Kittitas Reclamation v. Spider Staging

27 P.3d 645
CourtCourt of Appeals of Washington
DecidedJuly 26, 2001
Docket19535-0-III
StatusPublished
Cited by3 cases

This text of 27 P.3d 645 (Kittitas Reclamation v. Spider Staging) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kittitas Reclamation v. Spider Staging, 27 P.3d 645 (Wash. Ct. App. 2001).

Opinion

27 P.3d 645 (2001)
107 Wash.App. 468

KITTITAS RECLAMATION DISTRICT, a Washington Irrigation District, Respondent and Cross Appellant,
v.
SPIDER STAGING CORPORATION; and Flow International Corporation, Appellants.

No. 19535-0-III.

Court of Appeals of Washington, Division 3, Panel One.

July 26, 2001.

*646 Marc C. Levy, Preston, Thorgrimson, Seattle, for Appellants.

John P. Gilreath, Douglas W. Nicholson, Cone, Gilreath, Ellis & Cole, Ellensburg, for Respondent.

KATO, J.

Kittitas Reclamation District (Kittitas) contracted with Spider Staging Corporation (Spider) to design and build an incline inspection platform. During a demonstration, the platform did not function successfully. Kittitas demanded that Spider deliver a platform fit for its intended purposes or the platform would be rejected. Spider did not respond. Kittitas then sued Spider and its parent company, Flow International Corporation (Flow), for cancellation of contract and damages. The court found in favor of Kittitas and ordered Spider to pay $27,248.17, the cost of the platform. Claiming, among other things, that the statute of limitations precluded Kittitas's claim, Spider and Flow appeal. Kittitas cross-appeals the denial of prejudgment interest and consequential damages. Finding that the statute of limitations had run, we reverse.

Kittitas is an irrigation district organized pursuant to chapter 87.03 RCW. It was created in anticipation of the United States Bureau of Reclamation constructing the Kittitas division of the Yakima Irrigation Project.

Spider was an independent subsidiary of Flow. On September 30, 1997, Flow sold Spider's assets to Safeworks, a limited liability company. Spider's name was then changed to Flow Washington Corporation, which was later administratively dissolved in 1999.

Kittitas diverts water at Easton, Washington, through a main canal, which generally runs southwest of the Yakima River. Approximately 15 miles west of Ellensburg, the main canal connects with a siphon that passes underneath the Yakima River to divert water from the main canal to the north branch canal on the north side of the river.

The United States owns the siphon. Through the Bureau of Reclamation, it contracts with Kittitas to operate and maintain the facilities. Pursuant to this contract, Kittitas must periodically inspect the siphon.

Kittitas inspects the siphon by lowering an employee on a steel platform into the inclined portion of the siphon. In 1992, the Bureau of Reclamation advised Kittitas to replace the existing platform. Spider submitted a bid for the replacement platform, at a cost of $25,347.34 plus tax.

On October 19, Kittitas told Spider to begin constructing the platform. On November 29, Spider sent a purchase order to Kittitas outlining the cost of design and assembly. The total cost, including tax, was $27,248.17. *647 On January 10, 1994, Kittitas paid Spider in full.

In March 1994, Spider transported the platform to Kittitas. It was later returned at Spider's request for modifications. On April 6, 1995, Spider notified Kittitas that the platform was completed and ready for pick up.

A demonstration or field test of the platform was scheduled for November 1995, but it was canceled and rescheduled for April 1996. During the test, it became apparent that the platform would not function as intended. As it was lowered into the siphon, the back of the platform started to bend or deflect. Because the platform required extensive repairs, Kittitas asked Spider to modify the platform so that it would function as both a maintenance and inspection platform. Kittitas asked Spider for an estimate for these modifications.

Sometime after September 1997, Spider informed Kittitas the modifications would cost $120,000. Kittitas felt this was too expensive.

On October 26, 1998, Kittitas demanded that Spider deliver the platform fit for its intended purposes as originally designed after fully field testing it. Spider did not respond.

On September 8, 1999, Kittitas filed a complaint against Spider and Flow for cancellation of contract and damages. It alleged the implied warranty of fitness for the platform's intended purpose was breached.

The case proceeded to bench trial. Claiming the complaint was barred by the statute of limitations, Spider moved to dismiss. The court denied the motion. It determined Kittitas was entitled to judgment against both Spider and Flow for $27,248.17. This appeal follows.

Spider contends the court erred by failing to dismiss Kittitas's complaint as untimely. An action for breach of warranty must be brought within four years after the cause of action has accrued. RCW 62A.2-725(1).

A cause of action accrues when the breach occurs, regardless of the aggrieved party's lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.

RCW 62A.2-725(2). In other words, the statute of limitations period normally starts upon delivery of the goods. Holbrook, Inc. v. Link-Belt Constr. Equip. Co., 103 Wash.App. 279, 284, 12 P.3d 638 (2000). However, if goods are sold with a warranty of future performance, the statute of limitations starts from the date when the defect is or should have been discovered. Id. RCW 62A.2-725 provides a point of finality for businesses after which time they can destroy their business records without fear of a subsequent breach of warranty suit arising. Cent. Wash. Refrigeration, Inc. v. Barbee, 81 Wash.App. 212, 225, 913 P.2d 836 (1996), rev'd on other grounds, 133 Wash.2d 509, 946 P.2d 760 (1997).

At issue here is when Spider tendered delivery. Spider claims the platform was delivered in March 1994 or, at the very latest, in April 1995. In either instance, the September 1999 complaint would be untimely. But the trial court agreed with Kittitas that the platform was never delivered because a successful field test had not been performed.

"Tender of delivery" requires that the seller put and hold conforming goods at the buyer's disposition and give the buyer notification reasonably necessary to enable him to take delivery. RCW 62A.2-503(1). The official comments to the code shed some light on the meaning of the term:

The major general rules governing the manner of proper or due tender of delivery are gathered in this section. The term "tender" is used in this Article in two different senses. In one sense it refers to "due tender" which contemplates an offer coupled with a present ability to fulfill all the conditions resting on the tendering party and must be followed by actual performance if the other party shows himself ready to proceed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Terry Schilling, et ux v. ProBuild Company, LLC
Court of Appeals of Washington, 2018
Elward v. Electrolux Home Products, Inc.
264 F. Supp. 3d 877 (N.D. Illinois, 2017)
Cutter v. Biomet, Inc.
244 F. Supp. 3d 793 (N.D. Indiana, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
27 P.3d 645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kittitas-reclamation-v-spider-staging-washctapp-2001.