This text of 60 P. 176 (Limberg v. Glenwood Lumber Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Limberg v. Glenwood Lumber Co., 60 P. 176, 127 Cal. 598, 1899 Cal. LEXIS 664 (Cal. 1899).

Opinion

GAROUTTE, J.

Defendant appeals from a judgment and *599 order denying a motion for a new trial. The action is one for damages for personal injuries, and arises upon the following state of facts, as testified to hy the plaintiff and his witnesses:

Plaintiff was a teamster of experience, forty-one years of age. He was hired hy defendant to haul lumber with a wagon and four horses. He continued in this employment for a period of eleven months; then, while traveling upon the public road with his loaded wagon, he fell therefrom beneath the wheels, and the loss of a leg was the result. He asserts negligence upon the part of the defendant in this, that the appliances furnished him with which to do the work were defective. These defective appliances consisted of a wagon having no seat, and also of a pair of lines that were too short. It may he conceded that if either of these defects had not existed the accident would not have happened. A short time after the hiring of plaintiff he complained to defendant at two different times that the lines were too short, but never made any complaint as to the lack of á seat upon the wagon. Defendant made no promise to remedy the defective lines, hut remained silent when the complaints were made. From the foregoing state of facts it is insisted hy defendant that the motion for nonsuit should have been granted, and it is also claimed that the evidence does hot support the verdict and judgment. The contention in substance is but a. single one, and the sufficiency of the evidence is the question before the court. Testing the facts of this case hy the law, we cannot see how plaintiff is entitled to recover. It may he conceded that defendant was negligent in not furnishing plaintiff with proper appliances to do the work. Such concession being made, then the question presented is not strictly one of contributory negligence upon the part of the plaintiff, hut, rather, Did plaintiff assume the risk of working with these defective appliances? If there had been an express contract between the master and servant that the work should he done without a seat to the wagon, and with these, identical lines, clearly that agreement would have barred a recovery in this action. This being so, do not the facts indicate an implied contract to the same effect? While the servant only assumes the dangers and risks necessarily incident to the work to he performed, he may, hy contract, either express or implied, also *600 assume the risk of working with defective appliances. Indeed, many cases go further and sustain the proposition that, where the servant proceeds at the outset to perform his work with defective appliances, having knowledge of the defect, then an implied contract arises to the effect that he assumes the risk— especially so if he is aware of the danger surrounding him by reason of the defect. And to say that the servant assumes the risk is but another way of saying that he impliedly agrees to release the master from liability.

In this case we lay aside any question as to the lack of a seat upon the wagon. If the wagon was defective in this regard, the plaintiff, an expert teamster, by using it for a period of eleven months, without objection or protest of any kind, assumed all of the risks incident to the use of that kind of a wagon. We have found no case in the books involving anything like a similar state of facts which holds that plaintiff may recover damages for injuries received. We know of but a possible exception to the rule, and that would be a ease where the servant, though aware of the defect, was not aware of the danger incident to it. That exception cannot be urged here. This defect of the wagon was of a character that the servant, as a reasonably prudent man, must have b'een aware of the danger incidental to its use. He cannot be allowed to close his eyes to the danger, and thereafter say, “I did not know it was dangerous.”

As to the defective lines, additional principles of law are involved to those arising upon the defect of the wagon, for, as to the lines, the plaintiff made complaint to defendant on two different occasions regarding their defective character. Yet when we pause to consider that the last complaint was made more than nine months before the accident, and to consider the additional fact, pregnant with materiality here, that defendant remained silent under the complaint of .the servant, and gave no promise to cure the defect, the case as to the two respective defects is not widely variant. Plaintiff knew of the defect, and must have known of the danger that surrounded him by reason of it. Any reasonably prudent man must have been aware of it, and the defendant must be held to be a man of ■ ordinary prudence; indeed, it appears that he was an expe *601 rienced teamster. Here the master gave no intimation to the servant that he would remedy the defect, and allowed it to continue for nine months without taking a step toward remedying it. Under these circumstances, the servant, at the time of the accident, was not working in expectation that the defect would yet be remedied. After a lapse of nine silent months he had 'no right to indulge in any such expectation. Many cases hold that when th'e master, after complaint made, promises to correct the defect, the servant may continue his employment for a reasonable time, relying upon the master’s promise, but here we have no promise. lYe also have the lapse of a most unreasonable time. The mere fact that the servant malees complaint of the defect gives him no right to rely for all future time upon the complaint made, and thus irrevocably fasten a liability upon the master. If the master had positively refused to correct the defect when the complaint was made to him, then certainly the servant would have been forced by the law to do either one of two things—either assume the risk, and thus release the master from liability, or leave the master’s employment. In this case the same conditions substantially arose when a reasonable time had gone by after the making of the complaint to the master, and nothing had been done, or even promised. After complaint made, and nine months had come and gone, the plaintiff had no right as a reasonable man to believe that the master would remedy these defective lines.

The law of this question, as declared by text-books and decisions of courts, is in line with the foregoing views. Shearman and Eedfield on Hegligence, a work more friendly to servants than any other standard text-book, declares: “The latest and best authorities hold that the liability of the master for risks caused by his negligence, which did not exist when the servant accepted the employment, depends upon a 'question of fact whether a servant who works on, appreciating the risk, assumes it voluntarily or endures it, because he feels constrained to/ If he voluntarily continues work with full notice of the risk, he assumes it, but not so if he acts under coercion.” There certainly is no question of coercion in this case. It is said in Stephenson v. Duncan, 73 Wis. 408, 9 Am. St. Rep. 806: “But if the plaintiff did continue his employment for a reasonable *602 time after the defendant could have removed the defects, he would then he deemed to have waived his objections and assumed the risk of operating the machinery in the unsafe and dangerous condition in which it was.” We find the following language in Hough v. Railway Co., 100 U. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hatfield v. Levy Brothers
117 P.2d 841 (California Supreme Court, 1941)
Wilkerson v. City of El Monte
62 P.2d 790 (California Court of Appeal, 1936)
Gorman v. County of Sacramento
268 P. 1083 (California Court of Appeal, 1928)
Cheffings v. Hines
206 P. 726 (Oregon Supreme Court, 1922)
Morris v. Sierra & San Francisco Power Co.
207 P. 262 (California Court of Appeal, 1922)
Wintermute v. Oregon-Wash. R. & N. Co.
194 P. 420 (Oregon Supreme Court, 1921)
Webster v. Orr
163 P. 361 (California Supreme Court, 1917)
Titus v. Anaconda Copper Min. Co.
133 P. 677 (Montana Supreme Court, 1913)
Lonnergan v. Stansbury
129 P. 770 (California Supreme Court, 1913)
Hall v. Clark
125 P. 1047 (California Supreme Court, 1912)
Bresette v. E. B. & A. L. Stone Co.
121 P. 312 (California Supreme Court, 1912)
Dow v. Sunset Telephone & Telegraph Co.
106 P. 587 (California Supreme Court, 1910)
Parkin v. Grayson-Owen Co.
106 P. 210 (California Supreme Court, 1909)
Rase v. Minneapolis, St. Paul & Sault Ste. Marie Railway Co.
120 N.W. 360 (Supreme Court of Minnesota, 1909)
Pre v. Standard Portland Cement Co.
100 P. 122 (California Court of Appeal, 1908)
Coulter v. Union Laundry Co.
87 P. 973 (Montana Supreme Court, 1906)
Lee v. Salt Lake City
83 P. 562 (Utah Supreme Court, 1905)
Meek v. De Latour
83 P. 300 (California Court of Appeal, 1905)
Helling v. Schindler
78 P. 710 (California Supreme Court, 1904)
Limberg v. Glenwood Lumber Co.
78 P. 728 (California Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
60 P. 176, 127 Cal. 598, 1899 Cal. LEXIS 664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/limberg-v-glenwood-lumber-co-cal-1899.