Live Oak Lumber Co. v. Farr

153 P. 741, 28 Cal. App. 641, 1915 Cal. App. LEXIS 393
CourtCalifornia Court of Appeal
DecidedOctober 21, 1915
DocketCiv. No. 1389.
StatusPublished
Cited by6 cases

This text of 153 P. 741 (Live Oak Lumber Co. v. Farr) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Live Oak Lumber Co. v. Farr, 153 P. 741, 28 Cal. App. 641, 1915 Cal. App. LEXIS 393 (Cal. Ct. App. 1915).

Opinion

BURNETT, J.

The appeal is from a judgment in favor of plaintiff and respondent for lumber and material furnished to William F. Farr to be used and which was used in the construction of a sewer system for the city of Gridley, a municipal corporation of the sixth class. The action was brought under the provisions of the so-called Bond Act, approved March 27, 1897 (Stats. 1897, p. 201), as amended in 1911 (Stats. 1911, p. 1422).

The complaint contains two counts, one for the material furnished by plaintiff and the other on an assigned claim for *643 similar material furnished by the Diamond Match Company. A demurrer interposed by defendants was overruled and an answer was filed, and a trial had before the court. The appeal is on the judgment-roll alone.

1. There is no merit in the contention that by specific averment it should appear that the city was authorized to order the work done. The contract of suretyship upon which the action was brought contains this provision. “The condition of the above obligation is such that, whereas, the board of trustees of the city of Gridley, a municipal corporation of the sixth class, of the county of Butte, state of California, has heretofore awarded a contract to the above-named principal to do and perform the following work in said city of Gridley: . . . Now, therefore, if the above bounden William F. Farr fails to pay for any materials or supplies furnished for the said work contracted to be done, or for any work or labor thereon of any kind, the sureties on this bond will pay the same.” Having recited in their undertaking the execution of said contract and, upon the strength of said recital, having induced materialmen to deliver material to be used under said contract, the sureties are estopped from saying that the contract was invalid. (People v. Jenkins, 17 Cal. 500; People v. Huson, 78 Cal. 154, [20 Pac. 369] ; Kiessig v. Allspaugh, 91 Cal. 234, [27 Pac. 662]; Moore v. Earl, 91 Cal. 632, [27 Pac. 1087] ; People v. Hammond, 109 Cal. 384, [42 Pac. 36].)

Besides, the presumption would be that the contract was legal, and if otherwise the burden would be upon defendants so to assert and prove. Indeed, the allegation of the ultimate fact that said Farr “entered into a written agreement with the city of Gridley . . . whereby said William F. Farr did covenant and agree to construct for said city a sewer system,” etc., necessarily carried the implication that said contract was in accordance with the requirement of the law. This is true, at least, where the contract is, as here, manifestly within the scope of the authority granted to municipalities.

2. The second point made by appellants is that the complaint is insufficient because of its failure to allege that the work under the contract was completed. Indeed, it is expressly averred “that said work has never been completed.” The contention that the action was prematurely brought is *644 based upon the fact that said act provides that the claims must be filed “within ninety days after the completion of the whole work.” The significance of this expression, however, was elaborately considered in French v. Powell, 135 Cal. 636, [68 Pac. 92], in an opinion written by Commissioner Chip-man. As stated therein, “Plaintiff’s complaint sets forth three causes of action upon a bond executed by defendant Powell, as principal, and defendant company, as surety, under the provisions of the act of March 27, 1897 (Stats. 1897, p. 201). It is alleged that Powell entered into an agreement with the city of Los Angeles on February 8, 1889, to construct a tunnel in Third Street, from Hill to Flower streets, and to furnish at his own cost all the labor and material necessary therefor, amd that said work was never completed.” This case in every essential is like the one at bar and respondent’s position was expressly approved that said language “shall within thirty days after the completion of the whole work” was meant simply “to set a limit of time after which such claims could not be filed and not to forbid the filing of a claim before the completion of the whole work, provided the claimant’s demand is past due.” Said decision has never been overruled, although it is the contention of appellants that two later decisions are in conflict with it. The first of these is Republic Iron etc. Co. v. Patillo, 19 Cal. App. 316, [125 Pac. 923], being an action under the so-called Vrooman Act. Therein the claimant was required to file a verified statement with the street superintendent, setting forth the amount of his claim, “within thirty days from the time the improvement was completed. ’ ’ In the opinion it is declared : “It may be said that until the street improvement work had been completed, under the terms of the statute the notice of plaintiff’s claim could not have been properly filed, and any action brought on the bond prior to such completion, or before the occurrence of such events as might make a showing of formal completion unnecessary, would be premature.” It is apparent, however, that the foregoing statement was unnecessary to the decision, as the vital defect in the case was the failure of the claimants to file their verified claim.

A similar situation existed in the other case, Miles v. Baley, 170 Cal. 151, [149 Pac. 45], in which the supreme court adopted the opinion of this court prepared by Justice Hart. The decisive question in that case was whether the bond is what *645 is known as a “common-law bond” or a statutory undertaking, appellant having contended that it was the former and that, therefore, it was not necessary to file a claim with the board of trustees as required by the statute.

As to both these cases, it appearing that the claimant had failed entirely to perform an act made essential by the statute to constitute a cause of action, it is quite plain that a discussion of the question as to the exact time when such act should be performed was of mere academic interest. In neither of said eases was the attention of the court called to the decision in French v. Powell, for the quite manifest reason, probably, that it was not in point as it involved the actual fling of a claim before the improvement was completed, while they were concerned with a situation where the improvement had been completed but no claim was filed at all.

The foregoing consideration involves the principal objection made to the complaint and is, as we think, not tenable. Indeed, appellants’ synopsis of the complaint indicates its sufficiency. It is as follows: An allegation of “1. The incorporation of plaintiff. 2. The execution of a contract for the construction of a sewer with the city of Gridley and defendant Farr. 3. The execution of the bond by defendant Farr as principal, and defendants, Smith and Hueberger, as sureties. 4. The approval of the bond by the board of trustees of said city. 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reifke v. State
31 A.D.2d 67 (Appellate Division of the Supreme Court of New York, 1968)
Fan Co. v. United States
29 Cust. Ct. 231 (U.S. Customs Court, 1952)
Hamilton v. Abadjian
179 P.2d 804 (California Supreme Court, 1947)
Young v. Waldrop
109 P.2d 59 (Montana Supreme Court, 1941)
Kirkpatrick v. Douglas
65 P.2d 1169 (Montana Supreme Court, 1937)
National Surety Co. v. W. H. Holliday Co.
295 P. 913 (Wyoming Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
153 P. 741, 28 Cal. App. 641, 1915 Cal. App. LEXIS 393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/live-oak-lumber-co-v-farr-calctapp-1915.