Futurefuel Chemical Co. v. Lonza, Inc.

756 F.3d 641, 2014 WL 2898436, 2014 U.S. App. LEXIS 12135
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 27, 2014
Docket12-3433, 13-1396
StatusPublished
Cited by23 cases

This text of 756 F.3d 641 (Futurefuel Chemical Co. v. Lonza, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Futurefuel Chemical Co. v. Lonza, Inc., 756 F.3d 641, 2014 WL 2898436, 2014 U.S. App. LEXIS 12135 (8th Cir. 2014).

Opinion

SHEPHERD, Circuit Judge.

FutureFuel Chemical Company (FFCC) appeals the district court’s 2 grant of summary judgment on its claims of breach of contract and promissory estoppel against Lonza, Inc. (Lonza). FFCC also appeals district court orders denying FFCC’s belated request for a jury trial, concerning the unsealing of the court record, and awarding attorney’s fees to Lonza. For the reasons explained below, we affirm the grant of summary judgment to Lonza, we dismiss as moot FFCC’s claim that the district court abused its discretion in denying FFCC’s motion for jury trial, we also dismiss FFCC’s appeal as it pertains to the unsealing of the record for lack of appellate jurisdiction, and, finally, we affirm the district court’s grant of attorney’s fees in this case.

I.

In 2008, Lonza supplied advanced pharmaceutical ingredients to the pharmaceutical industry. One of its products was trityl losartan (TTL), which Lonza supplied to Merck Pharmaceuticals. Lonza used Diethoxymethane (DEM), a solvent, in its manufacture of TTL. In 2008, Lonza learned that it would need a new supplier for DEM. At the same time, FFCC began exploring the possibility of producing DEM and approached Lonza about supplying its needs for DEM. Lonza’s representative immediately informed FFCC that its needs for DEM were volatile and depended greatly on the amount of recycled DEM it could recover through its production process.

FFCC proceeded with its plans to begin production of DEM. In the middle of 2008, Lonza representatives visited FFCC’s facility in Arkansas and met with FFCC representatives. Again, FFCC learned that Lonza’s need of DEM varied depending upon the success of its recycling and recovery program. After the visit, Lonza and FFCC began evaluating a potential supply arrangement for DEM. FFCC proposed that the two parties sign a Letter of Intent that described in broad terms a future agreement of the parties. FFCC claimed that it needed such an agreement to proceed with a $1.7 million capital expenditure to construct a DEM processing facility.

After further negotiations, FFCC and Lonza representatives signed a three-page Letter of Intent on August 25, 2008. Under the heading “Purpose,” the Letter of Intent provided:

Based upon our discussions concerning the storage and supply of [DEM] conducted since May 2008 and the information we have exchanged, we are entering into this Letter of Intent in order to develop an Agreement under which [FFCC] will store purchased DEM for [Lonza] and will additionally supply FFCC-manufactured DEM to Lonza in accordance with Lonza’s specifications for the product.
This Letter of Intent contemplates that the parties will negotiate and execute a definitive supply agreement (the “Agreement”) on or before October 1, 2008. It is the intent of the parties to meet to begin preparation of the Agreement by August 31, 2008. *645 This Letter of Intent is intended to confirm our understanding of the principal terms and conditions of the transaction and our mutual willingness to proceed in good faith to work toward the execution of a definitive Agreement consistent with these terms.

Under the heading “Long Term Supply Strategy,” the Letter of Intent provided:

FFCC agrees to configure and modify existing manufacturing equipment to a state necessary to produce DEM to the quality that meets the specifications outlined in Table 1.
Lonza agrees to purchase DEM from FFCC at the following volumes: 1,000 metric tons in 2009, 80% of its worldwide demand for 2010 and 80% of its worldwide demand for 2011. Lonza estimates that the expected DEM usage in 2009 is 1800 metric tons, and 900 metric tons in 2010 followed by 800 metric tons in 2011.

The Letter of Intent included a price/volume chart that established price per pound and price per kilogram based upon the amount of DEM purchased annually, with amounts ranging from more than 1250 metric tons annually to less than 400 metric tons annually.

After signing the Letter of Intent, the parties continued to negotiate for a long-term supply agreement. Negotiations continued with various draft supply agreements and counter proposals. In June 2009, almost a year after signing the Letter of Intent, Lonza informed FFCC that its projected demand for DEM had dropped to between 200 and 250 metric tons due to the success of its recovery process and because Merck had ordered less TTL than originally expected. In July 2009, Lonza made a “spot” purchase of 60 metric tons of DEM, however, FFCC charged Lonza a rate that exceeded the price listed in the Letter of Intent’s pricing chart because FFCC considered the Letter of Intent to be dormant. In 2010, Lonza made another “spot” purchase of 79 metric tons of DEM, with FFCC again charging Lonza a price exceeding that found in the pricing chart. Later in 2010, Merck withdrew its business from Lonza, and Lonza sold its TTL production facility.

FFCC initiated this action in Arkansas state court, asserting the Letter of Intent constituted a binding contract for Lonza to purchase 1000 metric tons of DEM in 2009 and claiming that Lonza had breached the contract. Alternatively, FFCC argued that promissory estoppel should apply. Lonza removed the case to federal court on the basis of diversity jurisdiction. The district court then granted Lonza’s motion for summary judgment, holding (1) the Letter of Intent did not constitute a binding contract to purchase 1000 metric tons of DEM in 2009 and, thus, Lonza could not have breached the contract with FFCC, and (2) FFCC was not entitled to relief under the theory of promissory estoppel because it was unable to show that Lonza made a promise to purchase 1000 metric tons of DEM in 2009.

After the entry of summary judgment, the district court sua sponte notified the parties that it intended to unseal all documents the parties had filed under seal in the case and gave the parties 10 days to file objections. FFCC moved for reconsideration of the court’s decision to unseal the documents. Before the district court could review FFCC’s motion for reconsideration, however, FFCC filed its notice of appeal challenging the district court’s grant of summary judgment. Because the case was on appeal and the district court no longer had access to the record material in question, the district court denied the motion for reconsideration without prejudice. The district court stated that FFCC could refile its motion for reconsideration within 15 days after this court issues its mandate. *646 The documents in question remain under seal.

Also after the entry of summary judgment, Lonza moved for $105,865.61 in attorney’s fees. Lonza indicated through its submitted billing records that it attempted to eliminate the hours worked on FFCC’s promissory estoppel claim from the attorney’s fees claimed. The district court granted Lonza’s attorney’s fees request in full. Lonza also sought $6,840.40 in costs; the district court denied the costs request except for $350 in filing fees for removal of the action to federal court.

II.

FFCC appealed the district court’s grant of summary judgment and the district court’s order indicating its intention to unseal the court’s record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
756 F.3d 641, 2014 WL 2898436, 2014 U.S. App. LEXIS 12135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/futurefuel-chemical-co-v-lonza-inc-ca8-2014.