Louisville & N. R. R. v. Mason & Hoge Co.

104 S.W. 975, 126 Ky. 844, 1907 Ky. LEXIS 102
CourtCourt of Appeals of Kentucky
DecidedOctober 30, 1907
StatusPublished

This text of 104 S.W. 975 (Louisville & N. R. R. v. Mason & Hoge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisville & N. R. R. v. Mason & Hoge Co., 104 S.W. 975, 126 Ky. 844, 1907 Ky. LEXIS 102 (Ky. Ct. App. 1907).

Opinion

Opinion of the Court by

Judge Hobson

Reversing.

On April 21, 1903, a written contract was entered into between the Louisville & Nashville Railroad Company and the Mason & Hoge Company, whereby the latter undertook to build for the former 15% miles of railroad. The contract, among other things, contained these provisions: “And the said contractors agree to commence the said work within ten days from the date of this agreement, and to proceed with and complete the same to the satisfaction of the engineer by the first day of February, A. 13. 1904. And it is further agreed that the time herein stipulated' shall be considered as of the essence of this agreement. It is further agreed and understood, if at any time the contractors shall refuse or neglect to prosecute the work with a force sufficient, in the opinion of the engineer, for its completion within the time specified in this agréement, then, and in that case, the engineer in charge, or such other person as the engineer may designate, may proceed to employ such a number of workmen, laborers, and overseers as may, in the opinion of the said engineer, be necessary to insure thé completion of the work within the time heretofore mentioned, at such wages as he may find it necessary or expedient to give, pay all • persons so employed, and charge the amount so paid to the contractors, as for so much money paid to the contractors on this contract; or the said engineer may, at his discretion, for the failure to prosecute the work with an adequate force, for noncompliance [848]*848with his directions in regard to the manner of constructing it, or for any other omission or neglect of the requirements of this agreement and specifications on the part of the contractors, declare this contract abandoned which declaration of abandonment shall exonerate the Louisville & Nashville Railroad Company from any and all obligations and liabilities arising under this contract, the same as if this agreement had never been made; and the reserved percentage of' ten per cent, upon any work done by the contractors may be retained forever by the said company. And it is further agreed that if the said contractors fail to complete said work according to this contract, and the specifications, a part thereof, by the first day of February, 1904, as aforesaid, that then they will surrender to the Louisville & Nashville Railroad Company all of the retained percentage due them under this contract; and they hereby agree with the Louisville & Nashville Railroad Company that it may hold as its.own the whole of said retained percentage as reasonable liquidated damages for the failure on the part of said contractors to complete said work by said first day of February, 1904, and it is hfereby distinctly agreed by the parties that they do hereby fix the liquidated damages for the breach of this contract, as aforesaid, with respect to the time of the completion of the work at the amount of the whole of said retained percentage, whatever it may be on the first day of February, 1904. On or about the first day of each month, during the progress of the work, the engineer shall make, or cause to .be made, an estimate of the value of the work.by the contractors, during the preceding month, according to the prices set forth in the schedule or list herein-before given, and on or about the 20th day of the

[849]*849month. 90 per cent, of snch estimate shall be paid to the contractors at the office of the railroad company, in Louisville, Ky., in cash. Monthly estimates shall be considered as advances upon the final estimate, and shall be deducted therefrom. When all'the work embraced in this contract shall have been completed agreeably to the specifications, and in accordance with the directions and to the satisfaction and acceptance of the engineer, there shall be a final estimate made of the quantity, classification and value of said work agreeable to the prices set forth in said schedule, the balance appearing due to the contractors shall be paid to them when, and not until, the engineer shall make his written final certificate that the work had been fully and completely performed to his satisfaction, and the railroad company shall only be bound to pay the amount so certified to be due; and upon making said payment they shall give a release, under seal, to the railroad company from all claims or demands whatsoever growing in any manner out of this contract, and in computing the said final estimate, and giving the said final certificate, the said engineer shall not be bound by any 'preceding estimate, but such preceding estimates shall be held to be only approximate to the final estimate, and the said monthly estimates on unfinished work shall in no case be taken as an acceptance of the work or a release of the said contractors from responsibility therefor, until the final estimate and certificate are made, and the work in its entirety is accepted by the engineer as complete under this agreement.”

The Mason & Hoge Company did not begin the work within the time named, and failed to complete it until May, 1905. At the time the contract was made, it was understood that the Mason & Hoge Com[850]*850pany would construct a tunnel included in the work, and that the firm of Dunn & Lallande Bros, would construct the remainder of the work. The railroad company did not insist upon its right to terminate the contract when the work was not completed hy February 1, 1904, but allowed the contractors to continue the work as before. Dunn & Lallande Bros, completed the portion of the work assigned to them, which was all of the work except the construction of the tunnel, in October, 1904, and the railroad company then paid Dunn & Lallande Bros, the full amount of the final estimate for their part of the work. This payment was made under a written contract signed by all the parties, which stipulated as follows: ‘ ‘ That in any litigation that may arise under said contract the rights of the parties shall be determined as if said payment had not been made', except that the railroad company shall be entitled to credit for the full amount thereof.” The railroad company continued to hold back 10 per cent, of the monthly estimates until the tunnel was completed in May, 1905, and it then claimed the right to hold the 10 per cent., which had been retained because the work was not done within the time specified in the' contract. The Mason & Hoge Company thereupon filed this suit to recover from the railroad company the sum of $18,512.40. The railroad company filed an answer, to which the circuit court sustained a demurrer, and the railroad company appeals.

The judgment of the circuit court is based upon the ground that the railroad company, by not terminating the contract and allowing the contractors to complete the work, waived-its right to retain the 10 per cent, reserved in the monthly estimates, and that having waived this it could not resort to any other remedy [851]*851to recover damages for the noncompletion of the work in time. In support of this view, we are referred to Henderson Bridge Co. v. O’Connor, 88 Ky. 303, 11 Ky. L. R. 146, 11 S. W. 18, 957; Phillips v. Seymour, 91 U. S. 646, 23 L. Ed. 341; Walker v. Railroad Co., 1. C. P. Div. 518; Grant v. Railroad Co., 51 Ga. 348; Andrews v. Tucker, 127 Ala. 602, 29 South. 34. In Henderson Bridge Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips & Colby Construction Co. v. Seymour
91 U.S. 646 (Supreme Court, 1876)
Andrews v. Tucker
127 Ala. 602 (Supreme Court of Alabama, 1900)
McIntire v. Barnes
4 Colo. 285 (Supreme Court of Colorado, 1878)
Henderson Bridge Co. v. O'Connor & McCulloch
11 S.W. 18 (Court of Appeals of Kentucky, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
104 S.W. 975, 126 Ky. 844, 1907 Ky. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisville-n-r-r-v-mason-hoge-co-kyctapp-1907.