Linan-Faye Construction Co. v. Housing Authority

797 F. Supp. 376, 1992 U.S. Dist. LEXIS 12897, 1992 WL 207546
CourtDistrict Court, D. New Jersey
DecidedAugust 24, 1992
DocketCiv. A. No. 90-4651
StatusPublished
Cited by4 cases

This text of 797 F. Supp. 376 (Linan-Faye Construction Co. v. Housing Authority) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linan-Faye Construction Co. v. Housing Authority, 797 F. Supp. 376, 1992 U.S. Dist. LEXIS 12897, 1992 WL 207546 (D.N.J. 1992).

Opinion

OPINION GRANTING DEFENDANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT

IRENAS, District Judge.

This matter comes before the Court on defendant’s motion for partial summary judgment under Fed.R.Civ.P. 56(c) seeking to dismiss Count Three of the Complaint on the ground that plaintiff cannot prevail as a matter of law on its claim under 42 U.S.C. § 1983. For the reasons hereinafter set forth, this motion will be granted.

BACKGROUND

This long-standing dispute arose over the September 30, 1988 award to plaintiff, Li-nan-Faye Construction Co., Inc. (“LinanFaye”), of a construction contract in the amount of $4,264 million by the defendant, the Housing Authority for the City of Camden (“HACC”), for the rehabilitation of 244 low-income housing units at the McGuire Gardens Project in Camden. Plaintiff was apparently the low bidder, underbidding the next highest proposal by approximately $600,000.

In October and November disagreements arose with respect to some of the specifications, and HACC attempted to re-bid the project to find a new contractor. To enforce its rights to go forward on the project, plaintiff filed a complaint and order to show cause on December 20, 1988.

On December 21, this court entered a Temporary Restraining Order to prevent the re-bidding. On December 27, the parties met to resolve the matter, and the case was settled pursuant to a Stipulation of Settlement and Order of Dismissal with Prejudice (“Settlement Order”), which was approved and entered by this Court on January 23, 1989. The Settlement Order required the parties to execute the contract documents relating to the project, but Paragraph 2 specified that:

Nothing herein shall be construed to interpret nor pass upon the language of the contract, nor the obligations of the respective parties thereunder; nor shall this Stipulation and Order be construed to alter or amend the contract terms.

For purposes of this motion the court accepts plaintiff’s allegation that it fully signed all the required contract documents on January 5, 1989, (the “Contract”) but did not receive back a copy countersigned by defendant until November 29, 1989.

Paragraph 16 of the General Conditions to the Contract provide for a termination in the event of a default by the contractor, while Paragraph 17 allows a termination without cause whenever defendant determines that such termination “is in the best interest of” the defendant. This paragraph [378]*378is captioned “Termination for Convenience.”

Disputes quickly broke out again. Defendant asserts that plaintiff presented numerous problems or potential problems that it insisted be resolved by HACC before it would start work. Linan-Faye, on the other hand, asserts that it wanted to start work throughout 1989 but never received the signed contract documents or a Notice to Proceed from HACC.

HACC issued a Notice to Proceed on November 22, 1989, directing plaintiff to repair certain plumbing problems that were part of the over-all contract, but LinanFaye refused to proceed piece-meal, insisting that it would not begin until a certain number of vacant buildings were available at the same time so it could achieve economies of scale.

HACC then proposed pulling the plumbing portion out of the contract, and subsequently proposed a complete buy-out of Linan-Faye’s contract. The parties discussed the possibility of a buyout from early 1990 until July, 1990, at which time HUD informed HACC that it would not approve a buy-out. By letter of July 23, 1990, HACC reinstated the previous Notice to Proceed and set a start date 30 days hence.

A preconstruction meeting was held on September 6, 1990 at which Linan-Faye allegedly stated that it could not start work until the contract price was increased to reflect the passage of time. HACC under instructions from HUD, insisted that Li-nan-Faye must begin work before the price increase issue could be addressed. HACC asserts that because Linan-Faye still refused to begin work at that point, HACC elected to terminate Linan-Faye’s contract and did so by letter dated September 25, 1990. After objecting to HACC’s termination, Linan-Faye filed the instant suit on October 26, 1990.

DISCUSSION

The standard for granting a motion for summary judgment under Fed.R.Civ.P. Rule 56(c) is demanding and stringent. Wilson v. Sullivan, 709 F.Supp. 1351 (D.N.J.1989). Under Fed.R.Civ.P. Rule 56(c), “summary judgment is proper ‘if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.’ ” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). The Court has stated that “a party opposing a properly supported motion for summary judgment may not rest upon the mere allegations or denials of his pleading, but ... must set forth specific facts showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986) (citation omitted) (internal quotations omitted).

At the summary judgment stage, it is not the role of the judge to weigh the evidence or to evaluate its credibility but to determine “whether there is a genuine issue for trial.” Id, at 249, 106 S.Ct. at 2510. There is no issue for trial unless there is sufficient evidence favoring the non-moving party such that a reasonable jury could return a verdict for that party. Id. Although the moving party bears the initial burden of informing the district court of the basis for its motion, there is no requirement in the Rule that the moving party support its motion with affidavits or other similar materials negating the opponent’s claim. Celotex, 477 U.S. at 323, 106 S.Ct. at 2552-53.

The substantive law governing the dispute will determine which facts are material, and only disputes over those facts “that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Anderson, at 248, 106 S.Ct. at 2510. Finally, summary judgment should be granted unless a dispute over a material fact is genuine, which the Court has defined as such that “a reasonable jury could return a verdict for the non-moving party.” Id.

Plaintiff argues that it had a property interest in the contract awarded to it by defendant, and that defendant’s subsequent termination without a notice and [379]*379hearing deprived plaintiff of its property without due process of law and in violation of the Equal Protection clause. Accordingly, plaintiff argues the termination violated its rights under the fourth, fifth and fourteenth amendments of the Constitution. Count Three of the Complaint has asserted this federal civil rights claim under 42 U.S.C. § 1983.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
797 F. Supp. 376, 1992 U.S. Dist. LEXIS 12897, 1992 WL 207546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linan-faye-construction-co-v-housing-authority-njd-1992.