LeVangie v. Raleigh

2019 Ohio 810
CourtOhio Court of Appeals
DecidedMarch 8, 2019
Docket27946
StatusPublished
Cited by5 cases

This text of 2019 Ohio 810 (LeVangie v. Raleigh) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeVangie v. Raleigh, 2019 Ohio 810 (Ohio Ct. App. 2019).

Opinion

[Cite as LeVangie v. Raleigh, 2019-Ohio-810.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY

MICHAEL E. LEVANGIE, MANAGING : MEMBER : : Appellate Case No. 27946 Plaintiff-Appellee : : Trial Court Case No. 2016-CV-6116 v. : : (Civil Appeal from LINDA K. RALEIGH, et al. : Common Pleas Court) : Defendant-Appellant :

...........

OPINION

Rendered on the 8th day of March, 2019.

JOHN E. SHARTS, Atty. Reg. No. 0006905, 5 Fairway Drive, Springboro, Ohio 45066 Attorney for Plaintiff-Appellee

THOMAS W. KENDO, JR., Atty. Reg. No. 0058548 and GABRIELLE R. NEAL, Atty. Reg. No. 0092770, 7925 Paragon Road, Centerville, Ohio 45459 Attorneys for Defendant-Appellant

.............

TUCKER, J. -2-

{¶ 1} Defendant-appellant Linda Raleigh appeals from a judgment of the

Montgomery County Court of Common Pleas awarding damages to plaintiff-appellee

Michael LeVangie. For the reasons that follow, we affirm in part, reverse in part, and

remand for further proceedings.

I. Facts and Course of the Proceedings

{¶ 2} LeVangie is a general contractor and managing member of LeVangie

Construction, LLC. Linda Raleigh is the owner of a duplex housing unit located on Eby

Road in Germantown. In February 2014, a fire destroyed one of the duplex units and

caused serious damage to the other unit. Raleigh carried a policy of insurance on the

structure, and the insurance company gave her $177,897.39 to rebuild the structure.

{¶ 3} On November 14, 2014, Raleigh and LeVangie executed a contract to repair

and rebuild the duplex. The contract, which consisted of a handwritten page signed by

Raleigh and LeVangie, provided:

It is agreed to perform and complete all repairs required to complete

insurance all repairs on fire job at 10436 Eby Rd. and 10440. All materials

and labor will be supplied and installed according to codes compliance. A

reliese [sic] of lein [sic] will be furnished upon completion and final payment

and duly notarized. Total $177,647.34.1

1 LeVangie introduced into evidence another handwritten page that he claimed was part of the contract agreed to by Raleigh. The page was entitled “Scope of Work,” and set forth descriptions of the work to be performed. Raleigh denied seeing this page. The page was not signed by Raleigh and was on a different letterhead than the other page of the contract. It is clear that the trial court did not consider this page to be part of the -3-

{¶ 4} After the contract was signed, LeVangie began working to remove the burned

debris from the site. On December 9, 2014, LeVangie applied for a damage assessment

building permit and an electrical permit. Both permits were issued, and a damage

assessment was conducted by the Montgomery County Building Department on

December 10, 2014. That same day, the inspector issued a report which noted that

LeVangie would need to obtain electrical, mechanical, gas piping, plumbing and building

permits. The report also stated that LeVangie was required to submit construction

drawings in order to obtain a building permit.

{¶ 5} LeVangie began construction without obtaining a building permit. On

January 8, 2015, Raleigh disbursed approximately $52,520 to LeVangie.2 In May or

June 2015, LeVangie asked Raleigh for another disbursement of funds, but she did not

make any further disbursements.3

{¶ 6} LeVangie filed an application for a building permit on August 7, 2015.

LeVangie stopped work on August 15 because of Raleigh’s failure to make a further

monetary disbursement and, additionally, because a building permit had not been issued.

On September 8, 2015, the Montgomery County Building Regulations Division issued a

letter to LeVangie indicating six issues that needed to be addressed prior to issuance of

a building permit. The letter further indicated that review of the permit was suspended

contract.

2 From that disbursement, LeVangie issued a check to Raleigh in the sum of $10,000 in exchange for which Raleigh agreed to perform upkeep, such as mowing, of the premises.

3 According to Raleigh, she asked LeVangie to submit receipts for the work and materials prior to getting an additional disbursement. She testified that she never received the requested documentation. -4-

pending the submission of further information.

{¶ 7} On November 13, 2015, Raleigh sent a letter to LeVangie terminating his

services. Raleigh’s son and ex-husband hired an architect to draw plans for the project.

They then applied for a building permit which was issued on December 8, 2015. The

project was completed by Raleigh’s son and ex-husband. On December 17, 2015,

LeVangie filed a mechanic’s lien against the property.

{¶ 8} LeVangie filed a complaint for breach of contract and marshalling of liens on

December 2, 2016. Raleigh filed an answer and a counterclaim. In her counterclaim,

she asserted causes of action for breach of contract, negligence, unjust enrichment,

slander of title and fraud.

{¶ 9} A trial was conducted in October 2017, after which the trial court awarded

LeVangie $34,997.64. Raleigh filed a request for findings of fact and conclusions of law,

which were rendered on February 7, 2018. The trial court found that the parties had

entered into an express contract and that LeVangie had materially breached the contract

and, thus, was not entitled to recover under the contract. Specifically, the trial court

found that LeVangie failed to construct the house in a workmanlike manner according to

applicable building codes and that he began construction without obtaining a permit. The

trial court further found that the unrebutted evidence demonstrated that LeVangie’s work

had significant defects that had to be remedied by Raleigh’s ex-husband and son.

{¶ 10} However, the trial court went on to conclude that it believed it was

“appropriate under these circumstances to award [LeVangie] an amount for unjust

enrichment or quantum meruit. Since [LeVangie] cannot recover under the contract

because of his substantial breaches, he has, however, conferred a substantial benefit -5-

upon [Raleigh] for which he should be compensated.”4 Dkt. # 41, p. 3. The trial court

found that LeVangie had expended approximately $88,497 in labor and materials, and

thus, he should receive the difference between that amount and the $53,520 paid to him

by Raleigh, or $34,977.

{¶ 11} With respect to Raleigh’s counterclaims, the trial court found that Raleigh

had not proven her claims for breach of contract, negligence, unjust enrichment, slander

of title, or fraud. With respect to the breach of contract specifically, the court’s conclusion

was based on the evidence that, although LeVangie had breached the contract, Raleigh

had not proven any damages.

{¶ 12} On February 20, 2018, the trial court entered a “Judgment Entry and Decree

of Foreclosure,” which stated that the property would be foreclosed if Raleigh did not pay

the amount owed to LeVangie within 5 days.

{¶ 13} Raleigh appeals.

II. Unjust Enrichment

{¶ 14} Raleigh’s first assignment of error states as follows:

THE TRIAL COURT ERRED IN AWARDING PLAINTIFF DAMAGES

UNDER A THEORY OF UNJUST ENRICHMENT.

{¶ 15} Raleigh contends that a party cannot recover damages under a theory of

unjust enrichment for services that were provided for by an express contract. LeVangie

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Fukuvi USA Inc.
2022 Ohio 1608 (Ohio Court of Appeals, 2022)
Sullinger v. Sullinger
2020 Ohio 5225 (Ohio Court of Appeals, 2020)
Jochum v. State ex rel. Mentor
2020 Ohio 4191 (Ohio Court of Appeals, 2020)
John D. Smith Co., LPA v. Lipsky
2020 Ohio 3985 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levangie-v-raleigh-ohioctapp-2019.