Lobisser Building Corp. v. Planning Board of Bellingham

454 Mass. 123
CourtMassachusetts Supreme Judicial Court
DecidedJune 22, 2009
StatusPublished
Cited by7 cases

This text of 454 Mass. 123 (Lobisser Building Corp. v. Planning Board of Bellingham) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lobisser Building Corp. v. Planning Board of Bellingham, 454 Mass. 123 (Mass. 2009).

Opinion

Marshall, C.J.

The plaintiffs in this case, Lobisser Building Corp. (Lobisser) and Crystal Springs Condominium Association, Inc. (association), filed a complaint in the Land Court appealing [124]*124from a decision of the planning board of Bellingham (board) denying their application for a modification of a special permit and for development plan approval. The plaintiffs asserted that the board’s decision that the special permit had lapsed and that the issue of ownership of development rights was unresolved were in excess of the board’s authority. A judge in the Land Court entered summary judgment in part for the plaintiffs and in part for the board, agreeing with the board’s decision that the special permit had lapsed pursuant to G. L. c. 40A, § 9, but also finding that the association had validly amended its master deed, pursuant to G. L. c. 183A, § 5 (b) (2) (iii), to develop additional condominium units. The plaintiffs appealed from that part of the decision upholding the board’s decision that the special permit had lapsed, and we granted their application for direct appellate review.2 Because we conclude the special permit has not lapsed, we reverse the decision of the Land Court.3

1. Background. In December, 1985, the board granted the Onallam Realty Trust (trust) a special permit to construct eighty-four townhouse condominium units under § 4400 of the Bell-ingham zoning bylaw. The special permit included several conditions, two of which are relevant here:

“3. Plans shall be submitted under Section 1420 Site Plan Review, in annual phases ....
“5. Building permits shall not authorize construction of more than the following cumulative totals of dwelling units:
“Prior to January 1, 1987: 21 units, to begin at South Main Street;
“Prior to January 1, 1988: 42 units;
“Prior to January 1, 1989: 63 units;
“Prior to January 1, 1990: 84 units.”

[125]*125The permit thus contemplated a phased build-out, with no more than twenty-one units being built in any given year. The town building inspector issued the first building permit, for phase I, in April, 1986. In March, 1987, the first occupancy permit was issued, and the Crystal Springs Condominium was established with the recording of the master deed with the Norfolk County registry of deeds.4 As established, the condominium included twenty-one units in five buildings, with the right to add three additional phases to include an additional sixty-three units (i.e., phases II, III, and IV as indicated by the special permit).

The master deed was amended in September, 1987, to include the units of phase II, the plans for which had been submitted to the board pursuant to special permit condition no. 3 in January, 1987. Phase II would consist of five additional buildings with four units each, bringing the total number of units in the condominium to forty-one and in keeping with special permit condition no. 5 requiring that no more than forty-two units would be built prior to January 1, 1988. In the spring of 1988, an issue arose with the Bellingham town sewer system and a letter from the water-sewer department to the board requested an extension of time for the trust to submit to the board the plans for phase III of the project. The board and the trust then agreed that a written extension would not be necessary if the trust chose to delay construction of phases III and IV of the project, and that construction would resume when the municipal sewer system became available. No further construction took place, however, after the construction of phase II, even after the sewer system became available.

Nothing in the record before us indicates the reason for the cessation of the project at that time, and it appears that no further action related to the project occurred until the fall of 2005, when KML Holdings Corp. entered into an agreement with the association to purchase the development and phasing rights from the association, which had voted to revive the rights to develop addi[126]*126tional units in the condominium. The master deed was accordingly amended, and in December, 2006, Lobisser applied to the board for a modification of the special permit and for development plan approval.5

At the board meeting at which the application was discussed, the board voted to deny the application on the basis that the special permit had lapsed. The plaintiffs then filed their complaint in the Land Court, pursuant to G. L. c. 40A, § 17, appealing from the board’s decision and presenting two issues: whether the rights under the special permit for a phased construction project had lapsed within the meaning of G. L. c. 40A, § 9; and whether the association had validly amended the master deed to allow the construction of phases III and IV of the project. On the plaintiffs’ motion for summary judgment, the Land Court judge entered judgment in favor of the board on the issue of lapse and in favor of the plaintiffs on the issue whether the association had validly amended the master deed.6

2. Discussion. Massachusetts law provides for de novo review of local zoning authority decisions. See Roberts v. Southwestern Bell Mobile Sys., Inc., 429 Mass. 478, 485 (1999). “On appeal to the Superior Court or Land Court, a judge determines the legal validity of a zoning board decision on the facts found by him; he gives no evidentiary weight to the board’s findings.” [127]*127Id. at 485-486, citing Josephs v. Board of Appeals of Brookline, 362 Mass. 290, 295 (1972). Judicial review is, however, circumscribed and the decision of the board “cannot be disturbed unless it is based on a legally untenable ground, or is unreasonable, whimsical, capricious or arbitrary.” MacGibbon v. Board of Appeals of Duxbury, 356 Mass. 635, 639 (1970), citing Gulf Oil Corp. v. Board of Appeals of Framingham, 355 Mass. 275, 277 (1969). In this case, the board’s decision, and the judge’s affirmance of it, are not based on a legally tenable ground and cannot stand.

General Laws c. 40A, § 9, dictates that “[zjoning ordinances or by-laws shall provide for specific types of uses which shall only be permitted in specified districts upon the issuance of a special permit” and that “such permits may . . . impose conditions, safeguards and limitations on time or use.” The statute also requires that such ordinances or bylaws “provide that a special permit. . . shall lapse within a specified period of time, not more than two years, which shall not include such time required to pursue or await the determination of an appeal referred to in section seventeen [judicial review], from the grant thereof, if a substantial use thereof has not sooner commenced except for good cause or, in the case of permit for construction, if construction has not begun by such date except for good cause.”

In accordance with the statute, the town of Bellingham enacted zoning bylaw 1500, governing the issuance of special permits. Of relevance here is § 1550, which provides that a special permit will lapse if “a substantial use thereof or construction has not begun” within twelve months of special permit approval.7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Investors v. Town Plan & Zoning Commission
344 Conn. 46 (Supreme Court of Connecticut, 2022)
Commonwealth v. Bradley
998 N.E.2d 774 (Massachusetts Supreme Judicial Court, 2013)
Atwater v. Commissioner of Education
957 N.E.2d 1060 (Massachusetts Supreme Judicial Court, 2011)
Brookins v. Boston Board of Zoning Appeals
28 Mass. L. Rptr. 123 (Massachusetts Superior Court, 2011)
81 Spooner Road, LLC v. Zoning Board of Appeals
936 N.E.2d 895 (Massachusetts Appeals Court, 2010)
Glidden v. Zoning Board of Appeals
931 N.E.2d 1002 (Massachusetts Appeals Court, 2010)
Ginsberg v. Cambridge Affordable Housing Corp.
27 Mass. L. Rptr. 141 (Massachusetts Superior Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
454 Mass. 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lobisser-building-corp-v-planning-board-of-bellingham-mass-2009.