 13, 2009.

7 8. Both subcontracts stated that "time was of the essence in the subcontractor's 8 performance of this agreement." Section 10.1 of each subcontract provided that MEC 9 would get all pennies necessary for completing the work. At first, J&B tried to have 10 MEC get the permits, but since MEC could not afford to do so, J&B got the permits in ll

12 an effort to avoid delays.

13 9. MEC did not have the bonding capacity to apply for the permits and the bonds that are 14 required by DPW. J&B obtained the pennies and paid the premiums for the bonds and 15 never back-charged MEC for those costs. 16 10. Each subcontract provided that MEC would provide a construction survey, staking and 17

18 Ground Penetration Radar (GPR). The purpose of GPR was to trace the location of the

19 existing underground utilities.

20 11. The prime contracts each provided that change orders would be determined by the 21 actual cost of labor, permanent materials, equipment rental, power and consumable 22 supplies, insurance and a fixed fee not to exceed 15% of the net cost for supervision, 23

24 overhead, bond, profit, and other general expenses.

25 12. Both of MEC's subcontracts provided,

26 Section 3.3. In the event the Subcontractor is delayed in completing the Work by the 27 act, neglect, delay or default of the Contractor or the Owner, or of any other subcontractor employed by the Contractor, then the time fixed for completion of the 28 Work shall be extended for a period equivalent to the time lost, in the sole discretion of the Contractor, provided that no extension shall be granted unless written claim is made

Page 4 of 12 1 by Subcontractor within five (5) days from the inception of such delay. The extension of time hereinabove provided for shall be Subcontractor's exclusive remedy in the event 2 of such a delay, no matter how or by whom caused. 3 13. Both the prime contracts provided that no charge for extra work would be approved 4

5 unless approved in writing.

6 14. After MEC signed the Macheche-GIAA subcontract on March 24, 2008, it was notified

7 to begin its survey of the site with GPR in June 2008. Noel Lon tong completed this 8 survey in August 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

M ELectric Corp. v. PHIL-GETS Guam, (superctguam 2018).

M ELectric Corp. v. PHIL-GETS Guam (M ELectric Corp. v. PHIL-GETS Guam) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Government of Guam v. Collver
1 Guam 34 (D. Guam, 1958)
White Oak Corp. v. Department of Transportation
585 A.2d 1199 (Supreme Court of Connecticut, 1991)