LSP Transmission Holdings, LLC v. Lange

329 F. Supp. 3d 695
District Court, D. Maine·Decided June 21, 2017·No. Civil No. 17-4490 (DWF/HB)·Published·Cited by 9 cases

Opinion

DONOVAN W. FRANK, United States District Judge

INTRODUCTION

This matter involves a Constitutional challenge under the dormant Commerce Clause to Minnesota Statute § 216B.246, which grants incumbent electric utilities a *700right of first refusal to build and own electric transmission lines that connect to their existing facilities. Plaintiff LSP Transmission Holdings ("LSP") alleges that the statute discriminates against out-of-state transmission developers in favor of in-state utilities. Defendants1 have filed separate motions to dismiss LSP's lawsuit. (Doc. Nos. 18, 37 & 48.) For the reasons set forth below, the Court grants the motions.

BACKGROUND

This case involves electric generation, transmission, and delivery. Electricity is provided to consumers in three steps: (1) electricity is generated at various power plants; (2) electricity is transmitted on an integrated system of large power lines ("transmission lines"); and (3) electricity is then distributed to consumers through a network of smaller power lines ("distribution lines"). Electricity placed on transmission lines becomes part of an integrated, interstate system. State regulation of industries, such as the electrical industry, has long been recognized as a valid exercise of a state's police powers. See Munn v. Illinois , 94 U.S. 113, 126, 24 L.Ed. 77 (1876) (explaining that state regulation of property that is used in a way that is of public consequence is a valid exercise of the state's powers).

The principal federal statute governing electricity generation and transmission is the Federal Power Act ("FPA"), which was enacted in 1935. The Federal Energy Regulatory Commission ("FERC") exercises authority over the interstate transmission of electric energy and its sale at wholesale in interstate commerce. 16 U.S.C. § 824(b)(1). States retain jurisdiction over the retail sale of electric energy, as well as the "local distribution" and "transmission of electric energy in intrastate commerce." Id. Under the FPA, states have traditionally assumed all jurisdiction over the approval or denial of permits for the siting and construction of electric transmission facilities. See Piedmont Envtl. Council v. FERC , 558 F.3d 304, 310 (4th Cir. 2009).

In Minnesota, electric service is provided by monopolies. Electric utilities are assigned to service areas. Minn. Stat. § 216B.37. Within the respective service areas, each utility has "the exclusive right to provide electric service at retail to each and every present and future customer in its assigned area and no [other] electric utility shall render or extend service at retail." Minn. Stat. § 216B.40. In Minnesota, the PUC sets "just and reasonable" retail rates for public utilities. Minn. Stat. §§ 216B.03 -.04, and .79. The PUC also ensures that each utility provides "safe, adequate, efficient, and reasonable service" and "make[s] adequate infrastructure investments." Id.

FERC is empowered to "divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy" and has the "duty" to "promote and encourage such interconnection and coordination within each such district and between such districts." 16 U.S.C. § 824a(a). Regionally, FERC-approved nongovernmental agencies, *701independent system operators ("ISO"s), oversee the operation and expansion of electric transmission grids. (Doc. No. 1 ("Compl.") ¶ 14.) Each ISO issues a tariff, which establishes the terms by which its members build and operate grids. (Id. ¶ 15.) These tariffs are subject to the approval of FERC. (Id. ) The Midcontinent Independent System Operator ("MISO") is the regional planning entity that governs Minnesota.2 (Id. ¶ 16.)

Prior to 2011, FERC gave incumbent utilities a federal right of first refusal ("ROFR"). Under this system, if MISO approved construction of a new electric transmission line, the MISO member that distributed electricity in the area where the facility was to be built had a ROFR. Miso Transmission Owners v. FERC , 819 F.3d 329, 332 (7th Cir. 2016). In 2011, however, FERC issued Order 1000, which eliminated the federal ROFR. See Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils. , 136 FERC 61051, 2011 WL 2956837 ("Order 1000") ¶ 7. See also MISO Transmission Owners v. FERC , 819 F.3d at 332. Order 1000 was consistent with the effort to manage electric grids on a regional level. See Reg'l Transmission Orgs. , 89 FERC ¶ 61285, ¶ 1, 1999 WL 33505505, at *3 (Dec. 20, 1999) ; see also 18 C.F.R. § 35.34. At the same time, Order 1000 recognized that states could continue to regulate electric transmission lines. (Order 1000 ¶ 107) ("We acknowledge that there is longstanding state authority of certain matters that are relevant to transmission planning and expansion, such as matters relevant to siting, permitting, and construction. However, nothing in this Final Rule involves an exercise of siting, permitting, and construction authority."). FERC further explained:

Free access — add to your briefcase to read the full text and ask questions with AI

LSP Transmission Holdings, LLC v. Lange, 329 F. Supp. 3d 695 (D. Me. 2017).

329 F. Supp. 3d 695 (LSP Transmission Holdings, LLC v. Lange) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related