DALY, C. J.

The plaintiffs claim to recover $235 for a tank (to be used for heating water by steam) which they made and delivered to the defendant under a special contract. The defendant at first objected to the tank for certain alleged variations from the contract, but afterwards consented to take it upon the plaintiffs’ offering to make certain connections. When this additional work was done, objection was still made to the flanges furnished for the connections as unsuitable and imperfect, and defendant had new flanges made by another machinist, after which the tank was in constant use down to and at the time of the trial. Upon this state of facts the jury found for the plaintiffs, and the general term of the city court affirmed the judgment. The conceded facts show an acceptance of the tank by the defendant. Retention and use after discovery of the alleged defects made it liable to pay the price. It is contended that it makes a difference in principle that the tank was used after an alteration had been made at the defendant’s expense. This alteration did not make it, as defendant seriously urges, some other tank than the one furnished by plaintiffs, which he used and has continued to use. Kor is there any more force in the contention that the tank was not a chattel in the ordinary sense, but a fixture attached to the freehold, “which could not be returned if unsatisfactory, any more than any part of a building could be returned when once built.” The contention is not even plausible. An old tank was removed to make room for the new one, and, among the several small items of plaintiffs’ contract, was a stipulation to take the old tank out. There was nothing to prevent the removal of the new tank if it was unsatisfactory, and this, with a notification to the plaintiffs, would have relieved the defendant. The retention and use of the tank, under the circumstances, conclude the defendant, and also dispose of the claim, urged with much persistency, that the terms of the plaintiffs’ contract provided that their work was to be done to the defendant’s entire satisfaction. Defendant cannot keep and use the tank, and claim to be dissatisfied.

The only important exceptions taken by the defendant, and not involved in the disposition made of the foregoing objections, will be considered in the order of their importance. At the opening of the case defendant moved to dismiss the complaint upon the ground that it did not state facts sufficient to constitute a cause of action, as it did not allege performance, nor any time within which the contract was to be performed, nor that it was performed [778]*778within a reasonable time. The motion was denied. The complaint alleged an agreement to make a hot-water pressure tank, and deliver the same on foundation in cellar, for the price of $235, and alleged the plaintiffs “made and delivered the tank to the defendant, when it was found that a slight alteration was required by defendant, which alteration plaintiffs made, and that defendant retained and still has possession of the tank, and refuses to pay for the same.” The answer is a general denial. The general rule is that the plaintiff must allege the facts showing performance by him and the default of the defendant, and so should allege performance within the time fixed by the contract, or, if no time be fixed, performance within a reasonable time. But the complaint in this action alleged the receipt and retention of the tank by defendant after its delivery, and after it had been altered as required by defendant, and such an averment was equivalent to an allegation of acceptance, and dispenses with the usual averment of performance, as acceptance is a waiver of any unperformed conditions. The case upon which appellant relies (Pope v. Manufacturing Co., 107 N. Y. 61, 13 N. E. Rep. 592) was that of an executory contract for the sale and delivery of iron, and the complaint alleged tender of delivery and refusal to accept. It appearing that no time was fixed by the contract, the plaintiff was bound to prove delivery within a reasonable time, as this was essential to his cause of action, and whatever is essential to the cause of action must be pleaded, as well as proved; and so it was held the complaint should have averred an offer to deliver within a reasonable time. The distinction between the complaint in that case and one averring delivery and acceptance is obvious.

The plaintiffs produced in proof of the contract set up in the complaint letters containing proposals and acceptance passing between themselves and the defendant, which constitute a valid contract; but objection was made that it did not prove the contract alleged in the complaint, for the reason that the contract, as proved, for the manufacture and delivery of the tank, contained additional stipulations not set forth in the complaint, viz.: That plaintiffs were to cut apart the old tank so as to take out the old coil and put it in the new tank, to cut all holes for connections, take out the old tank, a hand-hole plate in each end, complete the job within two or three weeks, and furnish all necessary flanges, beveled for connections. As it would ordinarily be necessary for plaintiffs to prove performance of all the work before they would be entitled to recover the contract price, it was contetided that they were equally bound to plead the whole contract, and could not prove it under an allegation setting forth a part only. The observation of the court below upon this point was that the plaintiffs had merely “proved the contract fuller in detail than they had alleged it in the complaint.” It is not required by the Code that the proof and the pleading shall accord exactly. Allowance is expressly made for. variances, if the adversary be not misled; and an examination of the many cases of variances which have been held immaterial disposes of the objection in this case. See Code, § 539, and cases cited [779]*779under it. It is only where the allegation is “unproved, not in some particular or particulars only, but in its entire scope and meaning,” that there is a failure of proof. Code, § 541. Here we have an agreement for the manufacture and setting up of a specific article, with details and items of work required to put it in place of a former one, to remove the latter, and to do the work in a specified time. The complaint sets up the substantial subject-matter of the contract, and omits the details. There was no claim of surprise upon the trial, and an amendment, therefore, was not necessary, for the court might order the fact to be found according to the evidence. Sections 539, 540. The subject-matter of the contract set out in the complaint and proved on the trial were identical, and there was an omission of detail only in the pleading.

It is urged that the plaintiffs were permitted to recover as for a substantial performance, and yet that the court refused to admit testimony of the cost of the alteration of the flanges which were required before the tank could be used. It appears, however, that no competent testimony of this expense was offered. The defendant’s superintendent was asked how much he paid for having the tank altered, and this was objected to as incompetent, and the objection was sustained. It was clearly incompetent. The machinist who made the alteration, or other competent witness, should have been called to show the value of the work, but there is no proof of that kind in the case.

It is claimed that the court erred in excluding evidence of conversation with one of the plaintiffs through the telephone. The evidence was excluded, because the defendant’s witness could not identify the person with whom he had the conversation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liquid Carbonic Corp. v. Caroombas
132 Misc. 866 (New York Supreme Court, 1928)
Jonap v. Siebert
144 N.Y.S. 7 (Appellate Terms of the Supreme Court of New York, 1913)
Mizell v. Watson
57 Fla. 111 (Supreme Court of Florida, 1909)
Turl v. Knabe
26 Misc. 770 (Appellate Terms of the Supreme Court of New York, 1899)
Hospital Supply Co. v. O'Neill
31 N.Y.S. 792 (New York Court of Common Pleas, 1895)
Hamburger v. Rottenberg
30 N.Y.S. 240 (New York Court of Common Pleas, 1894)
Logan v. Berkshire Apartment Ass'n
23 N.Y.S. 1159 (New York Court of Common Pleas, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
22 N.Y.S. 776, 3 Misc. 296, 52 N.Y. St. Rep. 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/logan-v-berkshire-apartment-assn-nyctcompl-1893.