Long Island Lighting Co. v. Transamerica Delaval, Inc.

646 F. Supp. 1442, 2 U.C.C. Rep. Serv. 2d (West) 1333, 1986 U.S. Dist. LEXIS 18523
CourtDistrict Court, S.D. New York
DecidedOctober 27, 1986
Docket85 Civ. 6892 (GLG)
StatusPublished
Cited by63 cases

This text of 646 F. Supp. 1442 (Long Island Lighting Co. v. Transamerica Delaval, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Island Lighting Co. v. Transamerica Delaval, Inc., 646 F. Supp. 1442, 2 U.C.C. Rep. Serv. 2d (West) 1333, 1986 U.S. Dist. LEXIS 18523 (S.D.N.Y. 1986).

Opinion

GOETTEL, District Judge.

Much has already been written in the continuing saga of the Shoreham Nuclear Power Station (“Shoreham”). This, unfortunately, is yet another chapter.

BACKGROUND

In 1965, plaintiff Long Island Lighting Company (“LILCO”) initiated plans to construct a nuclear power plant on Long Island. Pursuant to requirements of the Nuclear Regulatory Commission (“NRC”), the plant had to include a reliable, independent onsite power source capable of running cooling and various other systems necessary to assure the safe shutdown of the reactor in case of emergency. In December 1973, LILCO issued specifications and invited defendant Transamerica Delaval, Inc. (“TDI”) to bid on the design and manufacture of three emergency diesel generators (the “diesels”) for the Shoreham facility. On May 20, 1974, LILCO issued a purchase order, awarding TDI the contract to manufacture the diesels. The diesels were delivered to Shoreham in 1976, but were not installed until 1981. 1 In August *1446 1983, during preoperational testing, the crankshaft in one of the three diesels broke. The other diesels were then inspected and cracks were found in their crankshafts as well.

LILCO retained a consultant who determined that the crankshafts were undersized and, as a result, the torsional stresses occurring at normal operating engine speeds were excessive. The consultant discovered additional defects in the diesels, including cracks in the connecting rod bearings and cylinders.

The 1983 diesel failure came under scrutiny by the New York State Public Service Commission (the “PSC”) as part of its investigation into the increased costs and delays in the construction of Shoreham. The PSC had initiated its investigation in 1979, but separated it into two phases. The phase regarding costs began in August 1981. Hearings were held in November 1981 and supplemental hearings in November 1983. On March 13, 1985, two PSC administrative law judges (the “ALJs”) issued their recommended decision (“ALJs’ Recommended Decision”), in which they concluded that LILCO had imprudently managed the construction of Shoreham and should be held responsible for a substantial portion of the resulting cost increases. On December 16, 1985, the PSC issued an Opinion and Order Determining Prudent Costs (the “PSC Opinion”), affirming the ALJs’ conclusion. The PSC Opinion noted, however, that its finding of imprudence by LILCO did not preclude a judicial finding that TDI failed to meet all of its legal obligations to LILCO.

LILCO filed this action against TDI in August 1985. The complaint sets forth eleven causes of action, including breach of contract, breach of warranty, fraud, negligence, strict products liability, and violation of the Racketeer Influenced and Corrupt Organizations Act (“RICO”), 18 U.S.C. §§ 1961-1968 (1982). 2 TDI moves to dismiss the complaint on a variety of grounds. It asserts that LILCO’s claims are untimely, should be barred by judicial and collateral estoppel, and fail to state claims upon which relief can be granted pursuant to Fed.R.Civ.P. 12(b)(6). 3 As discussed below, the defendant’s motion is granted in part and denied in part.

DISCUSSION

In challenging the sufficiency of the complaint, the defendant bears the burden of proving that under no interpretation of the facts set forth in the complaint can the plaintiff succeed. Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 101-02, 2 L.Ed. 80 (1957). For purposes of this motion, all of the plaintiff’s allegations are deemed true and no claim can be dismissed “unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Id.; Hughes v. Rowe, 449 U.S. 5, 10, 101 S.Ct. 173, 176, 66 L.Ed.2d 163 (1980).

TDI first asserts the affirmative defenses of judicial and collateral estoppel as *1447 overall bars to LILCO’s claims. The defendant then challenges each cause of action on one or more grounds. We consider TDI’s general estoppel defenses before proceeding to examine its arguments against the plaintiff’s individual claims.

I. Affirmative Defenses

A. Judicial Estoppel

The doctrine of judicial estoppel allows a court to preclude a party from asserting a position contrary to one upon which it prevailed in a prior proceeding. 4 This doctrine, sometimes called “[preclusion by inconsistent positions,” IB J. Moore, J. Lucas & T. Currier, Moore’s Federal Practice ¶ 0.405[8] at 239 (2d ed. 1984), protects judicial integrity by preventing a litigant from playing “fast and loose” with the court. Id. at 240. “The concern is to avoid unfair results and unseemliness.” 18 C. Wright, A. Miller & E. Cooper, Federal Practice and Procedure § 4477 at 779 (1981).

LILCO took the position before the PSC that it should not be held responsible for the cost of the diesel-related delays at Shoreham because, regardless of the diesel problems, Shoreham could not operate without an emergency evacuation plan, which the relevant authorities refused to approve. Because approval of the emergency plan was beyond its control, LILCO disclaimed liability for the delay costs, and sought to pass these costs along to its customers.

Initially, we note that LILCO was not successful in its position. The PSC barred LILCO from including in its rate base both the direct cost of the diesel failure and the cost of delays related thereto, since it found that the “failure of the diesels had a direct bearing on subsequent delays.” PSC Opinion at 124. The direct cost of the diesel failure was estimated at $95 million. Id. at 103, 126. As for delay costs, the PSC concluded that Shoreham would have become operational in April 1984, had the diesels not failed in August 1983. Id. at 119 n. 2. Therefore, the PSC required LILCO, not its customers, to absorb the delay costs from April 1984, to March 1986, by which time the diesels had been approved and Shoreham could have commenced operation had LILCO been able to obtain approval of an emergency evacuation plan. Id. at 119-25. The total diesel delay adjustment, not counting the $95 million direct costs, was calculated as $524 million. 5 Id., Appendix D at 2.

Success in the prior proceeding is a necessary part of the doctrine of judicial estoppel. See Universal City Studios, Inc. v. Nintendo Co., 578 F.Supp. 911, 921 (S.D.N.Y.1983), aff'd,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fiber-Span Inc v.
Third Circuit, 2022
In Re Moody's Corp. Securities Litigation
599 F. Supp. 2d 493 (S.D. New York, 2009)
Airfreight Express Ltd. v. Evergreen Air Center, Inc.
158 P.3d 232 (Court of Appeals of Arizona, 2007)
Shred-It USA Inc. v. Mobile Data Shred
222 F. Supp. 2d 376 (S.D. New York, 2002)
Kittitas Reclamation District v. Spider Staging Corp.
107 Wash. App. 468 (Court of Appeals of Washington, 2001)
Kittitas Reclamation v. Spider Staging
27 P.3d 645 (Court of Appeals of Washington, 2001)
United States Ex Rel. Roby v. Boeing Co.
79 F. Supp. 2d 877 (S.D. Ohio, 1999)
Potlatch Corp. v. Beloit Corp.
979 P.2d 114 (Idaho Supreme Court, 1999)
Washington Freightliner, Inc. v. Shantytown Pier, Inc.
719 A.2d 541 (Court of Appeals of Maryland, 1998)
Baker v. Dec International
580 N.W.2d 894 (Michigan Supreme Court, 1998)
Clifford v. Hughson
992 F. Supp. 661 (S.D. New York, 1998)
Netzer v. Continuity Graphic Associates, Inc.
963 F. Supp. 1308 (S.D. New York, 1997)
Joseph v. David M. Schwarz/Architectural Services, P.C.
957 F. Supp. 1334 (S.D. New York, 1997)
PC Com, Inc. v. Proteon, Inc.
946 F. Supp. 1125 (S.D. New York, 1996)
Raker v. DEC International
553 N.W.2d 667 (Michigan Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
646 F. Supp. 1442, 2 U.C.C. Rep. Serv. 2d (West) 1333, 1986 U.S. Dist. LEXIS 18523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-island-lighting-co-v-transamerica-delaval-inc-nysd-1986.