Leventhal v. Seiter

430 S.E.2d 378, 208 Ga. App. 158, 93 Fulton County D. Rep. 1277, 1993 Ga. App. LEXIS 475
CourtCourt of Appeals of Georgia
DecidedMarch 12, 1993
DocketA92A2333
StatusPublished
Cited by40 cases

This text of 430 S.E.2d 378 (Leventhal v. Seiter) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leventhal v. Seiter, 430 S.E.2d 378, 208 Ga. App. 158, 93 Fulton County D. Rep. 1277, 1993 Ga. App. LEXIS 475 (Ga. Ct. App. 1993).

Opinion

Blackburn, Judge.

The appellees, William and Kathleen Seiter, in July 1989, brought a breach of contract action against the appellant, Ronald Leventhal, seeking monetary damages and specific performance pursuant to the terms of three separate contracts for the sale of three different properties and improvements thereon. The appellant responded, asserting several defenses and counterclaims, including counterclaims for fraud and breach of contract. The case was tried by the trial court sitting without a jury, and on October 8, 1991, judgment was entered against the appellant in the amount of $65,610 principal and interest, $33,604 attorney fees, cost of the action and post-judgment interest. The appellant moved for new trial and to set *159 aside the judgment, both of which were subsequently denied by the trial court, and this appeal followed.

In the summer of 1988, the appellees, one of several builders of custom homes on lots in a subdivision that had been developed by the appellant, were contacted by the sales agent for the subdivision concerning the possibility of purchasing four remaining lots in the subdivision that the appellant had been unable to sell. The appellant needed to sell these lots to obtain working capital and to increase his cash flow. However, the appellees initially were not interested in purchasing these lots because the terrain of the lots was undesirable and they would be difficult to build upon. In addition, the appellees did not want to tie up their working capital in constructing speculative homes on these lots because the homes would be difficult to sell.

As a result of the appellees’ concern over the risks of purchasing these lots, the appellant suggested that the appellees design homes for these lots, supervise the construction of the homes, and the appellant would pay them $4,000 for their efforts. The appellant further indicated that he would obtain construction loans on the properties and bear the responsibility for all costs and expenses. This arrangement was suitable to the appellees, but the appellant was unable to obtain a construction loan from the bank. Thereafter, the appellees indicated that, in order for them to obtain a construction loan on the three lots, the appellant would have to agree to purchase the property for a certain amount to decrease the risk of the venture. A representative of Smyrna Bank & Trust (“the bank”), was consulted about this arrangement, and was willing to allow the appellees to borrow the money because of the appellees’ good track record. The bank, however, conditioned the loan on the appellant’s execution of contracts in favor of the appellees for the purchase of the properties in the event that the appellees were unable to sell the homes within a certain period of time.

Pursuant to this agreement between the parties, the appellees designed plans for the construction of homes on each of the three properties. On behalf of the appellant, the sales agent for the subdivision approved the home designs and approved the proposed cash prices for the homes of $117,000 for lot #1, $115,500 for lot #14, and 114,500 for lot #29 in cash on behalf of the appellant. The prices of the homes included the cost of the lots. Afterwards, the appellees applied for a construction loan to buy the three lots and build homes upon them. Based upon the agreement that the appellant would purchase each of the properties in the event that they were not sold to third parties, the bank agreed to loan the appellees in excess of $287,000 for the construction of homes on each of the three properties. An attorney for the bank prepared the three contracts evidencing the agreement between the parties that the appellant would purchase *160 lot #1 for $117,000, lot #14 for $115,500, and lot #29 for 114,500 in cash, before May 15, 1989, if any of the homes had not been purchased by third parties by that date.

The contract contained a clause which provided that if any of the properties were sold by either party at a price that would net the seller an amount equal to or greater than the sales price under the agreement, the contract between the appellant and the appellees would become a nullity, ending all obligations to the appellees and the appellant under original contract for any lot which was so sold. This clause was later amended in writing by the parties on October 21, 1988, and provided that if any third party sale netted to the seller an amount in excess of the agreed upon sales price, the appellees and the appellant would split the profits equally. The original contract also contained a merger clause, which provided that the agreement “constitute [d] the entire agreement between the parties and no modifications, representations, inducements, promises or agreements . . . not embodied herein shall be of any force or effect.”

On October 14, 1988, at the closing of the construction loan, the bank executed quitclaim deeds on each of the properties in favor of the appellant, releasing and conveying to the appellant, all of the bank’s rights, title and interest in each of the lots. The appellees purchased the three lots in question from the appellant, and paid the appellant $64,500, $21,500 for each lot, out of the loan receipts that the appellees simultaneously received from the bank for the purpose of constructing new homes on the three lots. Thereafter, the appellant executed a warranty deed on each of the three lots in favor of the appellees. The appellees subsequently built homes on each of the three lots. Although the homes were marketed by the sales agent of the subdivision and a private realtor, the appellees were unable to sell any of the three properties before May 1989.

On May 15, 1989, pursuant to the terms of the contracts between the parties, the appellees demanded that the appellant purchase the homes at the contract prices and the appellant refused. In a letter of that same date, the appellant, through counsel, indicated that the contracts did not reflect all of the terms and agreements of the parties because the agreed upon purchase price was $4,000 above the cost incurred by the appellees in building the homes. The appellant further demanded that the appellees convey title to the properties for the sum of $4,000 plus costs. On May 16, 1989, the appellees responded, stating that the contract terms were entirely reflected in the agreement. As a result of the appellant’s failure to comply with the terms of the contract, this action ensued. The properties in question and the homes thereon were subsequently purchased by third parties for less than the price contained in each of the contracts after the commencement of this action.

*161 1. In his first enumeration of error, the appellant contends that the trial court erred in refusing to grant further discovery pursuant to his motion to compel. We disagree.

This action was filed on July 5, 1989, and pursuant to a consent order that had been entered into between the parties on February 19, 1990, the time period for discovery had been extended through June 1, 1990. The appellant requested that the court compel responses to his interrogatories and request for production of documents on September 10, 1991, over a year after the discovery deadline had expired.

“ ‘Under the discovery provisions of the Civil Practice Act, the trial judge is granted broad discretion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christina Marie Heyman v. John Russell Heyman
Court of Appeals of Georgia, 2025
Willesen v. Ernest Communications, Inc.
746 S.E.2d 755 (Court of Appeals of Georgia, 2013)
Freese II, Inc. v. Lisa Mitchell
Court of Appeals of Georgia, 2012
Freese II, Inc. v. Mitchell
734 S.E.2d 491 (Court of Appeals of Georgia, 2012)
Higginbotham v. Knight
719 S.E.2d 1 (Court of Appeals of Georgia, 2011)
In the Interest of T. S.
686 S.E.2d 402 (Court of Appeals of Georgia, 2009)
In Re TS
686 S.E.2d 402 (Court of Appeals of Georgia, 2009)
General Electric Capital Corp. v. Nucor Drilling, Inc.
551 F. Supp. 2d 1375 (M.D. Georgia, 2008)
Calabro v. State Medical Education Board
640 S.E.2d 581 (Court of Appeals of Georgia, 2006)
Dempsey v. Kaminski Jewelry, Inc.
630 S.E.2d 77 (Court of Appeals of Georgia, 2006)
Flowers v. Union Carbide Corp.
610 S.E.2d 109 (Court of Appeals of Georgia, 2005)
Gill v. Spivey
592 S.E.2d 132 (Court of Appeals of Georgia, 2003)
Gerrard v. A.J. Gerrard & Co.
285 F. Supp. 2d 1331 (S.D. Georgia, 2003)
Byelick v. Michel Herbelin U.S.A., Inc.
578 S.E.2d 907 (Court of Appeals of Georgia, 2003)
Lott v. Arrington & Hollowell, P.C.
572 S.E.2d 664 (Court of Appeals of Georgia, 2002)
Yang v. Washington
568 S.E.2d 140 (Court of Appeals of Georgia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
430 S.E.2d 378, 208 Ga. App. 158, 93 Fulton County D. Rep. 1277, 1993 Ga. App. LEXIS 475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leventhal-v-seiter-gactapp-1993.