Lichter v. Goss

232 F.2d 715
CourtCourt of Appeals for the Seventh Circuit
DecidedMay 8, 1956
DocketNo. 11509
StatusPublished
Cited by22 cases

This text of 232 F.2d 715 (Lichter v. Goss) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lichter v. Goss, 232 F.2d 715 (7th Cir. 1956).

Opinion

SCHNACKENBERG, Circuit Judge.

Plaintiffs sued defendants to recover the reasonable value of work which plain[716]*716tiffs performed under a construction contract entered into with defendants, or, in the alternative, certain additional costs and damages incurred by them over and above the original contract price of $44,-000. Defendants filed an answer and a counterclaim. There was a trial by the district court, without a jury, following which the court entered findings of fact and conclusions of law and a judgment that the plaintiffs recover nothing and that defendants recover $1,069.67 and costs of the action against plaintiffs, from which plaintiffs have brought this appeal.

On August 25, 1944, defendants, as Contractor, entered into a contract with United States of America, as Owner, for construction of a group of buildings for the Veterans Administration at Perry Point, Maryland. On October 3, 1944, defendants, as Subcontractor, contracted with plaintiffs to construct interior hollow building tile and structural facing tile units. The contract of August 25, 1944, insofar as applicable, is incorporated into the contract of October 3, 1944. Defendants agreed to complete the prime contract within approximately 330 calendar days after receipt of notice to proceed, which notice was received on August 25, 1944.

Article IV of the contract of October 3, 1944 required plaintiffs to commence work immediately upon notice by defendants and that said work should be completed by April 1, 1945, unless delayed by acts of God, or causes beyond the control of the parties thereto, as defined, in article VIII (b) (c) of said agreement. The last mentioned provisions are as follows:

“(b) In the event that the Subcontractor shall claim to' háve sustained any damage by reason of delays, or for the performance of additional or different work, or for any other cause whatsoever, which claimed damage is or may be due to any act, omission, direction, or order of the Owner, the Subcontractor shall not have or assert any claim, or prosecute any suit, action or proceeding therefor against the Contractor, but provided that such claim is prepared by the Subcontractor in proper form for presentation to the Owner, so that said claim may be presented to the Owner in the manner and within the time specified in the principal contract, the Contractor agrees to present such claim to the Owner, either in his own name or in the name of the Subcontractor. The Contractor shall have the right to deduct from any sums recovered upon any such claim, all costs and disbursements, including legal fees and expenses incurred by the Contractor in the presentation, prosecution, and collection of such claim or claims,
“(c) In the event that the Subcontractor is delayed by the Contractor or any other Subcontractor in the progress of the work provided for in this contract, the Subcontractor shall be allowed one day extension of time for each calendar day that he has been so delayed, and no claim shall be made or allowed to the Subcontractor for damages which may arise out. of any delay caused by the Owner, unless the Contractor is allowed and compensated by the Owner for such delay or delays. In the event that the Contractor is compensated for delays caused by the Owner, then the Subcontractor shall be paid out of such amount so recovered, ■after deducting all legal expenses in making such recovery, for the days the Subcontractor was actually delayed in the ratio that the amount of the subcontract bears to the amount of the principal contract; provided that the period of delay for which the Subcontractor makes claim is within the period for which recovery for delays is made by the Contractor.”

The work was delayed and plaintiffs were not able to commence work by April 1, 1945. On May 18, 1945 defendants [717]*717notified plaintiffs that they should start no later than June 4, 1945, and plaintiffs agreed to do so. By July 6, 1945, plaintiffs did certain work in a store house covered by their contract. The contract price for this work was $1,850, being about 4 per cent of the total contract price of $44,000. Thereafter plaintiffs suspended operations because of delay in other phases of the construction. In March 1946 defendants called upon plaintiffs to perform their contract and the latter claimed that they were excused from performance due to the passage of time. On April 6, 1946, the parties entered into a supplemental agreement in which neither waived rights under the 1944 contract, but which provided for plaintiffs’ work to proceed. This supplemental agreement preserved the questions in controversy but did not in any way effect their solution.

Plaintiffs’ working crew returned to the job on April 8,1946. Plaintiffs’ work was completed in February 1947 and the entire contract was completed in April 1947, which was within the time of performance as extended from time to time by the Owner.

Defendants admit that delays occurred but they say that these delays were caused by the Owner or acts of God.

The district court’s findings are to the effect that the Owner estimated that a total quantity of 15,000 feet of piling with an average length of 21 feet for each pile would be required. The piling was ordered and the driving machine was equipped to handle piles up to 32 feet in length. When pile driving was commenced, the defendants and the Owner learned that the piles would have to be driven substantially deeper than 21 or 32 feet. Longer pile shells had to be ordered and a longer driving rig was required to handle the additional length. There was a delay in getting the additional piles and driving equipment. Eventually a total of 30,000 feet of piling, with an average pile length in excess of 40 feet, was required.

It was originally estimated that the pile driving would be completed in October of 1944 when the weather was favorable. Because of the 100 per cent underestimate by the Owner, pile driving carried over into the winter months when rain and snow filled the excavation, causing the banks to slough in, requiring continuous pumping of water out of the excavation and repeated hand re-excavation of the pile cap footings. The pile work was not completed until April 1945. The Owner granted defendants a four-month extension of time to perform the pile work. Testimony on this point is not in dispute. Continuing, the district court found that the delay was caused by an act of the Owner, without negligence or fault on the part of defendants. The district court further found that the piling had to be completed before work on the concrete foundations started. It is not disputed that the four-month period, April to July 1945, was the wettest such period in that area in 55 years and that pouring of foundations was seriously delayed. The rainy weather was of such character as to be considered an act of God and not a delay for which defendants were at fault.

The district court made the following findings in regard to the brick to be used: In November 1944, the defendants secured approval of grade M brick to be used in exterior walls; they ordered their requirements and some brick was actually delivered to the work site. In April 1945, the Owner rescinded its approval of that brick and requested that new samples be submitted. It is not disputed that this rescission arose because similar grade M brick had proved unsatisfactory in certain other buildings erected by the Owner, which had no connection with this case or these defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniel Hamm Drayage Co. v. Waldinger Corp.
508 F. Supp. 390 (E.D. Missouri, 1981)
Wheeler v. Wheeler
263 S.E.2d 763 (Supreme Court of North Carolina, 1980)
United States v. Walus
453 F. Supp. 699 (N.D. Illinois, 1978)
Horace Case v. Arthur E. Morrisette
475 F.2d 1300 (D.C. Circuit, 1973)
United States v. Idlewild Pharmacy, Inc.
308 F. Supp. 19 (E.D. Virginia, 1969)
Security Underground Storage, Inc. v. Anderson
347 F.2d 964 (Tenth Circuit, 1965)
Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (First Circuit, 1965)
B. C. Richter Contracting Co. v. Continental Casualty Co.
230 Cal. App. 2d 491 (California Court of Appeal, 1964)
Clarence Stanek v. Trailmobile, Inc.
283 F.2d 827 (Seventh Circuit, 1960)
Muntz, TV, Inc. v. Trav-Ler Radio Corp.
178 F. Supp. 623 (N.D. Illinois, 1959)
John William Wood v. Joe Reznik and Ralph C. Halbert
248 F.2d 549 (Seventh Circuit, 1957)
Lichter v. Goss
232 F.2d 715 (Seventh Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
232 F.2d 715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lichter-v-goss-ca7-1956.