Greater Media, Inc. v. Department of Public Utilities

614 N.E.2d 632, 415 Mass. 409
CourtMassachusetts Supreme Judicial Court
DecidedJune 7, 1993
StatusPublished
Cited by16 cases

This text of 614 N.E.2d 632 (Greater Media, Inc. v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greater Media, Inc. v. Department of Public Utilities, 614 N.E.2d 632, 415 Mass. 409 (Mass. 1993).

Opinion

Lynch, J.

This appeal by Greater Media, Inc., and interrelated cable television companies (Greater Media) challenges a decision of the Department of Public Utilities 2 (department) concerning rates charged by New England Telephone and Telegraph Company (NET) for use of conduit space. The department found that the rates charged by NET from 1984 through 1991 were not reasonable as required by G. L. c. 166, § 25A (1990 ed.), and ordered NET to reduce its rates retroactively to the date of the complaint. Greater Media, pursuant to G. L. c. 25, § 5 (1990 ed.), entered an appeal in the Supreme Judicial Court for Suffolk County. A single justice reserved and reported the case to the full court without decision. 3 We affirm.

Greater Media owns and operates cable television (CATV) systems serving approximately 72,000 customers in central Massachusetts. 4 In order to construct its cable network and extend its lines to reach its customers, Greater Media must install television cable in ducts located in underground conduit structures owned and operated by NET. 5 NET charges Greater Media an annual fee for each duct foot of NET conduit which it occupies. Beginning in 1981 and continuing until the time of this suit, NET charged $1.90 per foot per year *411 for the use of a full duct, and $.95 per foot per year for the use of a half-duct. Pursuant to G. L. c. 166, § 25A, inserted by St. 1978 c. 292, § 1, the department has the authority to prescribe “reasonable” rates for both pole and conduit attachments. See note 12, infra. While the department has not determined a specific method of calculating reasonable attachment rates, it has ruled that, under St. 1978, c. 292, § 2, “the maximum rate has two general components: (1) the capital and operating expenses (or the so-called ‘carrying charges’) and (2) the proportional share of the pole or conduit occupied by the CATV operator (or the space occupied by the CATV divided by the total usable space)” (emphasis added). 6 New England Cable Television Ass’n, D.P.U. 930 (hereafter D.P.U. 930). Should the department determine that a rate complained of is not reasonable, it has the option of terminating the unreasonable rate and substituting a reasonable one. 220 Code Mass. Regs. § 45.07 (1986).

Greater Media’s principal claim before the department was that the rates for conduit use were “unreasonable,” and it requested that the department terminate the rates, substitute new rates, and order NET to refund the amounts charged in excess of the maximum lawful rate after January 1, -1984. NET denied the claim and opposed retroactive relief. NET also argued that the department lacked authority to award retroactive relief and, even if it had such authority, it should not award such relief in this case since Greater Media unjustifiably delayed its complaint for several years.

The department found that NET’s rate for conduit space was unreasonable under G. L. c. 166, § 25A. The department reduced NET’s rates to $.84 per foot per year for use of full duct conduit space, and $.42 per foot for half-duct *412 space. The department ordered NET to' modify the agreement with Greater Media to reflect the new rate, effective October 21, 1991, the date Greater Media’s complaint was filed. The department made additional rulings which we set out in the margin. 7

In this appeal, Greater Media argues that the department improperly calculated the new rates and that its decision not to grant refunds prior to the date of the complaint was incorrect. The department calculated the rate by determining “the carrying cost to NET of its conduit and the amount of usable space, i.e., the applicable quantity of feet of duct over which such costs should be distributed.” 8 As the data source for its calculations, the department adopted Greater Media’s proposal and used NET’s “Form M,” a report filed with the Federal Communications Commission (FCC). 9 The method for calculating the “conduit carrying cost” figure arrived at is not disputed. 10

The “amount of usable space,” however, is the center of Greater Media’s first argument on appeal. The department stated: “In order to calculate the fully allocated conduit carrying cost on a per-foot basis, we must first determine the total number of duct feet to which costs shall be allocated.” Greater Media argued that the department should calculate this amount using the total amount of installed NET duct feet in Massachusetts as listed on NET’s Form M. Use of this figure would have decreased Greater Media’s share of *413 costs since the total conduit costs would be allocated to more space, and Greater Media’s share of the total space would be lower. The department, however, found it “appropriate to modify the Form M data to reflect the [duct] space that is unusable because it is reserved for maintenance and for municipalities.” 11

1. Claim under G. L. c. 166, § 25A. Greater Media first argues that the department’s exclusion of unusable conduit space was contrary to St. 1978, c. 292, § 2. 12 That statute limits maximum attachment rate to:

*414 “[No] more than the proportional capital and operating expenses of the utility attributable to that portion of the pole, duct or conduit occupied by the attachment. Such portion shall be computed by determining the percentage of the total usable space on a pole or the total capacity of the duct or conduit that is occupied by the attachment” (emphasis added). St. 1978, c. 292, § 2.

Greater Media claims that the statute requires the department to apply a different standard for poles and conduits, and that the department erred by including only usable space, and not “the total capacity of the duct or conduit,” in its calculations. We disagree.

In questions of statutory interpretation, “ordinary precepts of statutory construction instruct us to accord deference to an administrative interpretation of a statute.” Massachusetts Org. of State Eng’rs & Scientists v. Labor Relations Comm’n, 389 Mass. 920, 924 (1983). This is particularly so “where, as here, an agency must interpret a legislative policy which is only broadly set out in the governing statute.” Id.,. quoting School Comm. of Springfield v. Board of Educ., 362 Mass. 417, 442 (1972). General Laws c. 166, § 25A, and St. 1978, c. 292, § 2, confer broad authority on the department to calculate and to enforce reasonable rates. In its 1984 order interpreting G. L. c. 166, § 25A, and St. 1978, c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stoneham Retirement Board v. Contributory Retirement Appeal Board
32 Mass. L. Rptr. 607 (Massachusetts Superior Court, 2015)
Shea v. Benedetti
32 Mass. L. Rptr. 157 (Massachusetts Superior Court, 2014)
Lobisser Building Corp. v. Planning Board of Bellingham
454 Mass. 123 (Massachusetts Supreme Judicial Court, 2009)
Huezo v. Chelsea Housing Authority
25 Mass. L. Rptr. 22 (Massachusetts Superior Court, 2008)
Maffei v. Roman Catholic Archbishop
449 Mass. 235 (Massachusetts Supreme Judicial Court, 2007)
Morelli v. Metropolitan Property & Casualty Insurance
10 Mass. L. Rptr. 207 (Massachusetts Superior Court, 1999)
Augustine v. Rogers
710 N.E.2d 1030 (Massachusetts Appeals Court, 1999)
Jacobus v. Board of Appeal on Motor Vehicle Liability Policies & Bonds
7 Mass. L. Rptr. 401 (Massachusetts Superior Court, 1997)
Thomas v. Commissioner of Division of Medical Assistance
425 Mass. 738 (Massachusetts Supreme Judicial Court, 1997)
Daddario v. Cape Cod Commission
681 N.E.2d 833 (Massachusetts Supreme Judicial Court, 1997)
Globe Newspaper Co. v. Beacon Hill Architectural Commission
421 Mass. 570 (Massachusetts Supreme Judicial Court, 1996)
Cameron v. Carelli
653 N.E.2d 595 (Massachusetts Appeals Court, 1995)
Kates v. Board of Education
4 Mass. L. Rptr. 112 (Massachusetts Superior Court, 1995)
Massachusetts Oilheat Council v. Department of Public Utilities
641 N.E.2d 1318 (Massachusetts Supreme Judicial Court, 1994)
Bosley v. Department of Public Utilities
631 N.E.2d 47 (Massachusetts Supreme Judicial Court, 1994)
Central Water District Associates v. Department of Environmental Protection
2 Mass. L. Rptr. 81 (Massachusetts Superior Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
614 N.E.2d 632, 415 Mass. 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greater-media-inc-v-department-of-public-utilities-mass-1993.