Lyle v. McCormick Harvesting Machine Co.

51 L.R.A. 906, 84 N.W. 18, 108 Wis. 81, 1900 Wisc. LEXIS 168
CourtWisconsin Supreme Court
DecidedOctober 30, 1900
StatusPublished
Cited by10 cases

This text of 51 L.R.A. 906 (Lyle v. McCormick Harvesting Machine Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyle v. McCormick Harvesting Machine Co., 51 L.R.A. 906, 84 N.W. 18, 108 Wis. 81, 1900 Wisc. LEXIS 168 (Wis. 1900).

Opinion

Dodge, J.

1. The first, second, and third assignments of error naturally fall together for the purposes of discussion.. They present the question whether plaintiff has shown himself entitled to any damages, and, if so, to what amount-[85]*85These questions were raised by the motion for nonsuit and for direction of verdict and for an instruction to allow only nominal damages for the reason that no actual damages had been proved. Appellant’s position is predicated upon the propositions: (1) That the action is not in tort, for the reason that the disposal of the note by the defendant is not alleged to have been wrongful, and that it is neither alleged nor proved that the note was in its possession or control at the time when plaintiff’s contract right to and demand for its delivery came; therefore no conversion or other wrong could be committed by refusing its delivery. (2) That, being an action on contract, it falls within the class of those where the contract is substantially one of indemnity, and in this case is to be construed as indemnity only against the damage resulting from liability on the note, and therefore cannot be maintained until damage has been actually suffered by the compulsory payment of the note or the judgment thereon. (3) That, defendant being insolvent, the note has no value, and liability thereon occasions him no damage.

In the view we have taken of the other propositions, the first need not be authoritatively decided. It is urged in response thereto that, although no tort may have been committed at the time of refusing plaintiff's demand, still the defendant was under a duty to retain the note within its control so as to enable its delivery in case the plaintiff demanded it, and that its disposal thereof even before demand was in breach of that duty to the plaintiff, and therefore a conversion. In either event the measure of damage would be the value of the note prima facie, there being no special damages alleged. Such value, of course, might involve consideration of plaintiff's financial condition, and perhaps other circumstances.

The second proposition presents an interesting and somewhat novel question, upon which no entirely direct authority has been cited, and little has resulted from our own re[86]*86search. The principle is well recognized that, in case of an agreement to indemnify, ordinarily the construction of indemnity against damage only will be adopted, rather than indemnity against mere liability. This proposition is decided in Thompson v. Taylor, 30 Wis. 68, 72, and Taylor v. Coon, 79 Wis. 83, while the enforceability of a contract of indemnity clearly against liability alone is established by Smith v. C. & N. W. R. Co. 18 Wis. 17, 24. This contract before us, however, on its face is not a contract of indemnity. It is a plain and simple contract, under the circumstances shown to exist,- to deliver up plaintiff’s note upon demand. That demand being made, and not complied with, a distinct and complete breach of defendant’s contract was committed, and no reason is apparent why the plaintiff should not have a right to maintain an action upon such breach for whatever damages he has suffered. The measure of damages in an action for the breach of a contract is, of course, contractual. It is that which the defendant, either expressly or impliedly, has agreed to pay upon nonfulfilment of his stipulation. Where there is no express agreement as to what those damages shall be, the law raises the implication that they shall be compensation for what the plaintiff suffers by reason of the breach, so far as reasonably to be contemplated by the parties at the time of contracting. Analyzing the situation in the light of that principle, obviously the damage which fell upon the plaintiff in this case by reason of noncompiiance with the agreement to deliver up his note was the continued existence against him of a liability thereon; a liability the very existence of which was a breach of his right. The question, therefore, for trial was, What would compensate him for that liability ? It cannot be said that the damage which he suffered by defendant’s breach of its contract could only be what he might at some future time have to pay, for that would not be the damage falling upon him at the time of and by reason of the breach. That would result [87]*87from various subsequent circumstances. If the note were in the hands of the defendant, overdue, so that a perfect defense thereto might be made, he might ultimately have to pay nothing, or only the expenses of defense, while under other circumstances he might be put to expense and pecuniary loss much greater than the amount of the note.

In Barth v. Graf, 101 Wis. 27, 40, this general subject was considerably discussed, and the language of Church, C. J., from Kohler v. Matlage, 72 N. Y. 259, was quoted with approval, as follows: “ It is settled that upon an obligation to do a particular thing, or to pay a debt for which the covenantee is liable, or to indemnify against liability, the right of action is complete on the defendant’s failure to do the particular thing he agreed to perform, or to pay the debt, or discharge the liability.” This language was used in a case where a retiring partner gave bond to his copart-ners to pay on a day fixed certain debts for which all were liable. On his failure so to do, the obligees were held to have a complete cause of action for the amount of those debts; the court saying that, if there had been merely a bond to indemnify against damage by reason of those debts, no cause of action would have existed until they had actually paid them. This view was also taken in Loosemore v. Radford, 9 Mees. & W. 657, in which case the defendant, a debtor, had agreed with the plaintiff, his surety, that he would pay the guaranteed debt by a day certain. On failure so to do, it was held that the cause of action of his surety was complete, although the latter had not been called on to pay. Numerous other authorities similar in effect may be found. Lathrop v. Atwood, 21 Conn. 125; Redfield v. Haight, 27 Conn. 31; Gage v. Lewis, 68 Ill. 604, 617; Merriam v. Pine City L. Co. 23 Minn. 314, 322; Johnson v. Britton, 23 Ind. 105; Wilson v. Stilwell, 9 Ohio St. 467; Sedgwick, Damages (8th ed.), §§ 786, 789.

The reasoning of these cases seems to us founded on sound [88]*88principle. The breach of contract by the defendant is complete, and in analogy to all other situations the plaintiff should have his right of action therefor. If the measure of his damages is still involved in some degree of uncertainty, or if possibly a recovery of the full amount of the face of the note may work injustice to the defendant, still it must be remembered that the situation results from the fault of the latter, and not of the former. The postponement of the plaintiff’s recovery till he has paid, especially if he be poor or embarrassed, may subject him to serious injuries meanwhile, enhanced by his poverty. His attempts to do business or to emerge from his state of insolvency may be thwarted at every turn by the impairment of his credit from the mere existence of the liability. Any property acquired by him may be promptly sacrificed in the effort to enforce that liability, and still the debt remain unpaid, and he without remedy; and that, too, without any fault on his part save poverty. As' between the two, inconvenience should fall on the guilty rather than the innocent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chernin v. International Oil Co.
53 N.W.2d 425 (Wisconsin Supreme Court, 1952)
Pierce v. National Bank of Commerce in St. Louis
13 F.2d 40 (Eighth Circuit, 1926)
Peoples Co-Operative Store Co. v. Blegen
198 N.W. 425 (Supreme Court of Minnesota, 1924)
Maxey v. Rideout
173 F. 172 (U.S. Circuit Court for the District of Eastern Wisconsin, 1909)
Salchert v. Reinig
115 N.W. 132 (Wisconsin Supreme Court, 1908)
Du Cate v. Town of Brighton
114 N.W. 103 (Wisconsin Supreme Court, 1907)
Banderob v. Wisconsin Central Railway Co.
113 N.W. 738 (Wisconsin Supreme Court, 1907)
Luetzke v. Roberts
109 N.W. 949 (Wisconsin Supreme Court, 1906)
Schroeder v. Wisconsin Central Railway Co.
93 N.W. 837 (Wisconsin Supreme Court, 1903)
First Avenue Land Co. v. Parker
86 N.W. 604 (Wisconsin Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
51 L.R.A. 906, 84 N.W. 18, 108 Wis. 81, 1900 Wisc. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyle-v-mccormick-harvesting-machine-co-wis-1900.