Lieberman Properties Inc. v. Braunstein

134 A.D.2d 55, 522 N.Y.S.2d 874, 1987 N.Y. App. Div. LEXIS 50866
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 28, 1987
StatusPublished
Cited by12 cases

This text of 134 A.D.2d 55 (Lieberman Properties Inc. v. Braunstein) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lieberman Properties Inc. v. Braunstein, 134 A.D.2d 55, 522 N.Y.S.2d 874, 1987 N.Y. App. Div. LEXIS 50866 (N.Y. Ct. App. 1987).

Opinion

OPINION OF THE COURT

Brown, J.

The plaintiff in this action as contract vendee, seeks specific performance of a contract for the sale of a portion of a parcel of real property which is the subject of a pending application [57]*57for subdivision approval. In its complaint, the plaintiff demands, inter alia, that the defendants be compelled to consent to and cooperate in the subdivision application process, and that they be directed to grant plaintiff and its agents access to the property in order to conduct inspections and tests required in connection with the application.

The record reveals that in November 1982 the defendants, the owners of an approximately 4.8-acre parcel of waterfront property in Kings Point, had a survey conducted for a potential subdivision of their property into four separate parcels. The property straddles East Shore Road and the survey divided the property into four parcels designated A, AA, B and BB, with parcels A and B lying on one side of the road and AA and BB lying on the other side. On December 14, 1982, the defendants contracted with the plaintiff’s assignor for the sale of parcels B and BB of the proposed subdivision. The contract provided that the sale was conditioned upon, among other things, the approval of the proposed subdivision by the Village of Kings Point and it called for a closing within 20 days following that approval. The contract also required defendants to give all necessary consents to enable the purchaser to conduct such tests as might be required in connection with the subdivision application.

At a meeting of the Village Planning Board (hereinafter the board) on January 25, 1983, the plaintiff was instructed by the board to obtain certain information and to perform certain tests relating to the existing cesspool and sanitary system. The board also indicated that it would only consider a subdivision of the property into two parcels and would insist that a restriction be placed upon further subdivision of either parcel.

While the defendants had initially cooperated in the application process, by mid-February 1983 they began to exhibit some dissatisfaction with the process and informed the plaintiff that the "closing date” of March 14, 1983 was approaching and that they wished to resolve the matter. Then by letter dated March 16, 1983, the defendants indicated to the plaintiff that, notwithstanding the "unsatisfactory” status of the subdivision application, they would still afford the plaintiff an opportunity to close, and that if the plaintiff was not willing to do so at that time, they would have no alternative but to declare the contract null and void.

In a letter dated March 29, 1983, the plaintiff’s counsel pointed out to the defendants’ counsel that nowhere in the [58]*58contract of sale was March 14, 1983 set as a closing date. He further stated that his client was taking all reasonable steps to obtain subdivision approval, but claimed that the defendants’ failure to give permission for the plaintiff’s agents to enter upon the property to obtain the information required by the board regarding the location of the cesspool was delaying the approval.

By letter dated April 1, 1983, the defendants declared the contract null and void. The plaintiff responded that it considered the contract to still be in full force and effect, that it intended to enforce its rights under the contract, and that if the defendants failed to cooperate, it would pursue whatever legal remedies were available. Evidence presented at the trial reveals that following their letter dated April 1, 1983, the defendants refused to allow the plaintiff’s agents access to the premises.

The plaintiff appeared before the board again on April 11, 1983, and informed that body that it had complied with all of the recommendations made by the board at the January 25, 1983 meeting, with the exception of locating the cesspool, and that it intended to take whatever legal steps were necessary to comply with the board’s conditions. The board, at that time, reaffirmed that it could not grant preliminary approval to the plaintiff unless it obtained information on the sanitary system and that it would not approve any application for a subdivision unless it received the covenants against further development of the property.

Thereafter, in May 1983, following a rejection of its demand for access to the premises, the plaintiff commenced the instant action.

Following a nonjury trial, the Supreme Court granted the plaintiff’s request for specific performance of the contract and directed the defendants to consent to the application for a subdivision, and, further, directed them to allow the plaintiff and its agents to enter upon the property to obtain necessary data and make necessary tests in connection with the application. In its memorandum decision, the court also specifically found that the contract of sale did not require that all proceedings before the board be completed within 90 days.

We agree with the Supreme Court that the plaintiff is entitled to judgment directing the defendants to perform their obligations under the contract of sale by continuing to give their consent to the application for subdivision approval and [59]*59by cooperating with the plaintiff and its agents in allowing access to the premises to collect data requested by the board in connection with the subdivision application. The agreement clearly requires that the defendants cooperate with the plaintiff in obtaining the necessary data for approval of the subdivision and the record supports the finding that the defendants failed to cooperate by not permitting the plaintiffs agents and the water department access to their property for the purpose of locating and testing the sanitary system. The failure to cooperate was a violation of the terms of the agreement and the plaintiff was entitled to enforcement of those provisions.

Similarly, we agree with the Supreme Court that the contract does not require that all proceedings before the board be completed within 90 days of the execution of the contract. Therefore, the plaintiffs failure to obtain the required approvals within 90 days did not void the contract and the defendants continued to be obligated thereunder.

Where we depart from the Supreme Court, however, is over the scope of the judgment granting specific performance and the direction that the defendants continue to consent to the subdivision approval process. Based upon the present record, the defendants could not be bound indefinitely to the contract and ultimately compelled to specifically perform. Rather, their obligation to cooperate and to perform can only be enforced for a reasonable period of time. Accordingly, the provisions of the judgment granting specific performance must be vacated.

It is fundamental that where a contract for the sale of real property fails to designate a closing date, the court will construe the contract to require that the closing be held within a reasonable time (Cohen v Kranz, 12 NY2d 242; N E. D. Holding Co. v McKinley, 246 NY 40; 1 Rasch, Real Property Law and Practice § 946; 62 NY Jur, Vendor and Purchaser, § 37). Indeed, even where the parties specify a particular date for closing, absent a provision that time is of the essence, the court will still allow the parties a reasonable time within which to perform their respective obligations under their contract (Grace v Nappa, 46 NY2d 560, 565, rearg denied 47 NY2d 952).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pappas v. B & G Holding Co.
2024 NY Slip Op 51218(U) (New York Supreme Court, Bronx County, 2024)
Israel v. Charnews
46 A.D.3d 753 (Appellate Division of the Supreme Court of New York, 2007)
ADC Orange, Inc. v. Coyote Acres, Inc.
20 A.D.3d 493 (Appellate Division of the Supreme Court of New York, 2005)
Ferguson v. Upper Chesapeake
Fourth Circuit, 1996
2m Realty Corp. v. Boehm
204 A.D.2d 620 (Appellate Division of the Supreme Court of New York, 1994)
Goewey v. Delta D & I Corp.
175 A.D.2d 299 (Appellate Division of the Supreme Court of New York, 1991)
Savino v. DeLeyer
160 A.D.2d 989 (Appellate Division of the Supreme Court of New York, 1990)
Lynlil Land Development Corp. v. Deluca
159 A.D.2d 695 (Appellate Division of the Supreme Court of New York, 1990)
W.W.W. Associates, Inc. v. Giancontieri
152 A.D.2d 333 (Appellate Division of the Supreme Court of New York, 1989)
S.J.E. Realty Corp. v. Lantz
154 A.D.2d 523 (Appellate Division of the Supreme Court of New York, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
134 A.D.2d 55, 522 N.Y.S.2d 874, 1987 N.Y. App. Div. LEXIS 50866, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lieberman-properties-inc-v-braunstein-nyappdiv-1987.