Lockheed Martin Corp. v. England

CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 21, 2005
Docket2004-1461
StatusPublished

This text of Lockheed Martin Corp. v. England (Lockheed Martin Corp. v. England) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Corp. v. England, (Fed. Cir. 2005).

Opinion

Error: Bad annotation destination United States Court of Appeals for the Federal Circuit

04-1461

LOCKHEED MARTIN CORPORATION,

Appellant,

v.

Gordon R. England, SECRETARY OF THE NAVY,

Appellee.

E. Sanderson Hoe, McKenna Long & Aldridge LLP, of Washington, DC, argued for appellant. With him on the brief were Daniel G. Jarcho and Jason N. Workmaster.

William K. Olivier, Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for appellee. With him on the brief were Peter D. Keisler, Assistant Attorney General, David M. Cohen, Director, and Bryant G. Snee, Assistant Director. Of counsel on the brief was Charles W. Goeke, Attorney, Defense Contract Management Agency, of Philadelphia, Pennsylvania.

Appealed from: United States Armed Services Board of Contract Appeals United States Court of Appeals for the Federal Circuit

__________________________

DECIDED: September 21, 2005 __________________________

Before RADER, DYK, and PROST, Circuit Judges.

PROST, Circuit Judge.

Lockheed Martin Corp. (“Lockheed”) appeals from a decision of the Armed

Services Board of Contract Appeals (“Board”) in which the Board held that Lockheed

was not entitled to recover for subcontract effort in a termination settlement. Lockheed

Martin Corp., Naval Elecs. & Surveillance Sys.—Surface Sys., ASBCA Nos. 53032,

54064, 2003 ASBCA LEXIS 104 (Oct. 16, 2003). We affirm the Board’s decision.

I. BACKGROUND

Plaintiff Lockheed contracted with the Navy to supply antennas and transmitters for the Navy’s AEGIS program.1 This effort was known as the AEGIS Second Source

Radar Qualification Program and was divided into two phases: Phase I and Phase II.

Phase I consisted mainly of planning. Phase II required Lockheed to provide a

demonstration antenna and transmitter.

Lockheed enlisted several subcontractors to assist in the Second Source Radar

Qualification Program. For the antenna work, Lockheed itself was to be the leader,

Unisys Corp. (“Unisys”) would be the first-tier subcontractor, and Westinghouse Corp.

(“Westinghouse”) would be the second-tier subcontractor. For transmitters, first-tier

subcontractor Raytheon Co. (“Raytheon”) would lead the project, and Unisys would be

the second-tier subcontractor. We adopt the parties’ convention of using “Unisys-

Antenna” and “Unisys-Transmitter” to distinguish between the two roles Unisys played

in this contractual arrangement.

The prime contract between the Navy and Lockheed was initially undefinitized

but contemplated definitization into a cost-plus-fixed-fee (“CPFF”) contract. In a CPFF

contract, the contractor recovers its allowable incurred costs and also receives a pre-

negotiated fee. Before a contract is “definitized” through establishment of its final terms,

a contractor may begin performance pursuant to a preliminary contractual instrument

that is sometimes called a “letter contract.” The prime contract in this case contained

the standard Federal Acquisition Regulation (“FAR”) termination for convenience clause

for cost-type contracts. See 48 C.F.R. § 52.249-6 (2005).

1 The AEGIS Weapon System is a guided missile system that includes a radar system known as AN/SPY-1. The primary function of the SPY-1 Radar is to search, detect, and track air and surface targets in heavy clutter and electronic countermeasure environments. The SPY-1 Radar consists of a Transmitter Group, a Signal Processor, and an Antenna.

04-1461 2 The first-tier transmitter subcontract with Raytheon was also a CPFF contract. It

contained the standard FAR termination for convenience clause for cost-type contracts.

See id. However, the second-tier subcontract with Unisys-Transmitter was a firm-fixed-

price (“FFP”) contract. In an FFP contract, the price is not subject to any adjustment

solely on the basis of the contractor’s costs incurred in performing the contract. Both

antenna subcontracts were also FFP contracts. They contained the standard FAR

termination for convenience clause for fixed-price-type contracts. See 48 C.F.R.

§ 52.249-2 (2005). The structure of the overall contractual arrangement is shown in

Figure 1 below.

Navy

CPFF

Lockheed (Radar System & Antenna Leader)

CPFF FFP

Raytheon Unisys-Antenna (Transmitter Leader) (Antenna Follower)

FFP FFP

Unisys-Transmitter Westinghouse (Transmitter Follower) (Antenna Follower)

Figure 1: Contract Structure

The second-tier subcontracts required the subcontractors to deliver data items

known as Subcontract Data Requirements List items (“SDRLs”) to their next higher-tier

subcontractors. During both Phase I and Phase II, the subcontractors delivered many

04-1461 3 SDRLs. SDRLs included a wide variety of items, including status reports, meeting

agendas and minutes, presentation materials, quality assurance inspection reports, test

procedures, a production/delivery plan, a quality assurance program plan, and a list of

special tools and equipment.

On March 30, 1990, the Navy stopped work on the program. At this point, many

Phase II SDRLs had been delivered, but assembly of the demonstration hardware had

barely begun. The Navy proceeded to terminate the prime contract for the

government’s convenience on June 21, 1990. In consequence, Lockheed terminated

the Unisys-Antenna and Raytheon subcontracts for convenience, and those parties

terminated their second-tier subcontracts with Westinghouse and Unisys-Transmitter for

convenience. Each lower-tier subcontractor submitted a termination settlement

proposal to its next-higher-tier contractor for negotiation. Lockheed collected these

proposals and included them in its termination settlement proposal to the government.

None of the subcontractors’ settlements would become final until approved or ratified by

the Termination Contracting Officer. See 48 C.F.R. § 49.108-3(b)(2) (2005).

The Termination Contracting Officer did not ratify the subcontract settlements.

Specifically, she objected to the fee and profit amounts calculated based on Phase II

work by Unisys-Transmitter and Westinghouse.2 At that point, the Termination Contract

Officer was apparently unaware of the SDRLs that had been delivered by Unisys and

Westinghouse on the antenna and by Unisys on the transmitter. She determined that

none of the Phase II second-tier subcontract work had been completed and delivered

2 “Fee” and “profit” are similar concepts, but the term “fee” is used for cost- type contracts, and “profit” for fixed-price contracts. See FAR 49.202, 49.305-1.

04-1461 4 and consequently held that no profit or fee should be paid to Lockheed or its

subcontractors for Phase II. The Termination Contract Officer relied on FAR 49.202(a),

which states that “profit shall not be allowed the contractor for material or services that,

as of the effective date of termination [for convenience], have not been delivered by a

subcontractor, regardless of the percentage of completion.” 48 C.F.R. § 49.202(a).

In response, Lockheed’s final termination settlement proposal sought fee or profit

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Lockheed Martin Corp. v. England, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-corp-v-england-cafc-2005.