Bernstein v. Chief Building Inspector & Building Commissioner of Falmouth

754 N.E.2d 133, 52 Mass. App. Ct. 422, 2001 Mass. App. LEXIS 846
CourtMassachusetts Appeals Court
DecidedAugust 31, 2001
DocketNo. 99-P-730
StatusPublished
Cited by6 cases

This text of 754 N.E.2d 133 (Bernstein v. Chief Building Inspector & Building Commissioner of Falmouth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernstein v. Chief Building Inspector & Building Commissioner of Falmouth, 754 N.E.2d 133, 52 Mass. App. Ct. 422, 2001 Mass. App. LEXIS 846 (Mass. Ct. App. 2001).

Opinion

Greenberg, J.

The underlying issue in this case is whether, as ruled by a judge of the Land Court, Stubom Limited Partnership, an assignee of certain condominium development rights (developer), may construct a fifth building more than two years after a special permit has issued. Preliminarily, there is a question whether the plaintiff, as a unit owner, independent of the trustees of the condominium association, has standing to contest the chief building inspector and commissioner’s (commissioner) decision under the circumstances presented here. The Land Court found that the plaintiff has standing. The judge entered a partial judgment in the defendants’ favor appropriately certified pursuant to Mass.R.Civ.P. 54(b), 365 Mass. 821 (1974). The plaintiff appealed.2

On August 28, 1997, the Zoning Board of Appeals of Fal-mouth (board) issued a decision upholding the finding of the town’s commissioner that a special permit to construct “Building Five” of a condominium complex remained valid. The trustees of the Cape Codder Condominium Trust (trustees) filed a complaint pursuant to G. L. c. 40A, § 7, contesting the board’s decision.3 The plaintiff filed a separate complaint appealing the same decision. The Land Court judge ruled against the plaintiff, and this appeal followed.

The question arose in the following manner. The board granted a special permit for the construction of a condominium in five phases on the site of the former Cape Codder Hotel complex. The board found the condominium project consistent with that preexisting, nonconforming use. Under the permit, the [424]*424developer would restore the “turn of the century” Cape Codder hotel building and would raze other buildings on the property and replace them with buildings containing residences. As the final phase, a new building, designated on its plans as “Building Five” (building five) could be built. Neither the settlement agreement between the abutters to the property for which the relevant special permit had been issued and the developer — which settlement agreement allowed the issuance of the special permit — nor the permit itself placed any time limitations within which the construction was to be completed. None of the interested parties appealed from the grant of the special permit in 1986.

In 1987 the developer sought and received a modification of the original permit. Amongst other provisions, this modification allowed the developer to raze the original hotel building. Between 1987 and 1989 four buildings, containing twenty units, were built. The condominium master deed was recorded on October 19, 1989. Pursuant to its terms, the developer reserved the right to increase the number of units from twenty to forty-seven, including those contained in proposed building five. The master deed stated that the right to make certain improvements and to construct building five expired in ten years (on October 19, 1999).

In 1990, the developer sought to modify the original permit to revise various design plans and to extend the time for starting construction of building five. After a public hearing, the board issued its decision, ruling on five discrete issues. Because of the impending economic slow-down, among other things, the board acceded to the developer’s request to delay construction of the fifth and final phase until after the summer of 1991, possibly to October, 1991. As a basis for the extension, the board found that: “[t]he delay in construction will afford the neighbors an extended break from construction activity, and by virtue of economic and marketing conditions allow the developer to complete the project, including the further planning and erection of the revised building which may be more expensive than the previously proposed structure.”

Next the developer, aggrieved by several conditions imposed by the board in granting the modifications, filed an appeal. [425]*425However, before the appeal was decided, a judge of the Land Court, with the assent of all parties, remanded the case to the board. After a second public hearing, held on May 5, 1993, the board amended its 1990 decision and granted the developer additional modifications. It incorporated by reference the findings and conditions of the original 1990 decision. However, the board did not set the October, 1991, deadline as a condition of the permit.

In July, 1992, the plaintiff purchased his unit from the owner of record, Sippewissett Development. Neither the plaintiff, the condominium association, nor any of the abutters appealed the board’s grant of the modifications to the special permit in 1993.

By 1997, four years after the grant of modifications to the special permit, this developer acquired all of the development rights and prepared to construct building five. The attorney for the trustees requested the commissioner, pursuant to G. L. c. 40A, § 7, to determine that no building permit should issue pursuant to the special permit because the special permit had lapsed. The commissioner determined that there were no current violations of the special permit and declined to grant the trustees any relief. An appeal to the board followed.

The board, in affirming the commissioner’s decision, noted that the infrastructure, including the septic system for building five, had been completed in a timely manner and that the trustees were on notice of potential delay because the master deed expressly referenced additional construction. The board found that the trustees could have, but did not, appeal the 1993 decision modifying the special permit, which was duly recorded and remains the “most recent valid decision.” The board ruled that there was no condition “in the 1993 decision limiting the time in which the developer had to complete the project.”

The board observed that the special permit, as modified in 1993, clearly anticipated future construction. It concluded that “unless a special permit has a condition restricting the time for development, once the developer has activated the special permit it is valid indefinitely.” In addition, the board confirmed the commissioner’s decision, because there had been “substantial use and/or commencement of construction.” It found that the [426]*426construction delay was for good cause, noting the “dramatic decline in the economy in the early ’90’s, particularly the demand for condominium units.”

The subsequent appeal by Bernstein was decided by a judge of the Land Court on cross motions for summary judgment. The board took the position that Bernstein lacked standing to pursue this appeal. The judge ruled explicitly on that contention and concluded that Bernstein had standing. He held, in effect, that Bernstein’s enforcement request was without merit because the special permit as modified in 1993 was not subject to any deadline. He noted that the October, 1991, “deadline” that the developer proposed was not incorporated as a condition in any special permit. He also ruled that the permit had not expired pursuant to G. L. c. 40A, § 9. He declined to rule on other claims asserted by Bernstein that were moot or not ripe for adjudication.

We agree with the board and the developer that the language of G. L. c. 183A, § 10(b)(4), as inserted by St. 1963, c. 493, § 1, places limits on a unit owner’s ability to litigate certain issues. In pertinent part, the statute states that a condominium “association shall have, among its other powers, the following rights and powers: . . . [t]o conduct litigation ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Investors v. Town Plan & Zoning Commission
344 Conn. 46 (Supreme Court of Connecticut, 2022)
Bourgault v. Gooding
30 Mass. L. Rptr. 571 (Massachusetts Superior Court, 2013)
Lobisser Building Corp. v. Planning Board of Bellingham
454 Mass. 123 (Massachusetts Supreme Judicial Court, 2009)
Johnson v. Town of Wolfeboro Planning Board
945 A.2d 13 (Supreme Court of New Hampshire, 2008)
McDermott v. Board of Appeals
796 N.E.2d 455 (Massachusetts Appeals Court, 2003)
Aldrich v. ADD Inc.
437 Mass. 213 (Massachusetts Supreme Judicial Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
754 N.E.2d 133, 52 Mass. App. Ct. 422, 2001 Mass. App. LEXIS 846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernstein-v-chief-building-inspector-building-commissioner-of-falmouth-massappct-2001.