Lj Vontz Const. v. State, Dept. of Roads

432 N.W.2d 7, 230 Neb. 377, 1988 Neb. LEXIS 414
CourtNebraska Supreme Court
DecidedNovember 18, 1988
Docket88-156, 88-157
StatusPublished
Cited by19 cases

This text of 432 N.W.2d 7 (Lj Vontz Const. v. State, Dept. of Roads) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lj Vontz Const. v. State, Dept. of Roads, 432 N.W.2d 7, 230 Neb. 377, 1988 Neb. LEXIS 414 (Neb. 1988).

Opinion

Shanahan, J.

The appeals by L. J. Vontz Construction Co., Inc., pertain to Vontz’ two claims filed with the Director of Administrative Services, who found that Vontz’ claims were not based on contracts with the Department of Roads of the State of Nebraska, but were tort claims for which the director lacked jurisdiction to determine whether the claims were meritorious.

In April 1983, Vontz entered two construction contracts with the State’s Department of Roads (DOR) to repair asphalt shoulders on roads in Platte and Fillmore Counties, including asphalt removal, compacting the subgrade soil, recycling the removed asphalt, and replacing asphalt on road shoulders. Each of the Vontz-DOR contracts contained a clause incorporating “the general and detailed plans, the 1973 Standard Specifications for Highway Construction . . . ; the *378 contractor’s bond; the proposal; all special provisions; and all supplemental agreements” into the contract. Section 102.07 of the DOR’s 1973 Standard Specifications for Highway Construction provides in part that the DOR “will prepare full, complete, and accurate plans and specifications giving such directions as will enable any competent mechanic or contractor to carry them out.” The contracts also provided that Vontz “shall not do any work ... not covered and authorized by this contract, unless ordered in writing by the Engineer.”

On May 27, 1983, Vontz began removing the asphalt shoulders in the Fillmore County project and encountered “very wet subgrade soil conditions,” which made mechanical soil compaction impossible without DOR’s further directions. In spite of Vontz’ repeated requests, DOR provided no further directions until June 24, 1983, when DOR directed Vontz to remove, mix, dry, and recompact the wet subgrade soil. When Vontz encountered further unstable subgrade soil conditions during the “lay-down” phase of the project in Fillmore County, DOR’s project engineer required that the unstable areas be “cored out” and filled with recycled asphalt. As a result of the subgrade soil conditions, the Fillmore County project was substantially delayed and required Vontz to use additional road barricades and safety equipment, which cost in excess of $5,000.

On August 16, DOR informed Vontz that 33 percent of the allotted time for completion of the Platte County project had expired, but no work had been completed on the project. According to Vontz, DOR knew that Vontz contemplated completion of the Fillmore County project before Vontz would move its equipment to the Platte County project. Since the Fillmore County project was delayed by DOR’s tardy responses to the problems involving subgrade soil conditions, the Platte County project was not underway according to schedule.

On August 17, Vontz completed major items of the Fillmore County project but was unable to finish the entire project because irrigation runoff had flooded the site for construction of a culvert. Vontz claimed that DOR’s conduct in administering and engineering the Fillmore County project had delayed major asphaltic work for 30 days and minor work for *379 “several months.”

On receipt of DOR’s notice about lack of progress on the Platte County project, Vontz began work on the project by surface-milling the shoulders as required by a supplemental agreement with DOR. After milling for 4 days, Vontz had to stop because another contractor’s work on a requisite culvert had not been completed. Vontz maintained that DOR failed to require the culvert contractor to expedite its work in compliance with the specifications for the Platte County project. Further, Vontz claimed that it could have moved its milling operations to the other side of the culvert and continued operations if DOR had provided a stockpile area. In spite of Vontz’ requests, DOR did not provide a stockpile area until June 14,1984.

Vontz further contended that DOR’s plans and specifications were incorrect in the assessment of water levels in four designated “borrow pits” specified for the projects. As a result of the water level discrepancies, Vontz was able to remove less material than needed from the pits and also had to use special equipment to remove wet material, which had to be hauled to a site for drying and processing before use in the projects.

Vontz also claimed that DOR’s project inspector, without good reason, repeatedly rejected Vontz’ work on the Platte County project and even suspended project operations on November 9,1983. DOR’s final inspection of the Platte County project occurred on October 1,1985.

In its claims, Vontz asserted that DOR’s initial plans and specifications were inadequate and, consequently, necessitated additional compaction work. Vontz also asserted that DOR erroneously computed the amounts due under the contracts. For the Fillmore County project, Vontz claimed that DOR incorrectly deducted in excess of $18,000 under the contract’s provision for liquidated damages. For the Platte County project, Vontz asserted that the DOR “required the Claimant to perform work under bid items, but beyond the plans and specifications and made no measurement or payment of these items.”

Containing statements of the facts and circumstances set forth above in relation to the construction contracts, Vontz’ *380 claims were filed with the Director of Administrative Services pursuant to Neb. Rev. Stat. § 81-1170 (Reissue 1987), which provides in part:

All persons having claims against the state, except claims for overpayment of estate taxes and except claims within the jurisdiction of the State Claims Board, shall exhibit the same, with the evidence in support thereof, to the Director of Administrative Services to be audited, settled, and allowed within two years after such claims shall accrue.

Alleging that the Director of Administrative Services lacked jurisdiction to dispose of the claims, DOR requested dismissal of Vontz’ claims. The Director of Administrative Services concluded:

The question before the Director of Administrative Services is whether the Director has jurisdiction over these claims as contract claims. The issue for decision is whether the claims are tort claims or contract claims.
Tort claim is defined in Neb. Rev. Stat. §81-8,210(40 [sic] (Reissue 1981) which, in part provides: “Tort claim shall mean any claim against the State of Nebraska for money only on account of damage to or loss of property or on account of personal injury or death, caused by the negligent or wrongful act or omission of any employee of the state, while acting within the scope of his office or employment____”
The claimant has contended that the state was negligent in drafting contract specifications, special provisions, and construction plans; and interference with claimants [sic] performance of the contract. Clearly, the claims are tort claims as that term is defined in Neb. Rev. Stat. §81-8,210(4) (Reissue 1981) of the Tort Claims Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Huff v. Otto
28 Neb. Ct. App. 646 (Nebraska Court of Appeals, 2020)
Henriksen v. Gleason
643 N.W.2d 652 (Nebraska Supreme Court, 2002)
Cimino v. FirsTier Bank, NA
530 N.W.2d 606 (Nebraska Supreme Court, 1995)
Thomas v. Countryside of Hastings, Inc.
524 N.W.2d 311 (Nebraska Supreme Court, 1994)
Weatherly v. Blue Cross Blue Shield Insurance
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
Weatherly v. BLUE CROSS BLUE SHIELD INS.
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
Thomas v. Countryside of Hastings, Inc.
512 N.W.2d 660 (Nebraska Court of Appeals, 1994)
J.L. Healy Construction Co. v. State
463 N.W.2d 813 (Nebraska Supreme Court, 1990)
Nelson v. Production Credit Ass'n of the Midlands
729 F. Supp. 677 (D. Nebraska, 1989)
Hiway 20 Terminal, Inc. v. Tri-County Agri-Supply, Inc.
443 N.W.2d 872 (Nebraska Supreme Court, 1989)
Security Investment Co. v. State
437 N.W.2d 439 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
432 N.W.2d 7, 230 Neb. 377, 1988 Neb. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lj-vontz-const-v-state-dept-of-roads-neb-1988.