Henderson Bridge Co. v. O'Connor & McCulloch

11 S.W. 18, 88 Ky. 303, 1889 Ky. LEXIS 33
CourtCourt of Appeals of Kentucky
DecidedMarch 9, 1889
StatusPublished
Cited by9 cases

This text of 11 S.W. 18 (Henderson Bridge Co. v. O'Connor & McCulloch) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henderson Bridge Co. v. O'Connor & McCulloch, 11 S.W. 18, 88 Ky. 303, 1889 Ky. LEXIS 33 (Ky. Ct. App. 1889).

Opinions

CHIEF JUSTICE LEWIS

delivered the opietoít op the court.

December 7, 1881, O’Conner & McDonald made a written contract with the Henderson Bridge Company to construct for it, by October 1, 1888, the stone abutments and piers of a bridge across the Ohio river at. Henderson, Kentucky.

[317]*317June —, 1883, with consent of the company, McDonald retired, and McCulloch took his place as member of the firm and party to the contract.

February 14, 1884, the company attempted to annul the contract, and did, April 9, 1884, take possession, and proceed to complete the work, which was in an unfinished state.

This action was instituted August 1, 1884, by O’Conner & McCulloch, to recover of the company damages for an alleged breach of contract, and after a jury trial, lasting from November 3, to December 24, 1886, a verdict was found in favor of plaintiffs for eighty-six thousand eight hundred and five dollars and seventy-three cents, with interest thereon from April 9, 1884, making the sum of one hundred and one thousand eight hundred and thirty-seven dollars and fifty-eight cents, for which the judgment appealed from was rendered.

In their petition appellees allege that soon after the contract was made O’Conner & McDonald procured the necessary plant and materials, and following directions of appellant’s engineer as to the order of doing it, performed a large and valuable portion of the work during the year 1882, and up to June, 1883, but that appellant, almost from the beginning, commenced and continued in the following manner to hinder and delay them in carrying it on, as provided in the contract:

1. That having determined to so change the original plan as to make a through instead of draw-bridge, necessitating a change in the size and location of nearly every pier, appellant commenced in the spring of 1882 to obstruct progress of the work in order to avoid [318]*318locating the foundations until an act of Congress could be passed authorizing such change, which was not done until 1883, whereby the 'Contractors were prevented pushing the work at most available places, and using men and materials to advantage.

2. That although the work was bid for and undertaken with the understanding the contractors would not be required to use stone of better quality or more expensive than such as could be gotten at Hopkins-ville and Bowling Creen quarries, appellant, before the working season of 1882 began, notified them the Hopkinsville stone would not do, and refused to permit the Bowling Green stone used except for a small portion of the work.

3. That appellant from the beginning refused to furnish plans for shore work, although the contractors had from the spring of 1882 large amounts of material ready for, and requested permission to do, such work.

4. That great expense, labor and delay were caused by the manner, not contemplated, in which the contractors were required to construct caissons, and by negligence and mistake of appellant in other ways specially set out in the petition.

It is further stated that, in the spring of 1883, appellant notified the contractors it had altered the plan of the bridge so as to conform to the act of Congress just passed, and pending negotiations about prices for work to be done according to the new plan, McDonald transferred his rights and interests to McCulloch,' and a special contract in writing was, June, 1883, made between appellant and O’Connor & McCulloch for building the foundations and piers according to the specifica[319]*319tions of the original contract and the general profile of the modified plan, made part of the new contract, at prices specified and then agreed on, and which are stated in the petition. That, by reason of delays the contractors had been previously subjected to, and the radical change in the plan of the bridge, it was impossible to complete the work by October 1, 1883, and the purpose and expectation of it being done was waived by all parties at the time of the June contract, and appellant waived the provision of the original contract requiring it, and agreed said work might and could be done within a reasonable time.

It is further stated that the new firm at once proceeded to work under the original and special contract, though the latter was never signed by either party, obtained large amount of additional material, increased the number of men, and in all respects, to the extent allowed by appellant, carried on the work as rapidly as practicable, and more so than usual for such work to be done, but that appellant still refused to lay out or permit them to do shore work or to use Bowling Green stone, and although they continued to work until April 9, 1884, appellant wrongfully refused to make or cause made any estimate, or to pay them any part of what was due for work done during the months of December, 1883, January, February, March and April, 1884.

They further state that, while in peaceful possession of the work under the contracts, ready and able to complete it as rapidly as they had undertaken to do, appellant wrongfully and unlawfully, with a large number of men, and by force and violence, took possession, and drove them from said work, at the same time cutting [320]*320down and injuring their buildings and machinery. They had, in order to do said work, purchased .and constructed, at great expense and labor, a large and peculiar plant, a considerable portion of which was unfit for any other purpose, and expended much time and means in hunting for and operating quarries, making other preparations necessary for the work, and had on hand, in good condition, a great part of the materials therefor, but that, by reason of said breach of contract and expulsion from the work, their plant, equipment and preparations became of much less value, and they lost a large part of what was so invested. That if they had been allowed to complete .said work, they could and would have made large ■profits that were lost by said act of appellant. That the reserve of fifteen per cent, on the estimates up to November 30, 1883, amounting to thirty-three thousand seven hundred and sixty dollars and thirty-four cents, and also the amount due for work subsequently done, have been withheld, and that the whole loss and .damage sustained, after deducting what has been paid to them by appellant, amounts to two hundred and .sixty thousand dollars, for which they pray judgment.

We have referred in detail to the various grievances complained of in the petition, as well as to the elements of damages claimed because, in respect to each, a question of law or fact was made and passed on in the ■ lower court; but, before answering, appellant moved the court to strike out certain portions of the petition ■because irrelevant, which was sustained in part only, and also moved that appellees be required to specify the items of damages, which was overruled, and whether, [321]*321and to wliat extent, the rulings of the lower court on these motions were erroneous will be hereafter considered directly or. incidentally.

In paragraph 3 of the answer it is, in substance, alleged that appellees did not well and truly, from time to time, comply with the terms stipulated in the contract of December 7, 1881, and for a long time before February 14, 1884, and up to that day, it appeared

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clarke v. City of Albany
261 S.W.2d 435 (Court of Appeals of Kentucky, 1953)
Natural Rock Asphalt Corp. v. Carter
297 S.W. 1114 (Court of Appeals of Kentucky (pre-1976), 1927)
State v. Louisville & Nashville Railroad
96 N.E. 340 (Indiana Supreme Court, 1911)
Walton-Wilson-Rodes Co. v. McKitrick
132 S.W. 1046 (Court of Appeals of Kentucky, 1911)
United States v. Stone, Sand & Gravel Co.
177 F. 321 (Fifth Circuit, 1910)
Louisville & N. R. R. v. Mason & Hoge Co.
104 S.W. 975 (Court of Appeals of Kentucky, 1907)
Newport News & M. V. Co. v. McDonald Brick Co.'s Assignee
59 S.W. 332 (Court of Appeals of Kentucky, 1900)
Howard & Rice v. Thompson Lumber Co.
50 S.W. 1092 (Court of Appeals of Kentucky, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
11 S.W. 18, 88 Ky. 303, 1889 Ky. LEXIS 33, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henderson-bridge-co-v-oconnor-mcculloch-kyctapp-1889.