LoRoad, LLC v. Global Expedition Vehicles, LLC

787 F.3d 923, 2015 U.S. App. LEXIS 9029, 2015 WL 3449847
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 1, 2015
Docket14-2636
StatusPublished
Cited by10 cases

This text of 787 F.3d 923 (LoRoad, LLC v. Global Expedition Vehicles, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LoRoad, LLC v. Global Expedition Vehicles, LLC, 787 F.3d 923, 2015 U.S. App. LEXIS 9029, 2015 WL 3449847 (8th Cir. 2015).

Opinion

LOKEN, Circuit Judge.

LoRoad, L.L.C., based in Oregon' negotiated to have Global Expedition Vehicles, L.L.C. (GXV), based in Missouri, build a custom expedition vehicle. With the project underway, the relationship broke *925 down. LoRoad filed this diversity action to compel arbitration of the dispute, invoking the arbitration provision in a written Assembly Agreement allegedly entered into by the parties. GXV denied a valid, enforceable agreement to arbitrate. Ruling on cross-motions for summary judgment, the district court 1 held that LoRoad failed to accept the Assembly Agreement signed by GXV; therefore, the court could not enforce the arbitration provision in that Agreement. LoRoad appeals the resulting adverse summary judgment. We affirm.

I.

In September 2012, wilderness photographer Rodney Lough on behalf of Lo-Road began negotiations with GXV for construction of a custom expedition vehicle to be used by LoRoad for Lough’s off-road photography expeditions. On October 1, GXV sent a proposed Assembly Agreement for Lough’s review. The Agreement contained terms sufficiently definite and complete that, had LoRoad accepted, it would have been a binding contract. The terms included a “nonrefundable deposit of $120,000 to be paid at contract signing,” and an arbitration clause. GXV also emailed Lough that it would purchase a 2001 BAE 6x6 truck for $110,000 to serve as the base for Lough’s custom vehicle. Each subsequent version of the Assembly Agreement included this specific truck in calculating the total cost to build.

Rather than accept the October 1 proposed Agreement,. Lough returned a marked-up copy on October 9. GXV sent a revised Agreement on October 22, and after further negotiations, another revised Agreement on October 31. On November 2, LoRoad wired $120,000 to GXV, which René Van Pelt of GXV acknowledged on November 5. On November 16, Lough faxed GXV the October 31 draft Agreement with relatively minor handwritten notations and changes. In the space for LoRoad’s signature at the end of the Agreement, Lough wrote “LeeAnna Lough” (his wife and also a LoRoad principal) above the LoRoad signature line, and “By:” below that line.

On November 28, Lough emailed, ‘We still have unfinished business.” Van Pelt responded with answers to “notes and questions that we received by fax on November 16th.” On December 6, GXV sent a receipt for the $120,000 with the subject line, “Contract Deposit,” and emailed a status report on acquiring the base vehicle. On December 11, after further communications, Van Pelt sent LoRoad a revised Build List, which was “Exhibit A” to the Assembly Agreement and listed specifications for the vehicle. Van Pelt noted, “Once I get a thumbs up on the Build List, I will revise the contract and email to you as a complete document set.” On December 15, Lough emailed Van Pelt, “I am still not feeling comfortable with how things are at the moment ... We are very seriously looking at pulling out, at which point will [ ] want oúr money returned.”

On January 30, 2013, Van Pelt emailed Rodney Lough, “Your BAE 6x6 in transit,” explaining GXV’s delay in getting the truck and predicting it would arrive at GXV on Friday. On Friday, February 1, Van Pelt emailed Lough a picture of the truck. On February 11, Lough emailed Van Pelt asking for a status report. Van Pelt responded that GXV’s engineering team had started work on the truck, would send it to be painted when they were done, *926 and asked Lough to “respond via email that the color is staying per Build List: White.”

The next documentary exchange frames the contract issue on appeal. On February 11, Lough emailed Van Pelt saying Lo-Road “had no record of the parties’ creating and executing a final set of documents.” Lough asked GXV to send “a final set [of documents] incorporating everything we’ve come to agreement on” “for final review and then signatures, so we can get this thing moving.” Van Pelt responded that GXV received a signed contract from LoRoad on November 16. 2 Lough replied he had no record of that, and asked Van Pelt to “send me a copy of what you have, because we do not have one here nor do we have an executed copy from you either.” In response, Van Pelt returned a copy of the Agreement received from Lo-Road on November 16, with Lough’s handwritten changes and with the addition of Michael Van Pelt’s signature on the GXV signature line, but without the critical Build List.

In a February 14 reply, Lough asked for the entire Agreement, stated he did not know where the document came from, and asserted, “That is NOT LeeAnna’s signature ... I would never have authorized LeeAnna to sign a document that was not ready for signature and this document isn’t there and therefore we would not have signed it. I have emails from you going through and into December where the two of us continue finalizing the documents as they have not been completed.” Lough further stated, “We do want you guys to create this vehicle however we are no where near having the documents done ... and while you have our commitment in the form of a $120k deposit, that in no way means that you have an agreement with us until the final documents are signed, sealed and delivered properly.”

On February 22, Van Pelt sent a document titled “Assembly Agreement Addendum” dated February 2013, and a Build List dated December 11, 2012 (neither document is in the record on appeal). Lough responded: “Sending us an Addendum for a non-executed Assembly Agreement is not what you said you would do.” Lough “officially disputed your assertion that the Assembly Agreement is a signed and executed document.” On February 25, Lough reiterated LoRoad had not executed an agreement and described the $120,000 as a “good faith deposit,” not a payment under the Assembly Agreement. GXV then ceased work on the custom vehicle.

In March, LoRoad’s attorney began communicating with GXV. His first letter stated, “Lo Road is committed to purchasing the Expedition Vehicle” but “there is no final, executed contract in place.” The letter stated that, “according to all drafts of the Assembly Agreement, signed or not, GXV’s commencement of work was to begin 15 days after receipt of the deposit,” expressed concern about the delays, and asked for certain action items to be completed, including a revised Build List. An attachment detailed eleven reasons why there was “No Executed Contract in Place.”

On March 15, LoRoad’s attorney sent another letter, invoking the Adequate Assurances provision of the Uniform Commercial Code. GXV responded on March 16, “Global Expedition Vehicles contends that we do have an executed contract with the Lo Road, LLC. We have expended a great deal of money and engineering payroll, based on this contract.” Van Pelt sent an email on March 27 expressing *927 surprise that Lough wanted to change the Build List because Lough advised on February 22 he wanted to proceed with the December 11, 2012 Build List. On April 19, LoRoad’s attorney sent a letter stating that GXV had failed to provide adequate assurances and was in material breach of the contract, and that LoRoad intended to institute arbitration pursuant to the Assembly Agreement. This petition to compel arbitration followed.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
787 F.3d 923, 2015 U.S. App. LEXIS 9029, 2015 WL 3449847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loroad-llc-v-global-expedition-vehicles-llc-ca8-2015.