Arloe Designs, LLC v. Arkansas Capital Corp.

2014 Ark. 21, 431 S.W.3d 277, 2014 WL 255487, 2014 Ark. LEXIS 48
CourtSupreme Court of Arkansas
DecidedJanuary 23, 2014
DocketCV-13-158
StatusPublished
Cited by11 cases

This text of 2014 Ark. 21 (Arloe Designs, LLC v. Arkansas Capital Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arloe Designs, LLC v. Arkansas Capital Corp., 2014 Ark. 21, 431 S.W.3d 277, 2014 WL 255487, 2014 Ark. LEXIS 48 (Ark. 2014).

Opinion

KAREN R. BAKER, Justice.

_JjThis appeal stems from litigation between Arloe Designs, LLC (Arloe) and Arkansas Capital Corporation (ACC) and National Bank of Arkansas (NBA). We affirm.

Arloe is an Arkansas business owned and operated by Marshal L. Jacobs. It specializes in the design, refurbishing, manufacture, and installation of aircraft interiors for small aircraft. In 2007, Jacobs put together a proposal to expand Arloe’s operation to include exterior aircraft paint and servicing. In order to expand his operation, Jacobs proposed to build a 4900 square foot building at the North Little Rock Municipal Airport. In order to facilitate financing, Jacobs offered to provide a cash-equity infusion and a $100,000 bond as additional collateral.

Arloe contends that ACC and NBA were to work together in a joint venture to procure the loan for Arloe. ACC is an Arkansas nonprofit set up to secure niche funding for Arkansas Small businesses. ACC prepared a document styled “loan proposal” that did not include the requirement of the bond as collateral. This document specifically stated that it L“did not constitute a contractual commitment of ACC to make a loan on these or any other terms.”

NBA sent a letter to Arloe on August 20, 2007, which stated that NBA had approved financing for the construction of the building. However, the letter stated that the approval was subject to several conditions, including the assignment of the lease from the North Little Rock Airport Commission and that the lease must be transferrable. Arloe entered into a 30-year lease for the new hangar in October, 2007. The terms of the lease prohibited the lease from being assigned.

Arloe asserts that on October 25, 2007, Jacobs was informed that NBA would not close the loan without the bond as collateral. Arloe did not give the bond as collateral, and so the loan was not closed.

Arloe filed suit against ACC and NBA, alleging that ACC’s and NBA’s actions were a breach of contract, violated the ADTPA, were negligent, and that Arloe had reasonably relied on the promise of NBA and ACC to its detriment. Arloe claimed damages equal to the lost profits it would have received had the loan been given and had it been able to expand its business as planned.

ACC and NBA filed motions for summary judgment, asserting that Arloe’s claims failed as a matter of law because it could not prove with reasonable certainty that the expansion of its business would have made a profit, because there was no contract, that there was no actionable claim for negligence because NBA and ACC owed no duty to Arloe, and because the ADTPA did not apply. The circuit court granted NBA and ACC’s motions for ^summary judgment as to all but Arloe’s promissory estoppel claim, and limited damages for that claim to the money that Arloe had spent in reliance on the claimed promise. The circuit court also granted NBA and ACC’s motion in limine to ex-elude the testimony of Steven Schroeder. Arloe had proffered the expert testimony of Steven Schroeder to show that Arloe’s proposed expansion would have been profitable.

At trial, the jury found that Arloe had not proved that either NBA or ACC had made a promise to loan Arloe money. Ar-loe brought this timely appeal and asserts five points on appeal: (1) that the circuit court erred in granting summary judgment on Arloe’s breach-of-contract claim; (2) that the circuit court erred in granting summary judgment on Arloe’s negligence claim; (3) that the circuit court erred in granting summary judgment on Arloe’s ADTPA claim; (4) that the circuit court erred in limiting damages on Arloe’s promissory estoppel claim; and (5) that the circuit court erred in finding that Arloe’s lost profit damages were barred. We have jurisdiction pursuant to Ark. Sup.Ct. R. 1-2(b)(5).

Summary judgment is to be granted by a circuit court only when it is clear that there are no genuine issues of material fact to be litigated, and the party is entitled to judgment as a matter of law. Tillman v. Raytheon Co., 2013 Ark. 474, 430 S.W.3d 698 Once the moving party has established a prima facie case of entitlement to summary judgment, the opposing party must meet proof with proof and demonstrate the existence of a material issue of fact. Id. On appellate review, we determine if summary judgment was appropriate based on whether the evidentia-ry items presented by the moving party in support of the motion leave a material fact unanswered. Id. We view the evidence in the light most favorable to the party 14against whom the motion was filed, resolving all doubts and inferences against the moving party. Id. Our review focuses not only on the pleadings, but also on the affidavits and documents filed by the parties. Id.

For its first point on appeal, Arloe contends that the circuit court erred in granting summary judgment on its breach-of-contract claim. Arloe asserts that ACC and NBA did breach their contract, and that there is a material question of fact that an enforceable contract existed. We disagree.

In Williamson v. Sanofi Winthrop Pharmaceuticals, Inc., 347 Ark. 89, 60 S.W.3d 428 (2001), we said “it is well settled that in order to make a contract there must be a meeting of the minds on all terms, using objective indicators.” This court employs an objective test for determining mutual assent. See Ward v. Williams, 354 Ark. 168, 118 S.W.3d 513 (2003). The proposal ACC sent to Arloe specifically states that it “IS NOT INTENDED TO AND DOES NOT CREATE A LEGALLY BINDING COMMITMENT OR OBLIGATION.” Further, just above the signature line on page 8 of the proposal, it states “The undersigned understands that this letter does not constitute a contractual commitment of ACC to make a loan on these or any other terms, and any representation to the contrary is hereby expressly disclaimed.” Here, the objective indicators show that ACC did not assent to an contract to lend money to Arloe. Therefore there is no question that this document did not create a legally binding contract to lend.

The circuit court found that the August 20, 2007 letter constituted evidence that NBA had approved financing for the building. However, this approval was subject to several |sconditions, including that the lease be transferrable. It is uncontested that the lease Arloe entered into was not transferrable. Because an express condition of the approval was not met, there was no contract. See Carter v. Cline, 2011 Ark. 474, 385 S.W.3d 745.

Arloe formed no contract with either ACC or NBA, therefore the circuit court did not err in granting summary judgment against Arloe for its breach-of-contract claim.

For its second point on appeal, Arloe asserts that the circuit court erred in granting ACC and NBA’s motion for summary judgment on its negligence claim. The circuit court found that ACC and NBA owed no duty of care to Arloe. The question of the duty owed to the plaintiff alleging negligence is always one of law and never one for the jury. D.B. Griffin Warehouse, Inc. v. Sanders, 349 Ark. 94, 76 S.W.3d 254 (2002). If the court finds that no duty of care is owed, the negligence count is decided as a matter of law. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ark. 21, 431 S.W.3d 277, 2014 WL 255487, 2014 Ark. LEXIS 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arloe-designs-llc-v-arkansas-capital-corp-ark-2014.