L.S. Starrett Co. v. Federal Energy Regulatory Commission

650 F.3d 19, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20212, 2011 U.S. App. LEXIS 12083, 2011 WL 2347706
CourtCourt of Appeals for the First Circuit
DecidedJune 15, 2011
Docket10-1470
StatusPublished
Cited by8 cases

This text of 650 F.3d 19 (L.S. Starrett Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.S. Starrett Co. v. Federal Energy Regulatory Commission, 650 F.3d 19, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20212, 2011 U.S. App. LEXIS 12083, 2011 WL 2347706 (1st Cir. 2011).

Opinions

TORRUELLA, Circuit Judge.

L.S. Starrett Company (“Starrett”) appeals from two orders by the Federal Energy Regulatory Commission (“FERC” or “Commission”). The Commission concluded that Starrett would be required to seek licensing pursuant to Section 23(b) of the Federal Power Act (“FPA”)1 if it proceed[21]*21ed with certain proposed changes to its Crescent Street Dam Project (“the Project”), a hydroelectric generating facility. Under Section 23(b), Starrett must seek licensing if (1) its facility is located on a stream over which Congress has Commerce Clause jurisdiction, (2) its proposed changes constitute “post-1935 construction” within the meaning of the FPA, and (3) the proposed modifications will affect the interests of interstate or foreign commerce. See 16 U.S.C. § 817(1). For the reasons below, we conclude that we have no choice2 but to affirm.

I. Background

The Project is located on the non-navigable Millers River in Athol, Massachusetts, on property that belongs to Starrett. It consists of (1) an 87-acre-foot reservoir; (2) a 20-foo1>-high, 127-fooh-long concrete gravity dam; (3) two powerhouses, one at each end of the dam; and (4) various appurtenant facilities. The turbine generator in the powerhouse on the right side of the dam (“the right-side generator”) currently has an installed capacity3 of 250 kW and an actual capacity of 80 kW. The turbine generator in the powerhouse on the dam’s left side (“the left-side generator”) had an installed and actual capacity of 112 kW until 2006, when it failed. Prior to the failure of the left-side generator, the combined installed capacity for the Project was 362 kW. This installed capacity was memorialized in a 1992 FERC order, which concluded that the Project did not require FERC licensing because there had been no post-1935 construction. See L.S. Starrett Co., 61 FERC ¶ 62,200 (1992) (“Starrett /”). The facility, however, could only actually produce 192 kW of electricity, even prior to the failure of the left-side generator, because of the physical limitations of the site.

After the left-side generator failed, Starrett began to investigate its options for replacement or repair. In early 2007, Starrett retained GZA GeoEnvironmental, Inc. (“GZA”), which prepared a feasibility study that examined the financial costs and benefits of repairing the left-side generator. The study concluded that it would be cost effective to use hydropower generated by a new left-side turbine generator (“the new left-side generator”). The new left-side generator’s installed and actual capacity would be 198 kW. Installing the new left-side generator would increase the Project’s combined installed capacity approximately 24%, to 448 kW, and its total actual capacity approximately 45%, to 278 kW. The total actual capacity of the Project, however, would remain less than the previous total installed capacity (i.e., 362 kW, [22]*22the capacity documented in Starrett I), a point that Starrett now emphasizes.

In September 2008, believing that it did not require FERC licensing in order to proceed with its proposed changes,4 Starrett ordered a new cross-flow turbine generator5 and began the preparatory work for its installation inside the left powerhouse. According to Starrett, replacing the left-side generator required the following: (1) lowering the floor inside the powerhouse by approximately 5 feet;6 (2)(a) improving the plunge pool7 within the building footprint by mounting the draft tube8 below the turbine generator, and (b) widening the outlet portal from under the powerhouse to the river from approximately 4 to 17 feet, both in order to improve outlet hydraulics and project efficiency; (3) excavating approximately 10 cubic yards of bedrock from the bottom of the Millers River, again in order to improve outlet hydraulics and project efficiency; and (4) installing a transition piece to connect the existing penstock9 to the new turbine.

In March 2009, as Starrett was working to replace its left-side generator, the U.S. Fish and Wildlife Service (“USF & WS”) wrote to the Commission to request that the Commission investigate the work oc[23]*23curring at the Project. The USF & WS had become aware that Starrett planned to install higher capacity machinery, and was concerned that the increased capacity at the Project would negatively impact migratory fish.

On May 4, 2009, the Commission notified Starrett that its proposed work would increase the capacity of the Project and would be considered post-1935 construction, thus triggering the Commission’s licensing jurisdiction. The Commission asked Starrett to submit various details about its dam and the proposed changes. Starrett provided the requested details but maintained that its proposed work would not lead to an increase in capacity above the 362 kW total memorialized in Starrett I because only the installed capacity, not the actual capacity, would be over 362 kW. After reviewing these materials, the Commission issued an order finding that licensing of the Project was required. See L.S. Starrett Co., 129 FERC ¶ 62,053 (2009) (“Starrett II”). Following Starrett’s request for rehearing, the Commission issued an order denying rehearing. See L.S. Starrett Co., 130 FERC ¶ 61,112 (2010) {“StarrettIII”).

II. Discussion

We are now required to review the Commission’s determination that the Project fell within its jurisdiction under Section 23(b) of the FPA. Under that section, a hydroelectric project “without a valid pre1920 permit” is subject to the Commission’s licensing jurisdiction if it

(1) is located on a navigable water of the United States;
(2) occupies lands of the United States;
(3) utilizes surplus water or water power from a government dam or
(4) [a] is located on a stream over which Congress has Commerce Clause jurisdiction, [b] is constructed or modified on or after August 26, 1935, and [c] affects the interests of interstate or foreign commerce.

Starrett II, 129 FERC ¶ 62,053, at 64,160; see also 16 U.S.C. § 817(1). The Commission concluded that Starrett’s dam was subject to licensing under the fourth criterion. We lay out the governing standard of review, and then address each of the three prongs of the fourth criterion.

A. Standard of Review

Reviewing the Commission’s orders under the Administrative Procedures Act, we “must reverse an agency action that is ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.’ ” Knott v. FERC, 386 F.3d 368, 372 (1st Cir.2004) (quoting Wis. Valley Improvement Co. v. FERC, 236 F.3d 738, 742 (D.C.Cir.2001)); see also 5 U.S.C. § 706.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
650 F.3d 19, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20212, 2011 U.S. App. LEXIS 12083, 2011 WL 2347706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ls-starrett-co-v-federal-energy-regulatory-commission-ca1-2011.