LH Land Painting Co., Inc. v. S & P CONSTRUCTION, INC.

516 S.W.2d 14, 1974 Tex. App. LEXIS 2736
CourtCourt of Appeals of Texas
DecidedNovember 1, 1974
Docket17551
StatusPublished
Cited by12 cases

This text of 516 S.W.2d 14 (LH Land Painting Co., Inc. v. S & P CONSTRUCTION, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LH Land Painting Co., Inc. v. S & P CONSTRUCTION, INC., 516 S.W.2d 14, 1974 Tex. App. LEXIS 2736 (Tex. Ct. App. 1974).

Opinion

OPINION

BREWSTER, Justice.

This is a suit for damages arising out of an alleged breach of guaranty that was contained in a building contract.

The plaintiff and appellee here, S & P Construction, Inc., contracted with Howell Instruments, Inc., to build a two-story building for the latter on some of its land in Fort Worth. S & P Construction, Inc., entered into a subcontract with the defendant and appellant here, L. H. Land Company, a corporation, by the terms of which the latter agreed to install complete a facade onto the north and west sides of the building to be made of wall panels of marble chips as was specified in the contract. The subcontractor in his contract guaranteed his work against all defects of materials and/or workmanship for a period of one year after the date of acceptance of his work by the owner.

Both before and after the subcontractor’s work was accepted by the owner the subcontractor was called on a number of times by the contractor, S & P Construction, Inc., to repair a number of leaks and alleged defects in the facade. On one occasion, after a heavy rain, a number of tbe panels on the facade fell off to the ground.

The plaintiff contractor sued in this case to collect the damages that it allegedly sustained as a result of a claimed breach of warranty or guaranty committed by the subcontractor when the subcontractor allegedly failed and refused to correct the claimed defects that existed in the facade that it had constructed.

The subcontractor, defendant here, alleged as a defense to plaintiff’s suit that while he was engaged in repairing and in replacing the defects in the facade an order was communicated to him by the contractor on January 26, 1971, to cease further replacement and repair of such defects, and that he was never thereafter instructed to continue the work and that the contractor then in March, 1971, told him to get his equipment off the premises and that this conduct by the contractor prevented and made it impossible for the subcontractor to further perform the guarantee.

*16 The law is that if one party to a contract is prevented by the acts of the other party to the contract from performing' such contract, then the party so prevented from performing is excused from further performance of the contract. His failure to perform under those circumstances cannot be made the basis of an action for damages for a breach of the Contract. See Atomic Fuel Extraction Corporation v. Slick’s Estate, 386 S.W.2d 180 (San Antonio Civ.App., 1964, writ ref. in 403 S.W.2d 784) and Cox v. KTM Drilling, Inc., 395 S.W.2d 851 (Amarillo Civ.App., 1965, ref., n. r. e.). And in Kirkwood & Morgan, Inc. v. Roach, 360 S.W.2d 173 (San Antonio Civ.App., 1962, ref., n. r. e.) the court held that if one party to a contract does not perform because of the express direction of the other party to such contract for him not to perform, then such failure to perform cannot thereafter be made the basis of an action for damages for the breach of such contract.

In submitting this particular defense to the jury the trial court submitted the following issue in its charge: “Issue No. 1: Do you find from a preponderance of the evidence that S & P Construction, Inc., prevented L. H. Land Painting Co. from promptly correcting the work on the Howell Instruments Building on the north and northwest facade which was rejected by the architect as defective? Answer, ‘We do’ or ‘We do not’.” The jury’s answer to the issue was “We do.”

In answer to the only other issue that was submitted the jury found that $19,000.-00 was the reasonable and necessary cost for the replacement of the facade.

After receiving the verdict the trial court proceeded to render judgment notwithstanding the verdict in favor of the contractor, S & P Construction, Inc., awarding it a recovery from the subcontractor, L. H. Land Painting Company, Inc., of the sum of $18,051.73.

In the judgment the trial court recited that he disregarded the jury’s finding in answer to Issue No. 1 because he was of the opinion that such answer was not supported by any sufficient evidence.

The subcontractor has here appealed from that decree.

The appellant’s point of error No. 2 is that the trial court erred in granting appel-lee’s motion for judgment non obstante ver-edicto and in denying appellant’s motion for judgment.

We sustain that point of error and reverse the judgment.

In passing on this point the question for our decision is whether there is evidence of probative force in the record which supports the jury’s answer to Special Issue No. 1.

The controlling law is stated in Harbin v. Seale, 461 S.W.2d 591 (Tex.Sup., 1970) as follows:

“The law is clear in this state that before a trial court can render a judgment non obstante veredicto, based on the absence of evidence, it must determine that there is no evidence having probative force upon which the jury could have made the findings relied upon. Whiteman v. Harris, 123 S.W.2d 699 (Tex.Civ.App.-Fort Worth 1938, writ ref’d). In making this determination, all evidence must be considered in a light most favorable to the party in whose favor the verdict has been rendered, and every reasonable inference deducible from the evidence is to be indulged in such party’s favor.”

The following cases make the same holding: Lynch v. Ricketts, 158 Tex. 487, 314 S.W.2d 273 (1958) and Alamo Ambulance Service, Inc. v. Moulton, 402 S.W.2d 200 (San Antonio Civ.App., 1966, affirmed in 414 S.W.2d 444).

A trial court cannot disregard a jury’s answer to an issue merely because the evidence is factually insufficient to support the same. Garza v. Alviar, 395 S.W.2d 821 (Tex.Sup., 1965) and Nash v. *17 Roden, 415 S.W.2d 251 (Austin Civ.App., 1967, ref., n. r. e.).

Some of the evidence in the record relating to the question inquired about in Tssue No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
516 S.W.2d 14, 1974 Tex. App. LEXIS 2736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lh-land-painting-co-inc-v-s-p-construction-inc-texapp-1974.