Liberty Mutual Insurance v. Mandaree Public School District 36

459 F. Supp. 2d 866, 2006 U.S. Dist. LEXIS 77977
CourtDistrict Court, D. North Dakota
DecidedOctober 23, 2006
Docket2:06-cr-00056
StatusPublished
Cited by3 cases

This text of 459 F. Supp. 2d 866 (Liberty Mutual Insurance v. Mandaree Public School District 36) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty Mutual Insurance v. Mandaree Public School District 36, 459 F. Supp. 2d 866, 2006 U.S. Dist. LEXIS 77977 (D.N.D. 2006).

Opinion

ORDER DENYING DEFENDANT’S MOTION TO COMPEL ARBITRATION AND TO STAY THE LITIGATION

DANIEL L. HOVLAND, Chief Judge.

Before the Court is the Defendant’s Motion to Compel Arbitration and to Dismiss or Stay Litigation filed on September 22, 2006. For the reasons set forth below, the Motion to Compel Arbitration and the alternative Motion to Stay the Litigation are denied.

I. BACKGROUND

On July 17, 2006, the plaintiff, Liberty Mutual Insurance Company (Liberty Mutual), filed a complaint seeking declaratory judgment against the defendant, Mandaree Public School District # 36 (Mandaree). Liberty Mutual is a surety who issued a performance bond on a construction contract between Man-daree, the owner, and Tooz Construction, Inc. (Tooz Construction), the contractor. Liberty Mutual contends that Mandaree has discharged Liberty Mutual’s obligations under the performance bond by failing to give the required notice, undertaking repairs, and depleting the contract balance prior to allowing Liberty Mutual to investigate Mandaree’s claims *868 of default by Tooz Construction. On September 22, 2006, Mandaree filed a motion to compel arbitration and stay the litigation, arguing that Liberty Mutual is obligated to arbitrate its claim under the performance bond because the bond expressly incorporated a binding arbitration clause in the underlying construction contract. In the alternative, Mandaree contests that it is entitled to a discretionary stay of this lawsuit.

II. FACTS

On January 7, 2004, Mandaree entered into a construction contract with Tooz Construction for a school addition and remodeling project in the amount of $3,347,000. On January 16, 2004, Liberty Mutual, the surety, issued a performance bond for the project in the amount of $3,347,000. Paragraph 1 of the performance bond, executed using American Institute of Architects (AIA) document number A312, states:

The Contractor and the Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner for the performance of the Construction Contract, which is incorporated herein by reference.

See Docket No. 29-4. Paragraph 9 of the performance bond provides:

Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation to sureties as a defense in the jurisdiction of the suit shall be applicable.

See Docket No. 29-4.

The construction contract was executed using Abbreviated Standard Form AIA document number A107-1997, which incorporated the supplementary contract conditions contained in AIA document A201-1997. Section 6.2 of the A107-1997 document provides:

The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supei-sedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The contract Documents shall not he construed to create a contractual relationship of any kind (1) between the Architect and Contractor, (2) between the Owner and a Subcontractor or sub-subcontractor, (3) between the Owner and Architect or (4) betiueen any persons or entities other than the Owner and Contractor.

See Docket No. 29-2. Section 4.6 of AIA document A201-1997 provides the arbitration clauses, and section 4.6.1 states:

Any Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in Subparagraphs 4.3.10, 9.10.4 and 9.10.5, shall, after decision by the Architect or 30 days after submission of the Claim to the Architect, be subject to arbitration. Prior to arbitration, the parties shall endeavor to resolve disputes by mediation in accordance with the provisions of Paragraph 4.5.

See Docket No. 29-6. Section 4.6.4 of AIA document A201-1997 goes on to provide limitations on consolidation or joinder and states in pertinent part:

*869 No arbitration shall include, by consolidation or joinder or in any other manner, parties other than the Owner, Contractor, a separate contractor as described in Article 6 and other persons substantially involved in a common question of fact or law whose presence is required if complete relief is to be accorded in arbitration. No person or entity other than the Owner, Contractor or a separate contractor as described in Article 6 shall be included as an original third party or additional third party to an arbitration whose interest or responsibility is insubstantial. Consent to arbitration involving an additional person or entity shall not constitute consent to arbitration of a Claim not described therein or with a person or entity not name or described therein. The foregoing agreement to arbitrate and other agreements to arbitrate with an additional person or entity duly consented to by parties to the Agreement shall be specifically enforceable under applicable law in any court having jurisdiction thereof.

See Docket No. 29-6.

On November 4, 2005, Tooz Construction filed a demand for arbitration. Tooz Construction’s claim was for $470,424.62 allegedly owed by Mandaree for work done under the construction contract. See Docket No. 29-13. On December 16, 2005, Mandaree filed an answer and counterclaim and alleged numerous claims including breach of contract for defective construction, unjust enrichment, fraud, and negligent misrepresentation. On May 17, 2006, Mandaree notified the American Arbitration Association (AAA) and Tooz Construction of its intent to file an amended counterclaim “to assert all of its claims against Liberty Mutual ...” and add Liberty Mutual as a party to the arbitration. See Docket No. 33-3.

Mandaree asserts that Liberty Mutual first received notice on December 31, 2005, via a letter and a copy of Mandaree’s answer and counterclaim filed with the AAA. See Docket No. 29-11. On May 19, 2006, Mandaree sent a letter to Liberty Mutual declaring Tooz Construction in default and demanding that Liberty Mutual, as surety for Tooz Construction, meet its obligations under the performance bond. See Docket No. 29-11. Liberty Mutual contends that the May 19, 2006, letter was its first notice of Mandaree’s claims against Tooz Construction. See Docket No. 32.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schneider Elect. Build. Critical Systems v. Western Surety Co.
Court of Special Appeals of Maryland, 2016
Schneider Electric Buildings Critical Systems, Inc. v. Western Surety Co.
149 A.3d 778 (Court of Special Appeals of Maryland, 2016)
Filson v. RADIO ADVERTISING MARKETING PLAN, LLC.
553 F. Supp. 2d 1074 (D. Minnesota, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
459 F. Supp. 2d 866, 2006 U.S. Dist. LEXIS 77977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-mutual-insurance-v-mandaree-public-school-district-36-ndd-2006.