Lichoulas v. Federal Energy Regulatory Commission

606 F.3d 769, 391 U.S. App. D.C. 1, 2010 U.S. App. LEXIS 10970, 2010 WL 2134283
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 28, 2010
Docket08-1373
StatusPublished
Cited by17 cases

This text of 606 F.3d 769 (Lichoulas v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lichoulas v. Federal Energy Regulatory Commission, 606 F.3d 769, 391 U.S. App. D.C. 1, 2010 U.S. App. LEXIS 10970, 2010 WL 2134283 (D.C. Cir. 2010).

Opinion

Opinion for the Court filed by Circuit Judge HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

James Lichoulas, Jr. petitions for review of Federal Energy Regulatory Commission (FERC or Commission) orders that terminate his license to operate a hydro-power project attached to a historic six-story mill building in Lowell, Massachusetts. Lichoulas argues that FERC’s use of the implied surrender doctrine to terminate his license was arbitrary and capricious. He also argues that FERC engaged in impermissible ex parte contacts and abused its discretion in denying him an evidentiary hearing. Unpersuaded, we deny the petition.

I.

In 1986 FERC issued Lichoulas a license “to construct, operate and maintain the Appleton Trust Project” (Project) under Part I of the Federal Power Act (FPA), 16 U.S.C. §§ 791 a et seq. James Lichoulas, Order Issuing License (Minor Project), 36 F.E.R.C. ¶ 62,047, 63,133, 1986 WL 373956 (July 18, 1986). The Project was designed to generate up to 346 kilowatts of electricity when water from the Hamilton Canal passes through two turbine-generators on its way to the Lower Pawtucket Canal.

In a letter to Lichoulas dated March 6, 1997 1 FERC noted that the Project had been inactive since January 6, 1996. It requested that he submit plans for future operation by May 15, 1997. In June 1997, before Lichoulas responded, a fire damaged the property on which the Project is located. Despite the damage, on September 22, 1997 Lichoulas told FERC the Project would be “up and running” near the end of March 1998. Letter from James T. Lichoulas, Jr., Appleton Trust, to Victoria Kaye, FERC. In a March 24, 1998 letter to FERC, however, Lichoulas pushed back the target date to Summer 1998.

FERC followed up on March 2, 1999, writing to Lichoulas that he had failed to keep the Commission updated and requesting that he do so before April 16, 1999. Receiving no response, FERC sent Lichoulas a letter on July 8, 1999 expressing “uncertainty” that he would ever resume operation. Letter from Hossein IIdari, Chief, Engineering Compliance Branch, FERC, to James Lichoulas at 1. It requested that Lichoulas submit within forty-five days either a plan for resuming operation or “a petition for the voluntary surrender” of his license. Id. Fifty-seven days later, on September 3, 1999, Lichoulas responded with an itemized repair plan and an estimated completion date of Feb *772 ruary or March 2000. FERC approved his plan on October 27,1999.

In October 2000, approximately seven months after Lichoulas’s estimated date of resumed operation, he arranged with the city of Lowell (City) to demolish several buildings on or adjacent to the Project property that posed a potential fire hazard. The demolition exposed asbestos, of which remediation began in August 2001.

FERC staff visited the Project on July 24, 2002 and saw its roof caved in and debris littering its works. They also learned that, while the Project had recently generated power “for a short time,” it “had to be shut down due to vibrations.” Letter from Anton J. Sidoti, Regional Engineer, FERC New York Regional Office, to James Lichoulas, Jr. at 1 (July 31, 2002). In a letter dated July 31, 2002 FERC requested that Lichoulas provide a repair schedule within ten days. Lichoulas made a progress report forty-seven days later, on September 16, 2002, stating that the Project would be operable by March 2003. But he soon revised his estimate to May 2003. In a March 17, 2003 letter FERC responded, “As you have been previously advised, failure to operate the project is a violation of the terms and conditions of your license.” Letter from Anton J. Sidoti, Regional Engineer, FERC New York Regional Office, to James Lichoulas, Jr., Appleton Trust. It told him to resume operation by May 30, 2003 and provide a status report to FERC by June 15, 2003.

In a letter dated September 5, 2003 FERC told Lichoulas he had failed to comply with its March mandates. It said he was in violation of section 10(c) of the FPA. See 16 U.S.C. § 803(c) (“licensee shall maintain the project works in a condition of repair adequate ... for the efficient operation of said works in the development and transmission of power”). Accordingly, it said, “the Commission may revoke your license or take other enforcement actions.” Letter from Hossein Ildari, Division of Hydropower Administration and Compliance, to James Lichoulas, Jr. at 2 (Sept. 5, 2003). It told Lichoulas he could stave off such action by filing “a plan and schedule for the resumption of project operation” within twenty-one days. Id. at 1. Lichoulas responded approximately six months later, telling FERC staff by telephone that he would submit a plan to resume operation by March 26, 2004. But FERC received no such plan and its subsequent telephone calls went unanswered and unreturned. Thus, on September 23, 2004, FERC told Lichoulas:

Since you have not made the necessary repairs to your project to resume operations and the project has not operated regularly since November 1994, pursuant to standard article 16 of your license and section 6.4 of the Commission’s regulations, we consider the project to be abandoned and that it is your intent to surrender your license. Thus, the Commission may terminate your license under an implied surrender proceeding.

Letter from John Estep, Division of Hydropower Administration and Compliance, to James Lichoulas, Jr. at 1.

Lichoulas responded in a letter dated December 1, 2004. He apologized for the “lack of proper response regarding the status” of the Project. Letter from James T. Lichoulas, Jr. to Secretary, FERC (Dec. 1, 2004). He said “[t]he primary problem was that the [Project property] ha[d] been undergoing a major selective demolition .... During that process, asbestos was discovered. The asbestos removal and clean up process went on and on for the last several years.” Id. He said it was his “plan to understand [sic] and develop a full scope of work by early March 2005.” Id. According to FERC, however, “Lichoulas *773 never submitted this information.” James Lichoulas Jr., Order Terminating License by Implied Surrender, 124 F.E.R.C. ¶ 61,-255, ¶ 12, 2008 WL 4279430 (Sept. 18, 2008) (Termination Order).

In July 2006 FERC received notice that in April 2006 the City had obtained the Project property by eminent domain as part of an “Urban Revitalization and Development Plan.” See Letter from Stephen Crane, Urban Renewal Project Manager, to Magalie Roman Salas, Secretary, FERC (July 20, 2006). According to the City, at the time of the taking the Project was not functioning; “in fact,” it said, “the entire property [wa]s in a significant state of disrepair.” Id.

On March 23, 2007 FERC issued Lichoulas a “Notice of Termination of License by Implied Surrender and Soliciting Comments, Protests, and Motions to Intervene.” Docket No. P9300-017 (Mar. 23, 2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LSP Transmission Holdings II v. FERC
28 F.4th 1285 (D.C. Circuit, 2022)
State v. Houkom
2021 ND 223 (North Dakota Supreme Court, 2021)
Hispanic Affairs Project v. R. Alexander Acosta
901 F.3d 378 (D.C. Circuit, 2018)
Damus v. Nielsen
District of Columbia, 2018
Damus v. Nielsen
313 F. Supp. 3d 317 (D.C. Circuit, 2018)
Abulhawa v. United States Department of the Treasury
239 F. Supp. 3d 24 (District of Columbia, 2017)
Hispanic Affairs Project v. Perez
District of Columbia, 2016
Allina Health Services v. Burwell
201 F. Supp. 3d 94 (District of Columbia, 2016)
Flaherty v. Pritzker
195 F. Supp. 3d 136 (District of Columbia, 2016)
Anglers Conservation Network v. Pritzker
139 F. Supp. 3d 102 (District of Columbia, 2015)
R.I.L-R v. Johnson
80 F. Supp. 3d 164 (District of Columbia, 2015)
Flaherty v. Bryson
850 F. Supp. 2d 38 (District of Columbia, 2012)
Lichoulas v. City of Lowell
937 N.E.2d 65 (Massachusetts Appeals Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
606 F.3d 769, 391 U.S. App. D.C. 1, 2010 U.S. App. LEXIS 10970, 2010 WL 2134283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lichoulas-v-federal-energy-regulatory-commission-cadc-2010.